沈阳星摩尔购物广场项目地上结构模板施工方案第1页共48页目录一编制依据··································································································2二工程概述··································································································2三施工准备··································································································2四施工工艺··································································································3五施工方法··································································································3六模板加工·································································································18七模板拆除·································································································19八模板的维护与维修·····················································································20九质量验收标准···························································································21十质量保证措施···························································································22十一安全施工······························································································23十二文明施工······························································································24十三模板计算······························································································24沈阳星摩尔购物广场项目地上结构模板施工方案第2页共48页地上结构模板方案一编制依据1、本工程施工图纸。2、混凝土结构工程施工质量验收规范GB50204-20023、混凝土结构工程施工技术标准《ZJQ08-SGJB204-2005》4、建筑施工碗扣式钢管脚手架安全技术规范《JGJ166-2008》5、建筑施工扣件式钢管脚手架安全技术规范《JGJ130-2001》二工程概述1.星摩尔购物广场位于沈阳市北二路与景星街交汇处。总面积33万㎡,由商业,高层办公室、购物超市广场、美食城、电影院、餐厅等组成。地上部分建筑面积23.1万㎡,商场部分分成A~H八个岛状的商业区,H还包括高层办公楼,岛状的商业区位3层多层建筑,各岛之间有钢桥相连。2.H区办公楼为框架剪力墙结构。A~G区多层商业裙房为框架结构。3.H区办公楼总高为103.5m,购物广场总高为19.8m、23.5m.A区部分三层结构层高为10.35m,其余区段一层至三层层高均为6.6m。5.本工程主要柱截面有:600*600、700*700、900*900、1000*1000等。6.本工程主要梁截面有:300*750、400*1800、500*1000、300*850等。7.适用范围:本方案仅适用于H区办公楼、及所有层高小于或等于6.6m的地上结构。层高大于6.6m参照高支模方案施工。三、模板选型1.柱模板:采用10厚竹胶板、50*100木方、钢管(φ14对拉螺栓)抱箍。木方做边框、散拼背楞。2.墙模板:采用10厚竹胶板、50*100木方、100*100木方、φ48钢管。50*100木方做次龙骨,φ48钢管做主龙骨,100*100木方做角模龙骨。螺栓采用周转杆φ14圆钢螺杆,加套胶杯和塑料套管,对拉螺栓在模板拆除后抽出重复使用。所有墙体模板均采用散拼方式。3.顶板、梁模板:采用10厚竹胶板、50*100木方次龙骨、50*100木方两根合并做主龙骨。沈阳星摩尔购物广场项目地上结构模板施工方案第3页共48页四施工准备4.1技术准备1、测量员给定标高。2、定位尺寸线经过报验符合要求。4.2物资准备1、50*100木方、100*100木方,进场必须压刨。2、10厚竹胶板、15厚木胶板,裁割后用平刨扫边,用封边漆封边。3、周转杆、穿墙螺栓上油。4、碗扣钢管、钢管、扣件进场复试,涂刷不同颜色漆。4.3机具准备1、平刨、压刨、圆盘锯(上防护罩)、手锯(不得带到现场)、锤子、电焊机等重点要求:未经允许禁止私自切割木方、模板14对拉螺栓、山型卡。4.4人员准备钢筋工:木工:混凝土工:架子工:电焊工:电工:四施工工艺1、墙模板:预埋地锚→配模板钻孔→放线→模板安装→穿止水对拉螺杆→调整固定→打楔子→支设斜撑。2、柱模板:弹线→找平、定位→安装柱模→安装抱箍→安装斜撑→校正垂直度→检查验收。3、梁模板:抄平、弹线(轴线、水平线)→支撑架搭设→支柱头模板→铺设梁底模板→拉线找平(起拱)→绑扎梁筋→封侧模4、平板模板:支撑架搭设→安放可调头→调整可调头标高→放置主龙骨→放置次龙骨→铺竹胶板五施工方法5.1墙模板1、本工程地上结构墙体主要是H区办公楼核心筒墙体。H区办公楼1-3层层高6.6m,4-13层层高3.9m。均采用散拼形式。墙体与梁板整体浇注。2、墙模板采用10mm厚竹胶板,次龙骨采用50×100木方,100×100木方。沈阳星摩尔购物广场项目地上结构模板施工方案第4页共48页中心间距:250mm,并在其后增设横向背楞,均为2¢48钢管,对拉螺杆为¢14组合式对拉螺栓。模板在安装前要在木工房内按照要求进行配板,统一打直径为20mm的孔,将模板砖成标准孔,方便周转。对拉螺杆与孔一一对应安装。6.6m层高竖向间距第一道水平距模板下口150mm,第二道至第六道间距425mm,第七道间距450mm,最上部一道间距145mm,中间间距610mm。3.9m层高竖向间距第一道水平距模板下口305mm,第二道至第六道间距610mm。详见下图:6.6m层高3.9m层高沈阳星摩尔购物广场项目地上结构模板施工方案第5页共48页墙加固示意图3、H区办公楼1-3层层高6.6m,为避免核心筒墙体浇筑时变形。在浇注混凝土前将由专人在板上放地锚,其支撑斜角45°~60°之间,间距3m。地锚采用¢25的钢筋,露出板面200mm,埋进地面100mm)。先用在墙模板外侧做斜撑,内侧做水平支顶(内顶外撑)。且墙体外侧模板下口宜包住下层混凝土100-200mm,以保证接槎平整,防止错台。详见下图:注:H区办公楼标准层层高3.9m,只需减少内部支撑即可。4、细部节点沈阳星摩尔购物广场项目地上结构模板施工方案第6页共48页阴角模接缝处顶紧,用海绵条塞实两块平板连接处,并用海绵条塞实接缝用钉子钉紧竹胶板10x10cm木方a.两块模板拼接处用10×10cm木方设子母口,相互咬合,用钉子钉紧。并用海绵条塞实接缝。b.阴角处背10×10cm木方,用钉子钉紧,接缝顶紧,用海绵条塞实。c.预留门窗洞口的模板,应有锥度,安装要牢固。既不变形,又便于拆除。d.阳角模处两个方向钢管相遇时,一个方向的双钢管上(下)钢管伸出300mm,令一个方向的双钢管下(上)伸出300mm,形成咬合状态。然后用十字扣件将两叠合钢管紧锁在一起。5×10cm木方钉子子口母口沈阳星摩尔购物广场项目地上结构模板施工方案第7页共48页阳角处钢管构造5.2.柱模板1、本工程柱采用10mm厚竹胶板模板,木工房内按照要求进行配板,模板接触处粘贴海绵条,防止漏浆。2、5×10cm木方为次龙骨,Φ48×3.5mm钢管为主龙骨。支模前先对结构构件进行放线,放出结构的外边线,木方必须平直,当一根4m木方不够长度的时候,按照实际尺寸进行拼接,同时在接口处被一根木方,保证有两道抱箍对其加固3、柱模板根据柱子截面尺寸、高度,进行散拼安装,按照外边线尺寸进行调正。4、模板加固采用Φ48×3.5mm钢管+φ14对拉螺杆+山形扣件。纵向间距底部第一道为190mm,从柱顶以下2200mm范围内对拉螺杆间距为600mm,其他间距分别为450mm。详见下图:沈阳星摩尔购物广场项目地上结构模板施工方案第8页共48页独立柱模板支设平面图独立柱模板支设立面图3形卡14对拉螺杆木楔钢管50*100木方钢管50×100木方木楔10mm厚竹胶板表1:各类柱截面加固明细表柱截面抱箍间距每侧次龙骨根数对拉螺栓根数600*600从柱顶以下2200mm范围内对拉螺杆间距为600mm,其他间距分别为450mm40650*65050700*70050750*75050800*80051900*900611000*1000615、根据现场实际情况打木楔,进行加固并加钢管斜撑,校正其垂直度。6、柱模校正完毕后仔细检查加固钢管是否与木枋紧靠,特别是墙阴角处应仔细检查,空隙位置采用木楔楔入,支设斜撑。5.3、圆柱模板直径为1300mm采用预制玻璃钢筒模,直径为600mm圆形柱采用木模现场预制。1、玻璃钢模为两个半圆形(内径按照柱直径)。2、木制模板现场采用20*50mm木条按柱直径拼制成半圆模板,内侧用2mm厚PVC板粘贴在木条上,外侧40mm木板做背楞间距500mm。现场采用φ16钢筋做沈阳星摩尔购物广场项目地上结构模板施工方案第9页共48页抱箍,两头焊制角钢留空,抱柱子时用螺栓扭紧螺栓孔必须左右一致且均匀排布,以便安装时螺栓能顺利穿过,为防混凝土浇筑过程中灰浆流失,柱钢模垂直接缝处粘贴防水海绵胶。该模板组装成型校正完毕后,擦拭干净,再涂刷隔离剂。5.4、梁模板1、梁底挂通线,按照线位铺设梁底,梁侧模上口、下口要求拉通线找直。2、满堂脚手架搭设,主、次梁底加立杆单独支撑。3、腹板高度大于600mm的梁,在梁底两侧立杆上锁通常钢管,然后在通常钢管上加密锁梁底小横杆,间距0.6m。4、采用梁侧模包底模,楼板模压梁侧模法施工,楼板模板应与梁模板相对独立,拆除板底模板时,梁的支撑体系可以保持不变。5、楼板底模下设50×100木枋作为次龙骨,间距为250mm左右,主龙骨采用两个50×100木枋合并,间距为900mm左右,放置于支撑立柱上部的调节支撑头或直接与立杆用扣件相连。6、梁侧模采用5*10cm木枋做背楞(平放),梁底模大横杆、小横杆均采用Φ48钢管,梁底模用扣件锁死定位梁底板模板;当梁腹板小于600mm时,可以不设置对拉螺杆;当梁腹板大于600mm小于1000mm时沿梁长方向设置一道对拉螺栓,当梁腹板高大于等于1000时沿梁长方向设置两到螺栓,(间距400mm)抵抗砼的侧压力,14对拉螺杆水平应穿设18PVC管以保证周转使用,对拉螺沈阳星摩尔购物广场项目地上结构模板施工方案第10页共48页杆水平间距900mm左右。如图所示:夹紧木楔起拱木楔夹紧木楔起拱木楔夹紧木楔起拱木