都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)(TYK16+000~TYK24+077.569)路基高边坡开挖专项施工方案贵州省公路工程集团有限公司六盘水至威宁(黔滇界)高速公路LWTJ-7合同段项目经理部二○一六年三月目录一、工程简介...................................................................................................................................11.编制依据.............................................................................................................................12.工程概况.............................................................................................................................1二、施工准备...................................................................................................................................21.施工组织机构.....................................................................................................................22.内业准备.............................................................................................................................23.人员、设备准备.................................................................................................................3三、开挖原则...................................................................................................................................3四、挖方施工工艺...........................................................................................................................41.土方路堑施工.......................................................................................................................42.石方路基施工.......................................................................................................................6五、路基挖方边坡质量通病及防治方法.....................................................................................13六、预防坍塌和滑坡事故的防护措施.........................................................................................14七、质量保证措施.........................................................................................................................141.质量保证体系和质量责任制.............................................................................................142.质量反馈系统.....................................................................................................................153.质量控制主要措施.............................................................................................................16八、安全保证措施.........................................................................................................................161.安全保证体系.....................................................................................................................162.安全防范重点与措施.........................................................................................................173.施工安全应急预案.............................................................................................................18九、文明施工及环境保护.............................................................................................................191.文明施工.............................................................................................................................192.环境保护措施.....................................................................................................................20都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段路基高边坡开挖施工方案1一、工程简介1.编制依据(1)《都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段施工招标文件》。(2)《都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段投标文件》。(3)《都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段两阶段施工图设计文件》(第二册第1、2分册,第五册第1分册)(贵州省交通规划勘察设计研究院股份有限公司,二0一五年十一月)。(4)《公路路基施工技术规范》JTGF10-2006。(5)《公路工程施工安全技术规范》(JTGF09-2015)。(6)《公路工程质量检验评定标准》(JTGF80/1-2004)。(7)本标段对施工现场考察和勘验所获取的相关资料,范围内出、入口施工便道的现场考察资料及周边建筑布置情况。(8)本单位现有的技术能力、机械设备、施工管理水平及多年来参加高速公路建设所积累的施工经验。2.工程概况本标段起于水城县纸厂乡,接LWTJ-6标段终点,起点桩号TYK16+000。本标段终点止于六盘水市水城县勺米乡鱼塘,在此设鱼塘枢纽互通与杭瑞高速公路毕节至都格段(简称“毕都高速”)相交,终点桩号为TYK24+077.569,路线全长8.330581公里。其中高边坡路基土石方开挖工程数量为67.1669万立方米,边坡最大高度为50.58米,最高边坡为五级边坡,全线高边坡数量如下:序号段落桩号最大边坡高度(m)边坡最大级数(级)挖土石方量(m³)1TZK20+260~TZK20+44030.8941016492TZK20+640~TZK20+80039.3241070513TYK21+230~TYK21+40041.84700474TYK21+620~TYK21+94050.585213962都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段路基高边坡开挖施工方案25TYK22+160~TYK22+44038.244920066BK0+420~BK0+565(鱼塘枢杻互通)32.873518387ZK194+400~ZK194+658.540(鱼塘枢杻互通)48.76535116二、施工准备1.施工组织机构为确保本工程保质保量按期完成施工任务,我部将集中精良的机械设备,组织优秀的施工队伍进行本工程施工,设立强有力的六威七标项目经理部,对人员、机械设备、材料实行统一管理,统一调度。施工组织机构框图2.内业准备施工图纸及设计文件均已熟悉完,控制点复测及原地面复测已经完成。都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段路基高边坡开挖施工方案33.人员、设备准备人员配置如下:序号岗位人数1现场负责人32质检工程师23现场工程师74技术员75专职安全员76材料员47试验员3设备清单如下:序号设备名称数量备注1挖掘机8台已进场2装载机2台已进场3推土机2台已进场4平地机4台已进场5振动压路机4台已进场6自卸车30辆已进场7液压钻7台已进场三、开挖原则1.高边坡开挖施工以保证施工和周围环境安全及节点工期为原则。土方开挖的顺序和方法必须与设计工况相一致,严格掌握“分层、分段、分块、对称、限时”五个要点,并遵循“竖向分层、水平分区分段、严禁超挖”的原则,确保工程安全质量前提下快速施工,减少土体开挖后的暴露时间。2.开挖时,其纵横向边坡放坡应根据地质、环境条件采取安全坡度。开挖一级防护一级,严禁在一个工况条件下,一次开挖到底。材料的堆载应远离高边坡顶边线5米以外,防止侧压力过大。3.开挖前,应在坡顶外设置截水沟,防止地表水冲刷坡面和高边坡外排水再回流渗入坑内,防止边坡坍塌。4.加强明水排放,在高边坡开挖后,应及时设置排水沟,防止积水。5.机械挖土时,底层应保留300mm厚土层用人工挖除整平,防止超挖。6.在开挖过程中,应根据开挖情况随时进行地质核查,并对边坡稳定性进行都(匀)香(格里拉)高速公路六盘水至威宁(黔滇界)LWTJ-7合同段路基高边坡开挖施工方案4监测,并根据地形特征设置边坡控制点(或观测墩),进行沉降监测,测量其沉降和位移,绘制变形曲线,若变化较大时应加强监控频率,并通知项目安全管理小组,必要时人员、机械停工撤离。如现场实际情况与设计不符,应会同设计单位等进行处理。四、挖方施工工艺1.土方路堑施工(1)施工准备①施工前,提前搞好地址勘查工作,看是否有不良地