沣西新城应急给水厂深井泵房工程专项施工方案沣西新城应急给水厂项目深井泵房工程施工方案编制:审核:批准:日期:年月日沣西新城应急给水厂深井泵房工程专项施工方案目录第一章编制依据编制依据··············································1第二章工程概况第一节深井泵房施工概况······································1第四节电气自控施工概况······································2第三章项目经理部组成人员第一节项目经理部组织机构成人员·····························3第二节项目经理部机构组织···································4第三节项目经理部各级岗位职责·······························5第四节施工中平面布置图·····································6第四章劳动力、材料、机械设备投入计划第一节施工材料投入计划·····································7第二节劳动力安排计划·······································8第三节安全防护用品计划·····································8第四节检测仪器设备计划·····································9第五章施工方案第一节测量放线··············································9第二节基础施工·············································10第三节主体工程·············································13第四节装饰、装修工程········································23第五节屋面防水工程·········································26第六节脚手架工程···········································28第七节给排水及电气安装工程·································33第六章施工进度计划及工期保证措施第一节施工进度计划·········································35沣西新城应急给水厂深井泵房工程专项施工方案第二节工期保证措施·········································37第三节工程质量保证措施·····································43第四节冬期施工措施·········································47第五节安全施工措施·········································48第六节文明施工及环境保护措施·······························53沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司1第一章编制依据编制依据:1、《建筑工程施工质量验收统一标准》GB50300-20132、《砌体工程施工质量验收规范》GB50203-20113、《混凝土结构工程施工质量验收规范》GB50204-20023、《砌体结构设计规范》GB50003-2001(2002年局部修订)4、《多孔砖砌体结构技术规范》JGJ137-2001(2002年局部修订)5、《建筑地基基础工程施工质量验收规范》GB50202-20026、《砌筑工程施工质量验收规范》GB50203-20147、《屋面工程施工质量验收规范》GB50207-20024、《工程测量规范》GB50026-935、《建施扣件式刚管脚手架安全技术规程及验收规范》JGJ128-20007、《砌筑砂浆配合比设计规程》JGJ98-2000第二章工程概况工程名称:沣西新城应急给水厂深井泵房工程建设单位:西咸新区沣西新城投资发展有限公司设计单位:西安市政设计研究院有限公司工程地点:西咸新区沣西新城渭河大堤东侧第一节建筑部分深井泵房采用地面式砖混结构,其中A型深井泵房由2号泵房、4号泵房、5号泵房、7号泵房、12号泵房、13号泵房、15号泵房,井泵房设计尺寸为4.5mx4.5m;B型深井泵房由6号泵房、8号泵房、9号泵房、10号泵房、11号泵房、14号泵房、16号泵房、17号泵,深井泵房设计尺寸为9.3mx4.5m;C型深井泵房为1号泵房,泵房设计尺寸为9.3mx4.5m;D型深井泵房为3号泵房,泵房设计尺寸为9.3mx4.5m。本次施工的11号、12号及15号深井泵房现状地形比周围地形低3.8m-4.5m,故本次施工时首沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司2先分层回填夯实后至设计地坪后再进行泵房施工。泵房出水管道设计管径为DN150mm,接已设计给水预埋管道;泵房设计排水管道及集水坑排水管均在泵房外就近散排。深井潜水泵的设计扬程按照满足输水干管进厂的最小服务水头8米进行选取。同时每座深井泵房均设置配电柜、手动蝶阀、电磁流量计、止回阀、排气阀、压力表、深井水位仪等设施。水泵采用活动三脚架及手动葫芦进行起吊安装。深井泵房的进厂道路就近与规划路网衔接,道路设计红线宽度4米,设计总长度为1100米。道路路面均采用混凝土整体路面,混凝土面层厚度180mm。1、地基处理:地基处理应先将地表杂填土清理干净,采用素土回填至灰土垫层底,分层压实,压实系数不小于0.97;上做450mm3:7灰土垫层,压实系数不小于0.97.灰土垫层之上为砖基础,基础标高为-1.100m,建筑物抗震设防烈度为7度。结构为砖墙承重,墙厚均为240mm厚;所有墙体标高4.200mm、2.940mm处分别设置水平圈梁、构造柱,楼板为现浇板,板厚为120、150mm不等。2、砌体:±0.000m以下,采用MU10非粘土烧结实心砖,M10水泥砂浆砌筑;±0.000m以上,采用MU10.KP1非粘土烧结多孔砖,M7.5混和砂浆砌筑。3、砼强度等级,垫层为C15砼,梁、板为C30,构造柱、圈梁为C25。4、内、外墙饰面:内墙为乳胶漆墙面,外墙饰面涂料及饰面砖墙面。外墙保温层采用60厚PF板。5、地面:混凝土地面,水泥压光处理。6、屋面:不上人水泥砂浆面层屋面,保温层为70mm厚挤塑板,两道4mm厚SBS防水卷材。7、防水:凡无基础梁处均在室内地平下约60mm处做20mm厚1:2水泥砂浆墙身防潮层,内加相当于水泥重量5%防水剂。第二节电气自控及安装部分沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司3A型深井泵房不附设变配电室,B型深井泵房附设变配电室,A型深井泵房的电源由相邻深井泵房附设的变配电室引来,电压~380/220V电源由厂区10KV变配电所按南北两侧分别以环网引来4路10KV高压电源,经YJV22-10KV-3*95电缆直埋敷设至B、C、D型水泵房附设变配电室高压柜,高压系统为单母线分段,2路10KV电源1路供给SC10-10/0.4-D,yn11型干式变压器,经变压器降压到0.4KV后连接到低压开关柜,为B、C、D型水泵房及相邻A型深井泵房的动力、照明、PLC自控设备提供电源;负荷等级为二级负荷,深井泵房按第三类防雷建筑物防雷设防,采用TN-S接地方式,将配电柜(箱)外壳、变压器中性点及外壳、穿线钢管、工艺电气设备外壳、金属栏杆等均需作等电位连接,人工接地极采用L50*5*2500镀锌角钢3根做人工接地极,要求接地电阻≦1Ω.第三章项目施工组织部署第一节项目经理部组织机构人员我公司领导高度重视本工程并将其列为本年度重点工程之一,实现项目法管理,调遣类似工程经验丰富、业绩突出的专业工程队承建施工,组织以一级项目经理为首的项目经理部,其人员包括:项目经理、项目生产经理、技术负责人、质量负责人、安全负责人、材料负责人、施工负责人等。姓名职务职称学历专业备注杨英项目经理工程师本科市政一级建造师苗惠春项目副经理工程师本科工程管理一级建造师燕飞项目总工工程师本科土木工程二级建造师王海彬生产经理工程师本科土木工程伊俊质量负责人工程师大专设备安装二级建造师韩乐安全负责人助理工程师大专工程管理沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司4王乐材料负责人助理工程师大专材料管理党凯土建技术员助理工程师本科土木工程徐金柱设备技术员助理工程师大专设备安装冯纪林管道技术员工程师大专给排水马育红电气技术员工程师大专电气自动化第二节项目经理部机构组织项目经理部机构组织总工程师综合办公室项目经理项目生产经理材料设备部安全管理部试验、资料室工程管理部质量管理部安装施工队木工施工队砌体施工队土方施工队钢筋施工队混凝土施工队沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司5第三节项目经理部各级岗位职责1、项目经理主要岗位职责①代表公司对项目全面负责,在项目上实施公司的质量方针和经营宗旨,全面履行合同。②组织制定施工组织设计,审批施工组织设计,审核专业基础上组织设计。③保证质量体系在项目中的有效运行。对项目质量、安全、工期、成本和文明施工负责。2、项目生产经理主要岗位职责①对项目经理负责,负责工程施工、安全及文明施工工作。②做好施工准备工作,负责各区域、各专业施工的协调、对关键工序和特殊工序组织有效的控制。③执行公司工序交接管理制度。3、技术负责人主要岗位职责①对项目经理负责,协助项目经理监管项目质量保证体系的运行;②主管质量、技术管理工作;③组织施工组织总设计的编制工作;④负责对单位工程施工组织设计、重大方案审核;⑤组织协调解决重大技术问题。⑥组织不合格品处置、纠正和预防措施的实施;⑦组织实施对工程产品的标识和成品保护工作;⑧负责产品的可追溯性工作。4、质量负责人主要岗位职责①负责所需的规范、标准、规程的配备和实施;②负责设计文件的管理和联络工作;③组织、检查施工图纸的自审、会审和技术交底工作;④对工程质量进行检查与控制,对不合格品提出处置方案;⑤负责项目的检验和试验及检验、测量和试验设备的控制和管理工作;沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司65、安全负责人主要岗位职责①负责进场作业人员安全教育并登记造册;②检查进场施工机械申报手续是否健全,以及特殊作业人员持证上岗情况;③收集并做好现场安全文明施工及环境保护资料。6、材料负责人主要岗位职责①负责业主提供的工程所需的材料、半成品和设备的验证、现场保管、供应等管理工作;②负责自行采购的材料、半成品、设备的采购、验收、保管、供应等管理工作;③负责施工现场的物资标识工作;7、施工组织领导①在项目经理的领导下,采用横向分工负责、协调配合与纵向责任落实的方法,科学的制订计划和决策。②专职负责人员均进驻现场组织指挥、检查,并做好检查记录。③项目经理部定期召开由有关负责人参加的工程协调会。④各专职负责人应根据施工进度计划,提前做出本专业的工序安排、人员组织及有关专业人员配合的计划和要求。⑤中标后我公司现场项目经理部将根据设计交底内容和监理工程师的要求以及施工现场实际情况编制详细的施工组织设计及施工进度计划。第四节施工总平面布置图综合本工程的特点,施工组织的整体主导思路是:抓紧施工准备工作,上足专业机械技工;多点同步展开施工,技术组织方案先行;突出工程结构重点,阶段目标限期完成;安装专业紧密配合,网络管理有序可控;严把工艺材料质量,相关各方密切协同;精工细作保创市优,确保安全提前竣工。1、施工场地的办公用房及驻地的位置沣西新城应急给水厂深井泵房工程专项施工方案陕西有色建设有限公司7按照施工总平面布置图在工程所在位置平整场地搭设临时办公住宿设施,以满足工程人员施工、