西安科技大学高新学院毕业设计(论文)I一号教学楼施工组织设计摘要本施工组织设计作为主导施工的依据,编制时对目标工期、工程质量、项目管理机构设置、劳动力组织、施工进度计划控制、机械设备及周转材料配备、主要分部分项工程施工方法、安全保证措施、文明施工及环境保护措施、降低成本措施等诸多因素尽可能突出科学性及可行性。关键词:施工组织,质量措施,工程管理-高新学院一号教学楼施工组织设计IIAbstractTheconstructiondesignastheleadingbasisfortheconstruction,preparationofthetargettimeperiod,projectquality,projectmanagement,institutionalsetup,labororganizations,theconstructionschedulecontrol,equippedwithmechanicalequipmentandworkingmaterials,themainsub-segmentoftheconstructionmethods,safetyassurancemeasures,civilconstructionandenvironmentalprotectionmeasurestoreducethecostofmeasurestogivefullconsiderationtosuchmuchaspossible,highlightingthescientificandfeasible。Keyword:Constructionorganization,qualitymeasures,projectmanagement……西安科技大学高新学院毕业设计(论文)III目录绪论...................................................................11工程概况............................................................22施工部署............................................................52.1原则要求........................................................52.2工程目标与招标文件响应..........................................52.3施工程序........................................................53施工方案及对本工程重点、难点特殊部位的处理措施......................73.1测量............................................................73.1.1平面控制.................................................73.1.2垂直度控制.................................................73.1.3沉降观测...................................................73.1.4一层结构施工阶段的安全观测.................................83.2结构施工........................................................83.2.1土方开挖及基坑排水.........................................83.2.2土方回填...................................................93.2.3基础施工...................................................93.3主体结构施工...................................................113.3.1模板工程..................................................113.3.2钢筋工程..................................................143.3.3砼工程....................................................183.3.4砌体工程..................................................203.3.5门窗工程..................................................223.3.6屋面工程..................................................233.3.7楼地面工程................................................253.3.8装修工程..................................................283.3.9油漆涂料施工..............................................303.3.10构件安装.................................................323.3.11脚手架...................................................323.3.12对本工程重点、难点、特殊部位的处理措施...................334质量保证措施.......................................................354.1全面推行IS09002质量保证体系...................................354.2质量目标实现的保证措施:.......................................354.3质量控制及检验措施.............................................415安全保证措施.......................................................455.1安全生产制度...................................................455.2基础施工安全措施...............................................475.3塔式起重机重点注意如下几点:...................................486文明施工保证措施及现场平面布置.....................................526.1文明施工措施...................................................526.2现场平面布置...................................................547主要施工机具与劳动力等资源配备及进度计划............................557.1施工机械(具)安排计划.........................................55-高新学院一号教学楼施工组织设计IV7.2施工机械(具)进场计划........................................557.3劳动力计划....................................................577.4现场临时设施计划...............................................578项目主要管理人员的配备及质量保证措施...............................588.1项目主要管理人员工程技术人员的配备............................588.2项目管理人员配备的质保措施....................................588.3项目管理模式..................................................599保证工期措施.......................................................6110冬、雨季措施及地下管线及地下地上设施的加固措施.....................6210.1冬季施工.....................................................6210.2雨季施工措施.................................................6310.3地下管线及地下地上设施的加固措施.............................6411材料质量检验措施...................................................6511.1材料检验和实验................................................6511.2检验,测量和实验设备控制.....................................6512竣工验收...........................................................6612.1竣工验收标准..................................................6612.2竣工验收程序.................................................66主要参考文献..........................................................67结束语................................................................68致谢..................................................................69附录1................................................................70西安科技大学高新学院毕业设计(论文)1绪论1.建筑工程施工组织概述建筑工程施工组织是研究和制定组织建筑安装工程施工全过程既合理又经济的方法和途径。它是针对不同工程施工的复杂程度来研究工程建设的统筹安排与系统管理的客观规律的一门学科。2与建筑工程施工组织有关的基本概念1)、基本建设基本建设是利用国家预算内的资金、自筹资金、国内外基本建设贷款以及其他专项资金进行的,以扩大生产能力或新增工程效益为主要目的的新建、扩建工程及有关工作。基本建设是国民经济的组成部分,是社会扩大再生产、提高人民物质文化生活和加强国防实力的重要手段。2)、基本建设程序是基本建设全过程中各项工作必须遵循的先后顺序。这个顺序反映了人们进行建设活动中所必须遵守的工作制度,是经过大量实践工作所总结出来的工程建设过程的客观规律。我国基本建设程序一般可分为决策、设计、准备、实施及竣工验收五个阶段。研究对