武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案编制:审核:审批:武汉市轨道交通七号线一期工程第九标段土建工程项目经理部2015年11月武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-1-目录1编制依据.......................................................12工程概况.......................................................12.1设计概况.................................................12.2地理位置及工程范围.......................................22.3工程地质及水文地质.......................................22.3.1工程地质...........................................22.3.2水文地质条件.......................................32.4参建单位.................................................43施工筹划.......................................................43.1塔吊选型.................................................43.2塔机平面布置及周边建筑物情况.............................53.3工期安排.................................................63.4施工机械、设备投入情况...................................74施工工艺和施工方法.............................................74.1塔吊性能参数.............................................74.2基础制作与验算..........................................104.3塔吊安装................................................114.3.1施工准备..........................................114.3.2塔吊安装流程......................................124.3.3吊装基础节........................................124.3.4吊装爬升架........................................13武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-2-4.3.5安装回转支承总成..................................144.3.6安装塔头..........................................164.3.7安装平衡臂总成....................................174.3.8安装司机室........................................184.3.9配装平衡重........................................214.3.10起升机构绕绳系统.................................214.3.11接电源及试运转...................................214.3.12换倍率器的使用...................................214.4顶升加节................................................224.5塔吊的检查、验收........................................254.5.1安装后的检查......................................254.5.2塔吊验收..........................................264.6安全装置的测试..........................................274.7塔吊拆除................................................284.7.1施工准备..........................................284.7.2塔机拆除顺序......................................294.7.3拆塔过程中的注意事项..............................305群塔作业......................................................316施工安全保证措施..............................................346.1组织保障................................................346.2安全管理岗位职责........................................356.3安全保证措施............................................366.3.1高空作业人员安全保证措施..........................36武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-3-6.3.2塔机安全管理措施..................................376.3.3塔机安全防范的技术措施............................396.3.4施工用电安全措施..................................426.3.5其他安全保证措施..................................436.4安全文明施工措施........................................446.5危险源的辩识及分析......................................487应急预案......................................................507.1应急组织机构及职责......................................507.2救援设备................................................527.3应急救援响应............................................547.4安全事故应急救援措施....................................558劳动力计划....................................................569计算书........................................................569.1塔机属性................................................569.2塔机荷载................................................579.3基础验算................................................589.4基础配筋验算............................................649.5配筋示意图..............................................66武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-1-1编制依据1)《施工组织设计》及其建筑、结构施工图纸2)《塔式起重机设计规范》GB/T13752-19923)《建筑地基基础设计规范》GB50007-20114)《建筑结构荷载规范》GB50009-20125)《混凝土结构设计规范》GB50010-20106)《建筑桩基技术规范》JGJ97-20087)《塔式起重机混凝土基础工程技术规程》JGJ/T187-20098)《建筑机械使用安全技术规程》(JGJ33-2012)9)《塔式起重机安全规程》GB5144-200610)《建筑施工塔式起重机安装、使用、拆卸安全技术规程》JGJ196-201011)《重要用途钢丝绳》GB8918—200612)《施工现场临时用电安全技术规范》(JG46-2005);13)危险性较大的分部分项工程安全管理办法(建质[2009]87号文);2工程概况2.1设计概况武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站为地下四层双柱三跨盖挖逆作岛式站台车站。车站外包总长217.36m,标准段总宽25.3m,小里程盾构井基坑深35.962m,大里程盾构井基坑深35.53m,车站中心里程处埋深约34.16m,基底位于细砂层,主体基坑总面积11000m²。徐家棚站围护结构支护形式地下连续墙,地下连续墙深度约60m,墙底入中风化岩层1m,墙体厚为1.5m及1m两种;主体结构梁板系统作为基坑开挖阶段围护结构的水平支撑系统,地下四层两端盾构井因层高较高,增设两道Ф武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-2-609钢支撑。2.2地理位置及工程范围徐家棚站布置于和平大道与秦园路交叉路口以东的秦园路下,位于和平大道东南侧。车站北侧为337库房及民房,南侧为惠誉花园小区,武昌区环卫局宿舍,东侧为在建的滨江城市花园;西侧为徐家棚加油站。平面位置如下:车站平面位置示意图2.3工程地质及水文地质2.3.1工程地质1、地形地貌根据勘察结果,拟建工程场地地貌单元属河流堆积平原,属长江Ⅰ级阶地,地形平坦。地表高程介于22.37~23.97m之间。拟建场地表层填土工程性能差,硬壳层(可塑粘土)强度中等,工程性能一般,其下粉质粘土、淤泥质土及互层土强度低,工程性能差,中部砂土层强度稍高,工程性能一般,下伏第三系基岩较完整。武汉市轨道交通七号线一期工程第九标段土建工程徐家棚站塔吊安拆安全专项方案-3-2、地层构成场地地层构成表代号土名土层描述层厚(m)层顶埋深(m)1-1杂填土结构不均、土质松散0.8~4.31-2素填土稍密,局部松散0.7~3.00.8~2.61-3淤泥质粘土流塑,饱和1.0~2.21.5~2.13-1a粘土可塑,软塑,饱和0.9~5.01.0~4.33-3淤泥质粘土流塑,饱和1.0~5.33.4~6.83-4粉质粘土夹粉土软塑,饱和0.9~6.95.4~9.83-5粉质粘土、粉土、粉砂饱和、软塑、稍密-中密2.4~5.68.8~12.74-1b粉砂夹粉土、粉质粘土饱和、软-可塑1.3~5.68.8~5.84-1粉细砂饱和、稍密-中密4.5~11.412.8~19.34-2细砂饱和、中密1.1~19.419.9~38根据勘察结果,塔吊基础施工范围内由上至下主要地层为:杂填土层、粉质粘土层、粉质粘土夹粉土层、粉砂夹粉土粉细砂、细砂。2.3.2水文地质条件(1)地表水本站地处河流堆积平原地貌单元(相当于长江Ⅰ级阶地)。场地