普立(滇黔界)至宣威高速公路第十合同段普立(滇黔界)至宣威高速公路第十合同段临临时时用用电电管管理理方方案案浙江八咏公路工程有限公司普立(滇黔界)至宣威高速公路第十合同段2012年7月21日目录一设计依据及原则···················································31、设计依据························································32、设计原则························································3二、技术措施··························································31、接地防雷························································32、安全用电························································43、电气设备设置·················································44、漏电保护器安装设置········································55、电气设备的安装··············································56、电气设备的使用和维护·····································6三、用电管理·························································71、用电组织管理·················································72、电箱管理规定·················································83、电装置维修管理规定········································84、电气安全生产管理制度·····································95、电工操作规程·················································96、预防电气火灾措施···········································9四、安全技术交底···············································101、安全用电自我防护技术交底······························102、电工安全技术交底··········································113、焊接机械安全技术交底····································113施工现场临时用电管理方案一设计依据及原则1、设计依据⑴《建设工程施工现场供用电安全规范》GB50194-93;⑵《施工现场临时用电安全技术规范》JGJ46-2005;⑶《低压配电设计规范》GB50054-95;⑷《供配电系统设计规范》GB50052-95;⑸《通用用电设备配电设计规范》GB50055-93;⑹甲方提供的现场电源资料;⑺现场临时用电设备负荷和配置资料。2、设计原则(1)满足施工用电设备要求,合理选择电力线、开关、漏电保护器等电器设备。(2)采用“三相五线制”供电系统,PE线电气设备连接要严格按防雷接地要求规定安装。(3)满足施工安全用电原则,认真做好保护接地、保护接零,电器设备的金属外壳、框架必须接地,保护接零采用TN-S接零保护用电系统,以免发生触电事故。(4)执行设计、施工和验收制度,施工用电由电力工程师根据现场实际情况参照用电安全规范进行设计,专职电工按图组织施工;由电力工程师组织安全员、质检员、施工负责人和电工参加对用电线路、电器安装进行验收。二、技术措施1、接地防雷(1)所有电气设备的金属外壳与保护零连接,专用保护零由工作接地线、配电室的第一级漏电保护器侧的零线引出,施工现场的所有电气设备在正常情况下不带电的外漏导电部分,应做保护接零,包4括以下五个部分:1)电机、变压器、电器、照明器具、手持电动工具的金属外壳。2)电器设备传动装置的金属部分。3)配电屏与控制屏的金属框架。4)室内外配电装置的金属框架及靠近带电部分的金属围栏和金属门。5)电力线路的金属保护管、敷设的钢管(钢索)、起重机轨道、钢管外架镝灯等。(2)保护零线不得装设备开关和熔断器。(3)保护零线的截面不小于25m2,采用多股铜线,不准使用独股铝线。(4)保护零不准与工作零混用,保证工作零、保护零分别使用;保护零线严禁通过工作电流。(5)保护零采用五芯线从变压器中性点至总配电箱——分箱——开关箱到各种机械设备连通。(6)作防雷接地的电气设备,必须同时作重复接地。外用电梯、外架、塔吊的接地体,应制作独立的接地装置,用角钢、钢管、圆钢制作,不得使用螺纹钢。接地电阻值不大于10Ω,防雷冲击电阻不大于30Ω(7)在总配电箱、分配电箱做重复接地,每一重复接地装置的接地电阻值不应大于10Ω。2、安全用电在特别潮湿环境条件下、场所、工作采用安全电压照明。3、电气设备设置(1)配电系统设置室外防水总配电箱、分配电箱和开关箱及流动电箱,开关箱与分配电箱距离不超过40m,开关箱至用电设备的距离不超过3~5m。(2)照明线路设在各级配电箱的右侧,由动力开关上侧引入,并5安装照明漏电保安器,照明线路不得和动力线混合使用空开。(3)每台用电设备都必须设置独立漏电保安器,严禁用一个开关控制两台以上的电气设备。(4)配电箱、开关箱中导线的进出口应设在箱体的底下,严禁设在箱体的上顶面、侧面、后面或箱门处。(5)配电箱统一购买合格的产品,由现场电工负责保管和使用。(6)配电箱、开关箱应装设在干燥、通气及常温场所,不得装设在易受外来固定撞击、强烈震动、液体浸渐及热源烘烤的场所,周围不得碓房有碍操作、维修的物品。(7)配电箱、开关箱应装设端正、牢固,移动式的箱体应装设在坚固的支架上,固定式配电箱、开关箱的下皮与地面的垂直距离应大于1.3m,小于1.5m,移动式的下皮与地面的垂直距离为0.6~1.5m。4、漏电保护器安装设置(1)漏电保护器安装设在配电箱电流隔离开关的负荷侧和开关箱电源隔离开关的负荷侧。(2)漏电保护器安器选用泄露电流型漏电保护器,其漏电动作电流不大于30mA,总配电箱漏电动作电流放宽到80mA,额定漏电动作小于0.1s。(3)若漏电保护器安装具备过负载和短路保护功能,可不设分路熔断器和自动开关。(4)使用于特别潮湿和有腐蚀介质场所的漏电保护器应采用防溅型产品,其额定漏电动作电流不应大于15mA,额定漏电动作时间应小于0.1s。(5)漏电保护器必须按产品说明书安装、使用,对搁置很久,重新使用和连续使用一个月的漏电保护器,要认真检查其特性后方可使用,发现问题及时更换。5、电气设备的安装(1)配电箱、开关箱内的电器安装在绝缘板上,然后整体紧固在6箱体内。电器设备之间、设备与板四周的距离应符合有关工艺标准的要求。(2)电箱、开关箱内的工作零线应通过接线端子板连接,并应与保护零线接线端子板分设。(3)配电箱、开关箱内的连接线应采用绝缘导线,导线的型号及截面应严格执行临电图纸的标示截面,导线接头不得松动,不得有外露带电部分。(4)各种箱体的金属构架、金属箱体、金属电器安装板以及箱内电器的正常不带电的金属底座外壳等必须做保护接零,保护接零应通过接线端子连接。(5)配电箱后面的排线需排列整齐,绑扎成束,并用卡钉固定在盘板后,引出及引入的导线应加护套分路成束并做防水弯或留出适当余度,以便检修。移动箱的进、出线须用橡皮绝缘电缆。(6)导线剥削处不应伤线芯过长,导线压头牢固可靠,多股导线不应盘圈压接,应加装压线端子。6、电气设备的使用和维护(1)施工现场所有的配电箱、开关箱应每月进行一次检查和维修。检查、维修人员必须是专业电工。检查、维修时必须按规定穿、戴绝缘鞋、手套,必须使用电工绝缘工具。(2)检查、维修配电箱、开关箱时必须将前一级相应的电源开关分闸断电,并悬挂停电标示牌,严禁带电作业。(3)配电箱内盘面上应标明各回路名称,用途,同时要做出分路标记。(4)总、分配电箱应配琐,配电箱和开关箱应指定专人负责。(5)各配电箱内不允许设置任何杂物,并应保持洁净,不得挂接其他临时用电设备。(6)施工现场内临时用电的安装和维修或拆除必须经过培训后取7得上岗证书的专业电工完成,电工的等级应同工程难易程度和技术复杂性相适应,初级电工不允许进行中、高级电工作业。(7)所有配电箱、开关箱在使用过程中必须按以下操作顺序:1)送电:总配电箱——分配电箱——开关箱2)停电:开关箱——分配电箱——总配电箱(8)施工现场停工作业1h以上,应将动力开关箱断电上锁。(9)用电人员应作到:1)掌握安全用电基本知识和所用设备的性能。2)使用设备前必须按规定穿戴和配备好相应的劳动保护用品,并检查电气装置和保护设施是否完好,严禁设备带“病”运转。3)停电的设备必须拉闸断电,锁好开关箱。4)负责观察所用设备的负荷情况、保护零线和开关箱,发现问题,及时报告解决。5)搬迁或移动用电设备,必须经电工切断电源并作妥善处理后进行。三、用电管理1、用电组织管理(1)现场用电由安全工程师编制交底,项目经理、技术经理负责管理,电工工长负责指导,现场电工负责使用。(2)建立技术交底制度,本组织设计编写未尽之处由现场工长做详细安全交底,电气工程师向专业电工、各类用电人员介绍临时用电组织设计和安全技术交底措施的总体意图、技术内容和注意事项,并在技术交底文字中履行交底和被交底人签字手续,注明交底日期。(3)建立安全检查制度、从临时用电、送电开始,每月四次对临时用电工程进行检查,主要内容是:接地用阻值、电气设备绝缘电阻值、漏电保护器动作参数等,以监视临时用电工程是否安全可靠,并做好检查记录。(4)建立电气维修制度,加强日常定期维修工作,及时发现和清8除隐患,并建立维修记录,记载维修时间、地点、设备、内容、技术措施、处理结果、维修人员、验收人员等。(5)建立电气拆除制度,建筑竣工后,临时用电拆除工作应有统一的组织和指挥,并须规定拆除时间、人员、程序、方法、注意事项和防护措施。(6)建立安全用电责任制,对临时用电各部位的操作责任、维修分片、分块、电箱分人、设备分级落实责任到人头,并辅助必要的奖惩。2、电箱管理规定(1)非电工人员,严禁乱操作电气设备。(2)操作人员使用各种电器设备时,必须认真执行安全操作规程,并服从电工的安全技术指导。(3)任何单位和个人不得指派无电工操作证人员进行电气设备的安装、维修工作,更不准强令电工违章操作。(4)专业电工有权制止一切违章用电行为,有权向安全部门报告。(5)电箱就位后,经验收合格后方可使用。3、电装置维修管理规定(1)进行维修前必须将前一级电源开关分闸断电,并悬挂停电标志牌,然后用验电器检查确认被维修装置断电后,方可进行维修。(2)维修时必须二人在场,一人维修,一人监护,不得随意改变原配电装置接线,不得随意拆除原电气。(3)维修人员必须是熟悉配电装置的专业电工,使用绝缘工具,佩戴劳保用品。(4)更换电气必须与原规格一致,禁止使用不合格的代用品。(5)维修结束应脱离配电装置,然后由电源侧开始逐级合闸通电,用验电器确认电源接通后,再给下一级通电试验,然后摘除上一级电源开关上悬挂的停电标志牌。94、电气安全生产管理制度(1)工程开工前,必须编制施工用电方案,并向电工进行全面的安全技术交底。(2)项目经理部应有专人管理暂设电气工程,线路、设备安装后进行验收,合格后方可送电。(3)安装、维护暂设电气设备,必须严格执行《临时施工用电管理办法》。(4)对施工用电设备必须定期进行检查

1 / 12
下载文档,编辑使用

©2015-2020 m.777doc.com 三七文档.

备案号:鲁ICP备2024069028号-1 客服联系 QQ:2149211541

×
保存成功