山西大同李家窑煤业有限责任公司兼并重组整合矿井副斜井架空乘人装置安装工程施工安全技术措施编制单位:河南煤炭建设集团有限责任公司2012年5月2日目录一、编制依据································································二、工程概况································································三、施工工期································································四、目标策划································································五、关键过程和特殊过程控制···········································六、施工准备································································七、施工方法································································八、试运行···································································九、技术要求································································十、质量保证措施与质量目标···········································十一、重大危险源及应急预案···········································十二、安全技术措施·······················································十二、环境保护措施·······················································十四、劳动保护用品的配置与发放·····································十五、工程防护措施·······················································十六、成本控制措施·······················································十七、施工机具材料·······················································十八、劳力安排·····························································十九、施工组织机构·······················································二十、安全组织机构·······················································二十一、环境控制组织机构图···········································二十二、计划施工进度图表··············································-1-山西大同李家窑煤业有限责任公司兼并重组整合矿井副斜井架空乘人装置安装工程施工安全技术措施一、编制依据:⑴甲方提供的施工图纸和其他技术文件等。⑵本公司“三标一体”管理体系以及其他相关管理制度。⑶本工程采用的主要规范、规程及标准:《煤矿安装工程质量检验评定标准》(MT5010—95)《机械设备安装工程施工及验收通用规范》(GB50231-98)《施工现场临时用电安全技术规范》(JGJ46-2005)《煤矿安全规程》(2011版)《架空人车行业规范》GB3836-1/GB3836-2配套有关电气设备防爆的有关规定二、工程概况李家窑煤业有限责任公司兼并重组整合矿井副斜井架空乘人装置工程,斜井巷道为拱形,巷道最大坡度23度,吊椅间距16米,机尾重锤装置布置在巷道底部。先期土建工程已基本完毕,现安装一套RJY30-23/450型架空乘人装置。架空乘人装置横梁采用11#矿用工字钢,间距5米,矿用工字钢下面高度距地坪2800mm,。由于副井口施工,本工程属于井下工程,地质条件复杂,施工难度大,任务紧,特制订本措施,望全体人员贯彻执行。主要技术参数:-2-1、最大坡度:23°2、输送距离:450m3、最大输送效率:241人/h4、运输速度:0.8m/s5、电机功率:30KW6、钢丝绳最大牵引力9.35KN7、钢丝绳直径:16mm8、驱动轮直径:1000mm9、迂顺轮直径:1000mm10、托轮间距:10m12、吊椅间距:16m13、尾轮张紧行程:7m14、尾轮张紧重锤:750kg三、施工工期2012.5.14—2012.6.15、施工工期32天。四、目标策划我项目部根据公司领导、本工程建设规模、工期、质量、安全及文明施工目标的要求,建立健全施工管理体系和质量保证体系,认真对待施工过程的每一环节,全力以赴组织施工。同时配置高素质的劳务层,以高度负责的态度和科学严密的施工技术措施,严格管理、精心组织、科学施工,并与矿竭诚合作,优质、高效、确保本工程顺利建成。-3-1、质量目标:工程质量合格,一次验收合格率100%。2、职业健康安全管理目标:无重伤及重大责任死亡事故,员工轻伤负伤率1‰,无特种机械设备及机械设备事故;安全防护发放到位率100%;特种作业人员持证率100%3、环境管理目标:可回收固废回收率达到85%以上;有毒有害固废收集、存放、合法消纳达到100%;无毒固废合法处理达到90%以上;4、文明施工目标:争创文明施工工地。5、工期目标:2011年10月15日—2011年10月30日6、安全目标:无死亡、无重伤、年轻伤率1%。五、关键过程和特殊过程控制本工程的关键过程为:驱动装置安装。1、施工前的准备(1)项目部技术负责人组织有关人员对施工图纸进行会审,熟悉和领会设计意图,针对施工实际情况对施工图纸提出意见,并将会审意见汇总作好会审记录。(2)项目经理组织各管理人员对合同条款进学习,特别是对合同中的专用条款进行仔细的分析和学习。(3)公司相关部门人员和项目部技术负责人、施工技术人员参加有矿方召集组织的设计交底会。并将施工图纸会审意见在设计交底会议上提出协商解决办法,形成会议纪要。设计交底会议纪要由参加-4-会议的各方代表签字,单位盖章后生效。(4)项目部技术负责人组织施工技术人员编制施工措施,报公司相关部门审查后,由总工程师主持审批会议批准后实施。(5)项目部施工员根据施工组织设计或工程施工需要提出劳动力计划,施工机械、工器具计划,根据施工图纸提出材料计划。(6)项目部技术负责人组织各施工管理人员对工程所涉及的规范及标准进行学习。(7)项目部技术负责人在矿方的协调下负责与矿建单位办妥有关皮带机中心线、基础标高控制点的移交手续,同时作好复测记录。(8)工程开工前,项目部技术负责人、安全经理负责向施工员、质检员、材料员等,对工程范围及有关衔接部位的注意事项,质量评定标准,关键工序和特殊工序的控制要求,采取的安全措施等进行技术交底,并作好记录。(9)分项工程由专业工程师负责向班组长、作业人员交底并作好记录。(10)在施工前,对施工队伍的相应操作者进行检查,是否具备相应的操作资质,并留有复印件以便查询。(11)在施工准备工作一切就绪后,填写开工报告,并请矿方审批,作为正式开工的依据。2、施工过程的控制(1)人员控制:本工程的各管理人员,项目经理、技术负责人、安全经理、施工员、质检员、材料员等应具备相应的证书;特殊工种,-5-焊工、电工、起重指挥、吊车驾驶、铲车驾驶、机动车驾驶、架子工等应具备与其工作相符的特殊工种上岗证。(2)施工设备控制:本工程所用的大型施工设备为吊车,、机动车;小型设备为电焊机、气割、砂轮切割机、现场控制电箱;其余为小型电动工具。大型机械设备由项目部施工经理统一调度使用,具体由驾驶员维修保养,小型设备和小型电动工具由项目部仓库管理员进行管理,根据现场实际情况进调配使用,项目部指派保养电工进行维修和保养。(3)技术工艺控制:A、在每道工序工作前,由班组长对操作人员进行施工交底,工序结束,由操作者本人及班组长进行检查,重要工序由专业工程师和质检员进行检查,检查合格、进行下道工序,检查不合格,现场分析原因,下达质量整改通知单进行质量整改,整改合格后方可进入下道工序。B、对于设计修改,要有设计修改通知单;如非设计修改,需由矿方及监理确认后方可修改;修改的部位要在项目部保存的施工图上反映出来;对施工工艺进行修改,必须由专业施工工程师编写修改方案,报公司生产技术部,并由公司总工程师审核批准。(4)环境控制:本工程由于进行皮带硫化产生废弃物,要注意施工废弃物对环境造成的污染,必须将废弃物运至矿方指定地点排放,禁止乱丢乱放。3、验收和交付过程控制-6-(1)在中间验收和最终交工验收之前,项目部技术负责人组织项目部各专业施工员和质检员对即将验收的项目进行内部自查,并将检查的结果通知施工班组,对存在的缺陷责令班组限期消缺。(2)在项目部自查和消缺结束后,再请公司有关部门对需验收的项目进行预验收,并将结果通知项目部。(3)在公司有关部门的预验收合格后,请矿方及监理进行验收,对在验收过程中提出的疑问进行解释,对矿方及监理提出的要求整改的地方及时派专人进行限期整改,并将整改结果上报矿方及监理。(4)对在验收过程中涉及的资料,在验收之前要进行整理,并满足矿方及监理对资料的要求。六、施工准备1、施工准备(1)、组织所有施工人员熟悉图纸,设备技术文件要求,在工程施工前,对各工序的施工人员进行必要的岗位培训,同时对其进行技术、质量、安全交底,预防发生安全和质量事故。(2)、进入现场前根据施工现场情况搞好三通一平工作。根据现场实际情况和存在的问题及时提请矿方及监理商讨处理方案以及达到共识。(3)、及时与矿方联系,做好现场施工人员生活、生产、办公设施的搭建。合理地布置用水、用电及现场排水。2基础复测由建设单位、安装单位、监理单位、土建单位组成验收组,土建-7-单位要向安装单位提供基准点标高、横纵向基准线,以及基础砼标号。根据图纸及土建提供基准点、基准线对基础进行复测,并作出记录,对基础偏差较大的地方要由土建单位处理。基础划线用墨线把十字线投影在各设备基础上,根据图纸尺寸要求,检查各设备基础十字线是否符合设计要求,并留有施工记录,作好与土建交接手续。4、设备准备:根据本工程特点和我单位的综和施工能力,拟在本工程中配备性能良好、数量足够的机械、中小型施工机具。5施工组织机构我部将严格按照项目法施工,建立以项目经理为首的领导班子,组织一支懂技术、会经营、善管理的管理人员队伍,以及一支技术含量高、施工方法先进的施工专业队伍,严密管理,确保重点。七、施工方法1、驱动装置安装:认真检查土建预留基础位置标高,将驱动装置用叉车运至安装位置,用倒链吊起放在安装位置,用垫铁进行调整好,安装好预留螺栓,将预留螺栓进行灌浆后,待混凝土凝固后,达到强度后将驱动装置进行精找。2、轮系的安装(1)轮系包括:压绳轮、托绳轮、收绳轮、测速轮,绳轮是通过联接器连接在支撑筒上。A、联结器的安装-8-联接器是由左、右压块通过U型瞳固定在支撑筒上。将支撑筒U型卡固定在支撑筒上。紧固各处连接螺栓。工字钢横梁如果与底板的水平度不准确,将造成安装好的轮系不能与巷道底相平行,这时可调整联接器上的左右预紧螺栓,调节托、压绳轮的支承轴水平,使绳轮尽量水平。B、托绳轮的安装1)将支撑筒用U型卡联接在工字钢横梁上,支撑筒的中心线与先在横梁上做好的猴车实际运行的中线记号对齐。2)安装联接和托