1亨氏(中国)佛山一期婴幼儿米粉项目钢结构安装工程施工组织设计四川省第六建筑有限公司二○一三年八月十日1目录第一章施工总体部署·······················11.1编制依据·························································································11.2适用范围·························································································11.3工程施工总体目标··············································································11.4.工程概况·························································································21.5.施工组织机构···················································································3第二章工期施工进度及保证措施··················52.1.工期进度计划表················································································52.2.雨季施工工作安排及措施··································································52.3.工期保证措施···················································································62.4.进度保证承诺·················································································8第三章施工主要机械设备的配置·················10第四章施工平面布置和临时设施布置···············10第五章控制质量的施工措施···················145.1.钢结构安装····················································································14第六章关键施工技术、工艺及工程项目实施的重点、难点分析和解决方案156.1.高强螺栓的保管··············································································156.2.螺栓的安装工艺··············································································166.3.屋面围护系统安装的技术措施及解决方案·············································17第七章合同管理及竣工验收资料的编制··············187.1.合同管理·······················································································187.2.竣工资料的编写和管理·····································································19第八章安全文明方案-措施····················198.1.安全生产管理体系···········································································198.1.1.总经理(项目安全第一责任人)职责················································198.1.2.总工(副经理)(项目安全生产直接责任人)职责······························228.1.3.安全总监的职责···········································································228.1.4.施工工长的职责···········································································238.2.现场施工安全管理···········································································238.2.1施工现场安全生产交底································································238.2.2.现场安全生产技术措施··································································2528.3.安全保障设施·················································································268.3.1.现场安全用电··············································································268.3.2.现场防火及暴雨、水灾、地震之措施················································268.3.3.现场防雷击措施···········································································278.4.文明施工保证措施···········································································278.4.1.文明施工管理细则········································································278.4.2文明施工检查措施·········································································29第九章质量保证控制措施····················299.1质量管理体系及管理制度···································································309.2.安装过程检测·················································································409.4.现场安装质量保证措施·····································································469.5.现场涂装的质量保证措施··································································55第十章附表(图)·······················561第一章施工总体部署1.1编制依据以亨氏(中国)佛山市一期婴幼儿米粉项目钢结构工程设计图纸为依据,结合本公司的深化设计进行编制。1.2适用范围仅适用于亨氏(中国)佛山市一期婴幼儿米粉项目钢结构工程的钢结构安装及屋面工程。1.3工程施工总体目标工程施工的基本思路主要包括工程管理与工程施工两方面,工程管理上以“顾全大局、职责分明、发挥强项、统一协调”为指导思想;工程施工上,对于钢柱、钢梁等其它类似加工件则以“材料进场、现场堆放、单件安装”为原则进行施工,在整个工程施工过程中,本公司将充分发挥技术与设备的优势,以统一的专业化管理,精湛的施工技术,确保工程优良的品质,让业主满意,让业主放心。1.3.1.质量目标确保工程质量达到国家合格标准要求。1.3.2.工期目标本项目工期计划为100日历天,在该工期内完成所有分部分项工作(设计、制作、安装),安装工期为100天,从现场具备主钢架进场安装条件的日期算起。1.3.3.安全目标确保工程、设备安全,施工人员重伤、死亡事故为零指标。1.3.4.文明施工目标按规范化、标准化进行现场管理,确保文明施工。1.3.5.服务目标本公司将本着用户至上的原则,精心组织施工,用汗水和智慧赢得业主的信2任。1.4.工程概况1.4.1.工程简述1、项目名称:亨氏(中国)佛山市一期婴幼儿米粉项目钢结构工程2、项目地点:广东省佛山市三水区西南开发区3、建设单位:亨氏联合有限公司4、设计单位:中国轻工业广州有限公司5、监理单位:广东建设工程监理有限公司6、施工单位:四川省第六建筑有限公司7、工程简况:亨氏(中国)佛山市一期婴儿米粉项目钢结构工程,主钢结构采用门式轻型钢结构建筑体系;宽度1/O1-17轴为118米,长度A-Q轴为128米;主钢结构采用门式轻型钢结构建筑体系;屋面为单屋脊双坡屋面;厂房为单层钢结构,局部有二层、三层结构,厂房屋面围护系统采用轻型原色钢板围护,外面墙面采用压型钢板进行围护。在每一个分部工程施工的同时同步备好有关质保等技术资料,积极配合施工方面,及时做好竣工验收工作。7.1.编制原则1、确保质量。实行全面质量管理,实行技术、质量包保责任制,确保工程质量达到验评标准。2、保证工期。优化施工组织设计,利用先进的施工方法,精干的施工队伍,精心组织,科学施工,确保工程按时完工,争取略有提前。3、确保安全。推行安全目标责任制,制定安全保证措施,严格按安全规程操作,杜绝安全事故的发生。4、突出重点,统筹安排,组织连续,均衡而紧凑的施工生产。重点把握影响质量和工期的重点、难点工程,保证工期、质量及安全目标的实现。7.2.施工中执行的技术标准、规程、规范1.设计图纸及设计说明文件2.《钢结构工程施工质量验收规范》(GB50205-2001)3.《建筑钢结构焊接技术规程》(JGJ81-2002)4.《门式刚架轻型房屋钢结构技术规程》(CECS102:2002)35.《结构工程质量检测评定标准》(GB50221-95)6.《钢结构高强度螺栓连接的设计、施工及验收规程》(JGJ82-91)7.《建筑工程施工质量验收统一标准》(GB50300-2001)8.《压型金属板设计施工规程》(YBJ216-88)9.《涂装前钢材表面锈蚀等级和除锈等级》(GB8923-88)10.《屋面工程质量验收规范》(GB50207-2002)11.《建筑工程施工现场供用电安全规范》(GB50194-93)12.《建筑机械使用安全技术规程》(JGJ33-86)13.《施工现场临时用电安全技术规程》(JGJ46-88)14.《建筑施工高处作业安全技术规范》(JGJ80-91)1.5.施工组织机构项目管理组织机构图1.5.1.与各单位的配合1.5.1.1.与监理的配合⑴将正式施工组织设计报送监理工程师审定。⑵各类检测设备和重要机电设备的进场情况向监理申报。⑶施工用各类主要材料均向监理报送材质证明等有关技术资料。4⑷工程隐蔽前,在检查合