220kV万匹变扩建电气安装工程施工强制性条文执行计划江苏海宁电力实业公司二〇一一年十月220kV万匹变扩建电气安装工程施工强制性条文执行计划审批页批准:年月日技术审核:年月日质量审核:年月日安全审核:年月日编写:年月日施工强制性条文执行计划第1页目录1.工程概况······························································································12.编制目的······························································································13.编制依据······························································································14.施工强条实施组织机构············································································15.施工强条实施措施··················································································3附录A施工强条实施计划表(总表)···························································5附录B电气施工强条执行记录表(总表)····················································7附录C电气安全强条执行记录表(总表)·······················································14施工强制性条文执行计划第1页1.工程概况220kV万匹变电所位于江苏省宿迁市沭阳县万匹乡,所址所在区域场地平整开阔,交通便利,变电所所处的地理位置自然环境条件较好。变电所本期扩建220kV出线2回,调整220kV出线2个间隔。2.编制目的为了加强220kV万匹变扩建电气安装工程施工的安全质量过程控制,全面贯彻落实《建设工程质量管理条例》(国务院令第279号)、《建设工程安全生产管理条例》,《实施工程建设强制性标准监督规定》(建设部81令)、《中华人民共和国工程建设标准强制性条文》(电力工程部分),强化质量安全责任,确保施工严格执行强制性条文,保证工程质量、杜绝安全事故,特编制《220kV万匹变扩建电气安装工程施工强制性条文执行计划》,作为本工程施工过程中贯彻落实法律法规的重要依据和措施。3.编制依据《建设工程质量管理条例》《建设工程安全生产管理条例》《工程建设标准强制性条文(电力工程部分)》;施工承包合同;施工图纸和有关设计文件工程施工组织设计国家电网科[2009]642号《关于印发《输变电工程建设标准强制性条文实施管理规程》的通知》4.施工强条实施组织机构为了使强制性条文得到有效的宣传、贯彻和落实,确保工程施工合法性,项目部成立强制性条文的实施组织机构如下:施工强制性条文执行计划第2页4.1、项目经理是确保工程施工过程中的合法性的第一直接责任者,负责组织收集、宣贯、落实工程建设标准强制性条文及有关强制性条文的法律职责,负责组织编制、整理与本工程有关的强制性条文的有关条款,制定和落实执行计划,确保有效执行并对施工全过程的质量、安全负责。4.2、项目副经理应配合项目经理做好以上工作,着重指导和监督强制性条文执行计划的实施情况。4.3、项目总工程师负责收集工程建设标准强制性条文及有关强制性条文的法律职责,负责编制、整理与本工程有关的强制性条文的有关条款,制定执行计划,确保其有效性和可操作性。4.4、项目部技术员应配合项目总工程师做好以上工作,并做好实施过程中本专业有关条款的监督和指导工作。项目技术员:聂亮项目质检员:徐明富项目安全员:胡道贵项目资料员:蔡素凤起重队队长及技术员电气队队长及技术员调试队队长及技术员综合队队长及技术员项目经理:何龙项目总工:蒋劲明施工强制性条文执行计划第3页4.5、项目部质检员和安全员应分别从确保工程施工质量和确保工程施工安全的角度出发,负责指导、检查、监督施工过程中有关条款的实施,确保本执行计划的有效执行;负责过程资料的验证工作、确保过程资料的可追溯性。4.6、项目部资料员负责收集、整理强制性条文及有关的法律法规;收集、整理有关强制性条文执行计划的过程资料;收集、整理实施强制性条文的施工过程记录。确保资料的完整性、系统性。4.7、各施工队队长及技术员负责本队作业范围内各作业点强制性条文的具体实施,做好实施强制性条文的具体施工记录、签证等工作。5.施工强条实施措施为了使强制性条文在本工程得以真正的落实,项目部制定以下实施措施,在施工过程中应严格执行。5.1强制性条文实施准备5.1.1根据国家电网科[2009]642号《关于印发《输变电工程建设标准强制性条文实施管理规程》的通知》的相关要求,项目部在工程开工前按照单位、分部、分项工程明确本工程项目所涉及的强制性条文,项目经理针对本工程组织编制《35kV城东变电所升压电气安装工程施工强制性条文执行计划》经内部审批后,报监理单位审核,建设单位批准后执行,保证工程项目执行强制性条文的完整性。5.1.2强制性条文执行计划包括强制性条文执行计划表、电气施工强制性条文执行记录、施工安全强制性条文执行记录表。5.2强制性条文的执行5.2.1工程施工阶段,强制性条文执行的主体责任单位为施工单位。5.2.2工程施工过程中,项目部及时将强制性条文实施计划的落实情况,根据工程进展按分项工程据实记录、填写《输变电工程施工强制性条文执行记录表》,并由监理工程师审核,输变电工程强制性条文执行记录表见附录B、C。5.2.3电气施工强条执行记录表由项目质检员/安全员对每个分项工程进行检查后据实填写,对不符合强制性条文要求的按照公司《不合格品控制程序》进行处理,并根据公司《纠正和预防措施管理程序》采取措施防止类似情况的发生,检查合格后报监理工程审核。5.2.4施工安全强制性条文执行记录由项目部安全员在施工过程中按照每条严格检查,据实填写,检查合格后报监理工程审核。5.2.5加强过程监督,在每个涉及强制性条文的施工作业点都必须进行跟踪、检施工强制性条文执行计划第4页查,确保每个施工作业点都严格执行。5.2.6做好与强制性条文执行情况有关的信息管理工作,及时做好工程纸质、数码照片资料的收集与整理。5.3强制性条文执行情况检查5.3.1强制性条文执行情况的检查主体责任单位为监理单位5.3.2在分部工程验收时,应由总监组织对施工单位执行强制性条文情况进行阶段性检查,检查结果填写《输变电工程施工强制性条文执行检查表》,施工单位由项目总工进行签证。5.4强制性条文执行情况的核查在工程竣工验收阶段,对强制性条文执行情况核查的主体为建设单位,在工程竣工验收时,施工单位向建设单位提交《输变电工程施工强制性条文执行记录表》。施工强制性条文执行计划第5页附录A施工强条实施计划表(总表)表3.0.2变电站电气工程施工强制性条文执行计划表工程编号工程项目名称责任单位强制性条文执行表号单位工程分部工程分项工程施工单位监理单位建设单位2主控及直流设备安装○○●1主控室设备安装○●1控制及保护和自动化屏安装●○表6.1.2表6.7.23220kV配电装置安装○○●3进出线(母联.分段及旁站)间隔安装○●1隔离开关安装●○表6.1.2表6.4.22断路器安装●○表4.1.2表6.4.23电流互感器安装●○表6.1.2表6.4.24避雷器安装●○表6.4.2表6.6.26支柱绝缘子安装●○表6.1.27引下线及跳线安装●○表9.0.28就地控制设备安装●○表6.1.210220kV配电装置带电运行○●7全站电缆施工○○●1电缆管配制及敷设3电缆敷设○●1屋内电缆敷设2屋外电缆敷设●○表5.0.25控制电缆终端制作及安装○●1控制电缆终端制作及安装7电缆防火与阻燃○●1电缆防火与阻燃●○表5.0.213交接试验○○●1交接试验○●4互感器●○表13.4.26SF6断路器●○表13.6.29避雷器●○表13.9.211接地●○表13.11.2注:1、●为该项强制性条文执行的责任主体单位,并负责填写相应表格。2、○为该项强制性条文相关责任单位。施工强制性条文执行计划第6页表3.2.2变电站电气工程施工安全强制性条文执行计划表工程编号工程项目名称责任单位强制性条文执行表号单位工程分部工程分项工程施工单位监理单位建设单位2主控及直流设备安装○●○表4.1.2、表4.3.21主控室设备安装●○表4.1.2、表4.3.23220kV配电装置安装○●○表4.1.2、表4.3.23进出线(母联.分段及旁站)间隔安装●○表4.1.2、表4.3.210220kV配电装置带电运行●○表4.1.2、表4.3.27全站电缆施工○●○表4.1.2、表4.3.21电缆管配制及敷设●○表4.1.2、表4.3.23电缆敷设●○表4.1.2、表4.3.25控制电缆终端制作及安装●○表4.1.2、表4.3.27电缆防火与阻燃●○表4.1.2、表4.3.213交接试验○●○表4.1.2、表4.3.21交接试验●○表4.1.2、表4.3.2注:1、●为该项强制性条文执行的责任主体单位,并负责填写相应表格。2、○为该项强制性条文相关责任单位。3、换流站施工安全强制性条文执行计划参照执行。施工强制性条文执行计划第7页附录B电气施工强条执行记录表(总表)4.1断路器4.1.1本条适用于断路器施工强制性条文执行、记录。4.1.2断路器施工强制性条文执行记录见表4.1.2。表4.1.2断路器施工强制性条文执行记录表工程名称单位(子单位)工程名称分部(子分部)工程名称分项工程名称施工单位项目经理强制性条文内容执行要素执行情况相关资料执行标准《电气装置安装工程高压电器施工及验收规范》GBJ147-19904.4.1在验收时,应进行下列检查:三、断路器及其操动机构的联动应正常,无卡阻现象;分、合闸指示正确;辅助开关动作正确可靠。联动检查传动记录编号:分合闸动作检查辅助开关动作四、密度继电器的报警、闭锁定值应符合规定;电气回路传动正确。报警值、闭锁值报警值:闭锁值:密度继电器试验报告编号:电气传动五、六氟化硫气体压力、泄漏率和含水量应符合规定。气体压力气体压力:断路器试验报告编号:断路器安装记录编号:气体含水量气体含水量:断路器气体检漏六、接地良好。接地检查安装记录编号:项目部质检员(安全员):年月日专业监理工程师:年月日6.2室内外接地网施工6.2.1本条适用于室内外接地网敷设施工强制性条文的执行、记录。6.2.2室内外接地网敷设施工强制性条文的执行记录见表6.2.2。表6.2.2室内外接地网施工强制性条文执行记录表工程名称单位(子单位)工程名称分部(子分部)工程名称分项工程名称施工单位项目经理强制性条文内容执行内容执行情况相关资料《电气装置安装工程接地装置施工及验收规范》GB50169-2006施工强制性条文执行计划第8页3.2.4人工接地网的敷设应符合以下规定:1人工接地网的外缘应闭合,外缘各角应做成圆弧形,圆弧的半径不宜小于均压带间距的一半;接地网敷设隐蔽工程验收签证编号:2接地网内应敷设水平均压带,按等间距或不等间距布置;接地网敷设隐蔽工程验收签证编号:335KV及以上变电站接地网边缘经常有人出入的走道处,应铺设碎石、沥青路面或在地下装设2条与接地网相连的均压带。接地网敷设隐蔽工程验收签证编号:3.2.5除临时接地装置外,接地装置应采用热镀锌钢材,水平敷设的可采用圆钢、和扁钢,垂直敷设的可采用角钢和钢管。腐蚀比较严重地区的接地装置,应适当加大截面,或采用阴极保护等措施。不得采用铝导体作为接地体或接地线。当采用扁