1浙江大唐乌沙山发电有限责任公司废水处理区域围栏改造工程施工组织设计2目录第一章编制依据··································3第二章工程概况··································3第三章施工准备··································33.1技术准备···································33.2材料和构件准备································33.3施工人员准备·································4第四章施工工艺和技术措施·····························44.1施工流程···································44.2埋件埋设···································44.3栏杆立柱、水平钢管安装····························54.4扶手找位与划线································54.5扶手弯头配制··································54.6扶手连接预装·························错误!未定义书签。4.7扶手固定···································54.8整修·····························错误!未定义书签。4.9表面刷漆···························错误!未定义书签。第五章质量保证··································65.1质量标准···································65.2应注意的质量问题·······························6第六章成品保护··································7附件1:图集06J403-1第24页····························8附件2:图集06J403-1第75页····························9附件3:图集06J403-1第77页···························10附件4:图集06J403-1第78页···························11附件5:图集06J403-1第161页···························123第一章编制依据1、《建筑工程施工质量验收统一标准》(GB50300-2001);2、《人民防空工程施工及验收规范》(GB50134-2004)3、《建设工程施工现场供用电安全规范》(GB50194-93)4、《施工现场临时用电安全技术规范》(JGJ46-2005)5、《建筑装饰装修工程质量验收规范》(GB50210-2001)6、《工程建设标准强制性条文-房屋建筑部分》2002年版;第二章工程概况1.建设单位:浙江大唐乌沙山发电有限责任公司2.工程名称:浙江大唐乌沙山发电有限责任公司废水处理区域围栏改造工程3.建设地点:浙江省象山县西周镇工程概况:工业废水贮存池(含经常性和非经常性废水贮存池)上部围栏(含门)及踢脚板,工业废水贮存池上下爬梯,翻越管道用的楼梯平台等。脱硫废水贮存池上部围栏、爬梯、扶手等。工业废水处理加药箱所属楼梯、平台、扶手等。本工程包括拆除原有围栏(含门)及返库工作;立柱间距按照原系统间距进行,焊接在原预埋铁上。改造中所破坏及损伤的地面及其他建筑构造,必须由施工方负责完善;施工完成后需将围栏与预埋铁连接部位进行水泥密封及抹面。第三章施工准备3.1技术准备施工前应熟悉图纸、设计变更、图集相关要求,了解相关安全、质量规范,了解掌握栏杆、扶手的施工工艺,找出施工中安全质量施工注意点,做到施工中重点突出、心中有数。编制施工方案用以指导施工,逐级进行技术交底。3.2材料和构件准备3.2.1材料准备1、不锈钢扶手加工成规格成品,其品种、规格、尺寸、形状按设计要求。不锈钢质4量均应颜色一致,不得有锈迹、裂缝、扭曲等缺陷;不锈钢扶手按设计要求备弯头料。2、其他材料:砂纸、加工配件。3.2.2机具准备1、电动机具:磨光机、切割机、小台锯、氩弧焊机。2、手动工具:钢挫、方尺、割角尺、卡子等。3.2.3作业条件1、金属栏杆或靠墙扶手的固定埋件安装完毕。3.3施工人员准备1、施工人员必须熟悉相关规范、图集的要求及栏杆、扶手安装工艺要求。施工前进行详细技术交底和专业培训。2、坚持特殊工种持证上岗制度,并于施工前进行教育培训。3、实行三级交底制度,即:技术部对项目部相关管理人员和分包技术人员进行方案交底;工程部对分包工长、班组长进行交底;分包工长、班组长对栏杆扶手施工工人进行技术交底。第四章施工工艺和技术措施4.1施工流程(1)不靠墙栏杆扶手埋件埋设→栏杆立柱安装→扶手找位与划线→扶手弯头配制→扶手连接预装→扶手固定→扶手整修→栏杆立柱、扶手表面抛光。(2)靠墙栏杆扶手埋件埋设→水平钢管安装→扶手找位与划线→扶手弯头配制→扶手连接预装→扶手固定→扶手整修→栏杆立柱、扶手表面抛光。4.2埋件埋设(1)不靠墙楼梯栏杆下部连接须在每个踏步上埋设埋件,由于现场埋设埋件。故须在每个踏步上按照图集06J403-1类型要求进行埋件定位,预埋件详图见下图。(2)靠墙5扶手埋件间距按照设计要求不大于1200mm进行定位,由于结构、砌筑墙已经施工完成,并未埋设埋件。当预埋件位置在混凝土结构上时,采用膨胀螺栓锚入结构中,预埋件具体要求如(1)所述;当预埋件位置在砌筑墙上时,须从砌筑墙掏出砌块,安装好埋件,埋件按设计指定图集选用,再用C25混凝土进行浇筑,并振捣密实。3、锚板采用6mm厚钢板,如上图进行开孔加工。4.3栏杆立柱、水平不锈钢管安装1、栏杆立柱安装(1)栏杆立柱选用按图纸及图集选用;(2)埋件埋设完成后,在各个埋件上对栏杆立柱进行划线定位,立柱中心距边缘不小于50mm;(3)立柱高度按照工程设计、图集要求先加工好,立柱与锚板焊接时须保证立柱的垂直度;2、靠墙扶手水平不锈钢管安装(1)靠墙扶手水平不锈钢管采用应符合图纸及图集要求;(2)埋件埋设完成后,在各个埋件上对扶手水平钢管进行划线定位;(3)水平钢管伸出长度须满足扶手安装要求。4.4扶手找位与划线1、安装扶手的固定件:位置、标高、坡度找位校正后,弹出扶手纵向中心线。2、设计扶手构造,根据折弯位置、角度,划出折弯或割角线。3、在楼梯栏杆顶面,划出扶手直线段与弯头、折弯段的起点和终点的位置。4.5扶手弯头配制1、按栏杆顶面的斜度,配好起步弯头。2、整体弯头制作:不锈钢成品弯头。4.6扶手固定分段预装检查无误,进行扶手与栏杆上固定件,用氩弧焊焊接固定。6第五章质量保证5.1质量标准5.1.1一般要求(1)有构件下料应保证准确,构件长度允许偏差为1mm。(2)构件制作时保证项目:规格尺寸正确,表面光滑,线条顺直,曲线面弧顺,楞角方正,无戗槎、刨痕、锤印等缺陷。(3)构件安装时保证项目:位置正确,割角线准确、整齐,接缝严密、坡度一致,粘结牢固、通顺,螺帽平正,出墙尺寸一致。(4)硬木扶手选型、材质形状、尺寸应符合设计要求。(5)安装固定扶手的预埋件必须牢固,无松动现象,木扶手入墙处应做防腐处理。(6)构件焊接时构件必须放置的位置准确,焊接时构件之间的焊点应牢固,焊缝应饱满,焊缝表面的焊波应均匀,不得有咬边、未焊满、裂纹、渣滓、焊瘤、烧穿、电弧擦伤、弧坑和针状气孔等缺陷焊接完成后,应将焊渣敲净,构件焊接组装完成后,应适当用手持机具磨平和抛光,使外观平顺光洁。5.1.2强制性要求(1)楼梯段(坡段)栏杆高度不小于0.9m。(2)转角处栏杆高度不小于0.9m。(3)最高楼层的楼梯水平段临空处栏杆离地面0.10m高度内不应留空,且栏杆高度为不小于1.2m。注:上述栏杆高度指地面完成面至扶手最高点的距离。5.2应注意的质量问题1、尺寸超出允许偏差:对焊缝长宽、宽度、厚度不足,中心线偏移,弯折等偏差,应严格控制焊接部位的相对位置尺寸,合格后方准焊接,焊接时精心操作。允许偏差项目见表一。表一:楼梯扶手安装允许偏差项目允许偏差(mm)检查方法栏杆(板)垂直3吊线尺量检查7栏杆间距3尺量检查扶手直线度4拉通线尺量检查扶手高度3尺量检查2、焊缝裂纹:为防止裂纹产生,应选择适合的焊接工艺参数和焊接程序,避免用大电流,不要突然熄火,焊缝接头应搭接10~15mm,焊接中不允许搬动、敲击焊件。3、表面气孔:焊接部位必须刷洗干净,焊接过程中选择适当的焊接电流,降低焊接速度,使熔池中的气体完全逸出。第六章成品保护1、安装扶手时,应保护楼梯栏杆、楼梯踏步和操作范围内己施工完成的项目。2、木扶手安装完毕后,宜刷一道底漆,并应加包裹,以免撞击损坏和受潮变色。3、扶手安装后应及时包裹保护。8附件1:图集06J403-1第24页9附件2:图集06J403-1第75页10附件3:图集06J403-1第77页11附件4:图集06J403-1第78页12附件5:图集06J403-1第161页