海富山水文园二期(二)C13#楼混凝土灌注桩施工记录建设单位:黑龙江海富永业房地产开发有限公司设计单位:黑龙江省西埃迪建筑设计院监理单位:黑龙江淸宇建设工程监理有限责任公司施工单位:黑龙江省百竣建筑工程有限责任公司混凝土灌注桩施工记录工程名称海富山水文园二期(二)C13#施工单位百竣建筑工程有限责任公司成孔工艺干作业螺旋钻孔灌注桩机械类型JZB-60桩位编号成孔混凝土浇筑成孔时间日/月.时.分孔径(㎜)孔深(m)虚土或沉渣厚(㎜)自然地面标高(m)孔底标高(m)孔倾斜值(㎜)泥浆种类护壁泥浆清孔泥浆比重护筒埋深(㎜)浇筑时间日/月.时.分桩顶标高(m)砼体积(m3)砼充盈系数比重含砂率胶体率设计实测设计实测设计实测计算实注1129.26400405212130-2.45-23.42359.26-2.75-2.752.702.851.06599.26400408212150-2.46-23.41429.26-2.75-2.752.742.901.06479.26400410212140-2.48-23.52199.26-2.75-2.752.772.971.071089.26400408212150-2.47-23.42529.26-2.75-2.752.742.861.041119.26400405212120-2.45-23.43199.26-2.75-2.752.702.801.041159.26400409212130-2.46-23.43529.26-2.75-2.752.762.891.051179.26400410212160-2.48-23.42149.26-2.75-2.752.772.901.05609.26400410212140-2.47-23.43409.26-2.75-2.752.772.881.04629.26400406212150-2.45-23.40389.26-2.75-2.752.722.821.041319.26400403212130-2.46-23.43499.26-2.75-2.752.682.791.04589.26400410212170-2.48-23.41129.26-2.75-2.752.772.911.05489.26400408212160-2.47-23.41519.26-2.75-2.752.742.871.05509.26400412212180-2.45-23.37619.26-2.75-2.752.802.991.07监理工程师施工技术施工主要操作(建设单位代表):负责人:质检员:人员:记录人:注:1、本表适用于干成孔、泥浆护壁桩,所列项目根据工艺和设备具体要求填写;2、孔底标高=自然地面标高(孔上部周围地面实测标高)-孔实钻深度+虚土或沉渣厚度。3.砼浇筑计算体积=πD2×(桩顶标高实测值-孔底标高)÷4;D—孔径实测值(直径不同时可分段计算)4、孔底标高为虚土或沉渣处理后,灌注混凝土前实测标高。混凝土灌注桩施工记录工程名称海富山水文园二期(二)C13#施工单位百竣建筑工程有限责任公司成孔工艺干作业螺旋钻孔灌注桩机械类型JZB-60桩位编号成孔混凝土浇筑成孔时间日/月.时.分孔径(㎜)孔深(m)虚土或沉渣厚(㎜)自然地面标高(m)孔底标高(m)孔倾斜值(㎜)泥浆种类护壁泥浆清孔泥浆比重护筒埋深(㎜)浇筑时间日/月.时.分桩顶标高(m)砼体积(m3)砼充盈系数比重含砂率胶体率设计实测设计实测设计实测计算实注1799.26400405212130-2.45-23.42359.26-2.75-2.752.702.851.06469.26400408212150-2.46-23.41429.26-2.75-2.752.742.901.06769.27400410212140-2.48-23.52199.27-2.75-2.752.772.971.07729.27400408212150-2.47-23.42529.27-2.75-2.752.742.861.04739.27400405212120-2.45-23.43199.27-2.75-2.752.702.801.04749.27400409212130-2.46-23.43529.27-2.75-2.752.762.891.05759.27400409212130-2.46-23.43529.27-2.75-2.752.762.891.05829.27400410212160-2.48-23.42149.27-2.75-2.752.772.901.05799.27400410212140-2.47-23.43409.27-2.75-2.752.772.881.04839.27400406212150-2.45-23.40389.27-2.75-2.752.722.821.04809.27400410212170-2.48-23.41129.27-2.75-2.752.772.911.0599.27400408212160-2.47-23.41519.27-2.75-2.752.742.871.05109.27400412212180-2.45-23.37619.27-2.75-2.752.802.991.07监理工程师施工技术施工主要操作(建设单位代表):负责人:质检员:人员:记录人:注:1、本表适用于干成孔、泥浆护壁桩,所列项目根据工艺和设备具体要求填写;2、孔底标高=自然地面标高(孔上部周围地面实测标高)-孔实钻深度+虚土或沉渣厚度。3.砼浇筑计算体积=πD2×(桩顶标高实测值-孔底标高)÷4;D—孔径实测值(直径不同时可分段计算)4、孔底标高为虚土或沉渣处理后,灌注混凝土前实测标高。混凝土灌注桩施工记录工程名称海富山水文园二期(二)C13#施工单位百竣建筑工程有限责任公司成孔工艺干作业螺旋钻孔灌注桩机械类型JZB-60桩位编号成孔混凝土浇筑成孔时间日/月.时.分孔径(㎜)孔深(m)虚土或沉渣厚(㎜)自然地面标高(m)孔底标高(m)孔倾斜值(㎜)泥浆种类护壁泥浆清孔泥浆比重护筒埋深(㎜)浇筑时间日/月.时.分桩顶标高(m)砼体积(m3)砼充盈系数比重含砂率胶体率设计实测设计实测设计实测计算实注19.27400405212130-2.45-23.42359.27-2.75-2.752.702.851.06789.27400408212150-2.46-23.41429.27-2.75-2.752.742.901.0629.27400410212140-2.48-23.52199.27-2.75-2.752.772.971.0739.27400408212150-2.47-23.42529.27-2.75-2.752.742.861.04819.27400410212140-2.48-23.52199.27-2.75-2.752.772.971.0749.27400408212150-2.47-23.42529.27-2.75-2.752.742.861.0459.27400405212120-2.45-23.43199.27-2.75-2.752.702.801.0469.27400409212130-2.46-23.43529.27-2.75-2.752.762.891.0579.27400406212150-2.45-23.40389.27-2.75-2.752.722.821.0489.27400403212130-2.46-23.43499.27-2.75-2.752.682.791.04959.27400410212170-2.48-23.41129.27-2.75-2.752.772.911.05969.27400408212160-2.47-23.41519.27-2.75-2.752.742.871.05949.27400412212180-2.45-23.37619.27-2.75-2.752.802.991.07监理工程师施工技术施工主要操作(建设单位代表):负责人:质检员:人员:记录人:注:1、本表适用于干成孔、泥浆护壁桩,所列项目根据工艺和设备具体要求填写;2、孔底标高=自然地面标高(孔上部周围地面实测标高)-孔实钻深度+虚土或沉渣厚度。3.砼浇筑计算体积=πD2×(桩顶标高实测值-孔底标高)÷4;D—孔径实测值(直径不同时可分段计算)4、孔底标高为虚土或沉渣处理后,灌注混凝土前实测标高。混凝土灌注桩施工记录工程名称海富山水文园二期(二)C13#施工单位百竣建筑工程有限责任公司成孔工艺干作业螺旋钻孔灌注桩机械类型JZB-60桩位编号成孔混凝土浇筑成孔时间日/月.时.分孔径(㎜)孔深(m)虚土或沉渣厚(㎜)自然地面标高(m)孔底标高(m)孔倾斜值(㎜)泥浆种类护壁泥浆清孔泥浆比重护筒埋深(㎜)浇筑时间日/月.时.分桩顶标高(m)砼体积(m3)砼充盈系数比重含砂率胶体率设计实测设计实测设计实测计算实注779.27400405212130-2.45-23.42359.27-2.75-2.752.702.851.061139.29400405212130-2.45-23.42359.29-2.75-2.752.702.851.061039.29400406212150-2.45-23.40389.29-2.75-2.752.722.821.041029.29400403212130-2.46-23.43499.29-2.75-2.752.682.791.041019.29400410212170-2.48-23.41129.29-2.75-2.752.772.911.051009.29400409212130-2.46-23.43529.29-2.75-2.752.762.891.05719.29400410212160-2.48-23.42149.29-2.75-2.752.772.901.05709.29400410212140-2.47-23.43409.29-2.75-2.752.772.881.04699.29400408212150-2.46-23.41429.29-2.75-2.752.742.901.06689.29400410212140-2.48-23.52199.29-2.75-2.752.772.971.07979.29400408212150-2.47-23.42529.29-2.75-2.752.742.861.04129.29400405212120-2.45-23.43199.29-2.75-2.752.702.801.04119.29400412212180-2.45-23.37619.29-2.75-2.752.802.991.07监理工程师施工技术施工主要操作(建设单位代表):负责人:质检员:人员:记录人:注:1、本表适用于干成孔、泥浆护壁桩,所列项目根据工艺和设备具体要求填写;2、孔底标高=自然地面标高(孔上部周围地面实测标高)-孔实钻深度+虚土或沉渣厚度。3.砼浇筑计算体积=πD2×(桩顶标高实测值-孔底标高)÷4;D—孔径实测值(直径不同时可分段计算)4、孔底标高为虚土或沉渣处理后,灌注混凝土前实测标高。混凝土灌注桩施工记录工程名称海富山水文园二期(二)C13#施工单位百竣建筑工程有限责任公司成孔工艺干作业螺旋钻孔灌注桩机械类型JZB-60桩位编号成孔混凝土浇筑成孔时间日/月.时.分孔径(㎜)孔深(m)虚土或沉渣厚(㎜)自然地面标高(m)孔底标高(m)孔倾斜值(㎜)泥浆种类护壁泥浆清孔泥浆比重护筒埋深(㎜)浇筑时间日/月.时.分桩顶标高(m)砼体积(m3)砼充盈系数比重含砂率胶体率设计实测设计实测设计实测计算实注139.29400405212130-2.45-23.42359.29-2.75-2.752.702.851.06999.29400406212150-2.45-23.40389.29-2.75-2.752.722.82