国家电网公司电力安全工作规程电网建设部分(试行)国家电网公司发布目录第一篇通用部分1总则·······················32基本要求·····················42.1分部分项工程开始作业条件···········42.2作业人员···················42.3施工分包···················52.4安全施工方案·················62.5作业现场安全组织措施·············63施工现场·····················143.1一般规定··················143.2道路····················143.3临时建筑··················153.4材料、设备堆(存)放管理···········163.5施工用电··················173.6消防····················244通用作业要求···················284.1高处作业··················284.2交叉作业··················304.3有限空间作业················314.4运输、装卸·················324.5起重作业··················344.6焊接与切割·················364.7动火作业··················414.8季节性施工·················424.9特殊环境下作业···············445通用施工机械器具················465.1起重机械··················465.2施工机械··················495.3施工工器具·················595.4安全工器具·················706建筑工程····················786.1土石方施工·················786.2爆破施工··················826.3脚手架施工·················836.4混凝土施工·················876.5桩基施工··················956.6砖石砌体施工················976.7装饰施工··················986.8拆除施工··················996.9构支架施工················101第二篇变电(换流)站部分7电气装置安装·················1057.1一般规定·················1057.2油浸变压器、电抗器安装··········1067.3断路器、隔离开关、组合电器安装······1077.4串联补偿装置、滤波器安装·········1107.5互感器、避雷器安装············1107.6干式电抗器安装···············1117.7穿墙套管安装················1117.8换流阀厅设备安装··············1117.9蓄电池组安装················1127.10盘、柜安装················1127.11母线安装·················1137.12电缆安装·················1157.13电气试验、调整及启动···········1167.14变电站施工专业机具使用··········1238改、扩建工程··················1268.1一般规定··················1268.2邻近带电体的作业··············1298.3电气设备全部或部分停电作业安全技术措施···1318.4改、扩建工程的专项作业···········134第三篇线路部分9杆塔工程····················1399.1一般规定··················1399.2钢筋混凝土电杆排杆·············1429.3杆塔组装··················1429.4倒落式人字抱杆整体组立杆塔·········1439.5分解组立钢筋混凝土电杆···········1449.6附着式外拉线抱杆分解组塔··········1459.7内悬浮内(外)拉线抱杆分解组塔·······1459.8座地摇(平)臂抱杆分解组塔·········1469.9流动式起重机组塔··············1479.10直升机组塔················1489.11杆塔拆除·················15010架线工程···················15210.1跨越架搭设与拆除·············15210.2人力及机械牵引放线············15510.3张力放线·················15710.4压接···················16010.5导线、地线升空··············16110.6紧线···················16110.7附件安装·················16210.8平衡挂线·················16310.9导线、地线更换施工············16410.10预防电击················16411停电、不停电作业···············16711.1一般规定·················16711.2不停电跨越作业··············16911.3停电跨越作业···············17112电缆线路···················17412.1一般规定·················17412.2电缆敷设施工···············17512.3电缆接头施工···············17612.4电缆试验·················177附录A(资料性附录)现场勘察记录·········179附录B(资料性附录)输变电工程安全施工作业票A········180附录C(资料性附录)输变电工程安全施工作业票B········183附录D(规范性附录)各类安全工器具数据······185附录E(规范性附录)送电线路常用安全数据·····194附录F(规范性附录)起重机具检查和试验周期、质量参考标准···········197W第一篇通用部分版权专有不得翻印12版权专有不得翻印版权专有不得翻印31总则1.1为贯彻执行“安全第一、预防为主、综合治理”的安全工作方针,坚持以人为本、安全发展,加强公司电网建设施工现场安全管理,落实安全责任,规范人员行为,保障施工作业安全,依据国家有关法律、法规,结合电网建设实际,制定本规程。1.2参建单位管理人员、现场作业人员应遵守并严格执行本规程。1.3任何人发现有违反本规程的情况,应立即制止,经纠正后方可恢复作业。作业人员有权拒绝违章指挥和强令冒险作业;在发现直接危及人身、电网和设备安全的紧急情况时,有权停止作业。1.4在试验和推广新技术、新工艺、新设备、新材料的同时,应制定相应的安全技术措施,经本单位分管领导批准后执行。1.5参建单位可根据本规程的规定,结合本单位及工程的特点,编制专项实施细则或补充规定,经本单位分管领导批准后执行。1.6本规程适用于公司系统35kV及以上新(扩、改)建及公司所属单位承揽的公司系统以外的电网工程。35kV以下电网工程及境外电网工程可参照执行。4版权专有不得翻印2基本要求2.1分部分项工程开始作业条件2.1.1相关的施工项目经理、项目总工程师、技术员、安全员、施工负责人、作业负责人、监理人员、特种作业人员、特种设备作业人员及其他作业人员应经安全培训合格并到岗到位。2.1.2安全施工方案编制完成并交底。2.1.3相关机械、工器具应经检验合格,通过进场检查,安全防护设施及防护用品配置齐全、有效。2.1.4有施工分包的,施工承包单位应与分包单位签订合同和安全协议,且劳务分包单位已与其被派遣劳务人员签订劳动合同。2.1.5开工前,应编制完成工程安全管理及风险控制方案,识别评估施工安全风险,制定风险控制措施。2.2作业人员2.2.1应身体健康,无妨碍工作的病症,体格检查至少两年一次。2.2.2应经相应的安全生产教育和岗位技能培训、考试合格,掌握本岗位所需的安全生产知识、安全作业技能和紧急救护法。2.2.3应接受本规程培训,按工作性质掌握相应内容并经考试合格,每年至少考试一次。2.2.4特种作业人员、特种设备作业人员应按照国家有关规定,取得相应资格,并按期复审,定期体检。2.2.5进入现场的其他人员(供应商、实习人员等)应经过安全版权专有不得翻印5生产知识教育后,方可进入现场参加指定的工作,并且不得单独工作。2.2.6涉及新技术、新工艺、新设备、新材料的项目人员,应进行专门的安全生产教育和培训。2.2.7作业人员应被告知其作业现场和工作岗位存在的危险因素、防范措施及事故应急措施。2.2.8作业人员应严格遵守现场安全作业规章制度和作业规程,服从管理,正确使用安全工器具和个人安全防护用品。2.2.9发现安全隐患应妥善处理或向上级报告;发现直接危及人身、电网和设备安全的紧急情况时,应立即停止作业或在采取必要的应急措施后撤离危险区域。2.3施工分包2.3.1施工分包应依据施工承包合同的约定,或经业主批准。2.3.2分包单位资质应符合国家、行业相关要求,不得超越资质范围承揽工程。2.3.3应同时签订分包合同及安全协议。2.3.4专业分包单位的施工机械、工器具等应经承包单位和监理入场检查合格,方可进场,现场人员应经验证。2.3.5专业分包单位应开展安全教育培训,应提前将参与施工的所有人员培训考核情况书面提交承包单位审核认可,或经承包单位复训考核。2.3.6专业分包工程的重要临时设施、重要施工工序、特殊作业、危险作业项目以及危险性较大的分部分项工程作业时,承包单位应派员监督。2.3.7劳务分包人员安全教育培训纳入承包单位统一管理。2.3.8劳务分包人员不得独立承担重要临时设施、重要施工工序、特殊作业、危险作业以及危险性较大的分部分项工程施工。6版权专有不得翻印2.4安全施工方案2.4.1一般规定2.4.1.1安全施工方案包括作业指导书、施工方案的安全技术管理内容及专项安全施工方案。2.4.1.2重要临时设施、重要施工工序、特殊作业、危险作业应编制专项安全施工方案。2.4.1.3危险性较大的分部分项工程,应编制专项安全施工方案并附安全验算结果。2.4.1.4超过一定规模的危险性较大的分部分项工程,编制的专项安全施工方案应经专家论证、审查。2.4.2编审批及交底2.4.2.1作业指导书应由施工单位组织编制并发布。2.4.2.2施工方案由施工项目部技术人员编制,并经安全、质量管理人员、技术负责人或施工单位技术管理人员审核,施工单位技术负责人批准。2.4.2.3专项安全施工方案应由项目部技术负责人组织编制,并经施工单位技术、质量、安全等管理部门审核,施工单位技术负责人批准。2.4.2.4专业分包单位编制的作业指导书或专项安全施工方案应经施工承包单位审核。2.4.2.5交底应由编制人负责完成。2.4.3变更安全施工方案如需变更,应重新履行审批手续,并组织交底。2.5作业现场安全组织措施2.5.1保证作业现场安全的组织措施a)作业风险识别、评估、预警。b)安全施工作业票(以下简称作业票)。版权专有不得翻印7c)作业开工。d)作业监护。e)作业间断、转移、终结。2.5.2作业风险识别、评估、预警2.5.2.1作业票签发人或作业负责人在作业前应组织开展作业风险动态评估,确定作业风险等级。2.5.2.2作业前,应通过改善人、机、料、法、环等要素,降低施工作业风险。作业中,采取组织、技术、安全和防护等