1目录一、编制依据·························································21.1编制依据······················································21.2编制原则······················································2二、工程概况·························································2三、冬季施工总体筹划·················································33.1XX市冬季气温情况············································33.2冬季施工期限确定··············································43.3冬季施工总体部署··············································4四、冬季施工措施·····················································84.1施工降水保温措施··············································84.2土方开挖冬季施工防滑措施······································84.3钢支撑安装冬季施工措施········································94.4主体结构冬季施工措施··········································9五、安全措施·························································155.1施工现场安全措施··············································155.2冬季施工用电安全措施··········································165.3冬季施工防火措施··············································165.4冬季施工防风安全措施··········································175.5机械设备冬季防寒、防冻、防火措施································17六、质量保证措施·····················································176.1冬季施工温度监管措施··········································176.2冬季施工试块管理··············································186.3泵送混凝土质量保证措施········································18七、安全文明施工措施·················································187.1冬季施工安全教育··············································187.2现场安全管理··················································187.3冬季施工消防管理··············································192冬季施工专项方案一、编制依据1.1编制依据1、《建筑工程冬期施工规程》(JGJ104-97)2、《地下铁道工程施工及验收规范》(GB50299-1999)(2003版);3、《建筑基坑工程技术规范》(YB9258-97);4、《建筑桩基础桩基技术规范》(JGJ94-2008);5、《建筑基坑支护技术规程》(JGJ120-2012);6、《建筑地基基础设计规范》(GB50007-2011);7、《XX地区建筑地基基础设计规范》(DGJ32/J12-2005);8、现行其他的施工验收规范、规程和标准,省、市有关建筑技术、质量、安全和文明的规定;9、XX工程施工设计文件10、XX施工合同文件11、本单位公司现有的技术、管理水平及以往类似工程的施工经验。12、XX市气温气候条件。1.2编制原则严格执行国家及XX市政府所制订有关冬季施工的法律、法规和各项管理条例,并做到模范守法、文明施工。根据本标段总体施工进度计划安排,有针对性对冬季施工项目采取保护措施。以成熟的施工技术及先进的设备,确保冬季施工安全和工程质量,按期为业主提供一个优质的工程产品。二、工程概况XX站:XX站位于XX地区XX村、XX路北侧,与规划XX地铁七号线换乘,为地下两层双柱岛式站台。车站长211.5m,标准段基坑宽21.7m,深15.492m盾构井段基坑宽26.1m,深17.064m(局部深18.274m)。车站采用地下连续墙+内支撑进行基坑支护、明挖顺筑法施工。车站共设置4个出入口、2组风道。车站对应地表规划3为友谊路,规划标高8m,现状地面标高6.5m~7.5m。规划远期地铁7号线区间下穿本站。XX站:XX站为XX工程中间站,位于规划XX与XX路路口,沿江东南路呈东西向设置,XX站设计为地下二层两跨岛式站台车站,车站总长189.7m,车站标准段宽19.2m,高13.33m。车站采用地下连续墙+内支撑进行基坑支护、明挖顺筑法施工。车站共设置4个出入口、2组风道。沿车站方向有规划新交通有轨电车,车站结构外墙与新交通路基桩基础最小距离2.08m。XX站~XX站区间:XX站~XX路站区间位于南京河西地区,起至XX站,沿规划友谊路向北,经XX村,于里程YCK10+150m处拐向西行,接XX路站。区间设计起点里程为YCK9+575.125m,终点里程为YCK10+588.000m,双线全长2000.439m,覆土厚度约8.38~13.40m。区间隧道左、右线平面分别设置一条半径R=350m平曲线,左右线线间距13.500~19.430m;区间隧道线路纵坡设计为“V”形坡,最大纵坡10.4‰,最小竖曲线半径R=3000m,在YCK10+133.500m位置设置联络通道兼排水泵站一座,联络通道线间距18.88m。XX路站~XX路站间:XX路站~XX路站区间位于XX地区,现场地为拆迁区,与XX路、XX路交叉。该区间南侧距离XX河约1.5km。此外,该区间中部有一条中心河交叉而过,宽约11m;该区间还穿过XX河,宽约12m。区间设计起点里程为YCK10+776.100m,终点里程为YCK11+485.100m,双线全长1422.836m。区间隧道左、右线平面分别设置一条半径R=1000m平曲线,左右线线间距13.500~16.000m;区间隧道线路纵坡设计为“V”形坡,最大纵坡10.61‰,最小竖曲线半径R=3000m,覆土厚度约8.39~11.96m。于YCK11+131.75m位置设置联络通道兼排水泵站一座,联络通道线间距14.09m。三、冬季施工总体筹划3.1XX市冬季气温情况XX属北亚热带湿润气候。XX处于西风环流控制之下,季风显著,四季分明,冬季受欧亚大陆气团影响较深,天气晴朗、寒冷、干燥。XX的全年平均气温为15.6℃,冬季(12月、1月、2月)平均气温为3.7℃;11月到次年3月的平均气温分别为410.6℃,4.5℃,2.3℃,4.3℃,8.8℃。3.2冬季施工期限的确定3.2.1温控:根据《建筑工程冬期施工规程》(JGJ104-97)的规定,当室外日平均气温连续5d低于5℃,即进入冬季施工期;当室外日平均气温连续5d高于5℃时,解除冬期施工。3.2.2时控:根据XX地区气候特点,本工程冬季施工时间除执行国家规范的具体规定外,原则上应为每年11月20日~次年3月20日,且注意上述时间范围之外的气温突降。3.3冬季施工总体部署3.3.1成立冬季施工领导小组项目部成立冬季施工领导小组,小组设总负责1人,由项目经理担任;副组长2人,其中:施工副组长1人,由项目副经理担任,技术副组长1人,由项目总工程师担任;组员为:工程技术部、安全质量部、物资设备部、财务部、综合办公室及工地试验室。冬季施工组织机构图冬季施工人员表组长工程技术部安全质量部工地测量队综合办公室物资设备部工地试验室施工副组长技术副组长5序号人名职责联系电话1XX组长XX2XX施工副组长1XX3XX技术副组长XX4XX物资负责人XX5XX安质负责人XX6XX工程负责人XX7XX试验负责人XX8XX测量负责人XX9XX办公室负责人XX3.3.2各岗位岗位职责1、组长职责负责本工程冬季施工的全面管理工作。负责组建冬季施工组织管理机构;贯彻执行国家有关冬季施工的法律、法规、方针、政策和强制性标准等;组织编制冬季施工方案,并组织实施、督促检查及处理突发事件;负责冬季施工所需的人员、物资、设备及资金等调配工作;建立冬季施工质量和安全管理体系并使之有效运行。2、技术副组长职责负责本工程冬季施工的全面技术管理工作。组织编制本工程冬季施工的实施性冬季施工方案、各类冬季施工措施、冬季施工的质量安全保证措施及有关冬季施工的应急预案等;组织技术人员进行全面、详细的技术交底;组织技术人员做好冬季测量放线、放样、点位保护及日常施工测量等关键工作;组织做好冬季施工的成本控制核算;参与定期性质量检查验收、问题处理及不断完善冬季施工方案。3、施工副组长职责负责冬季施工的生产组织、指挥和协调,是本工程冬季施工的质量、安全、进度、文明施工和队伍管理的直接负责人。组织编制冬季施工的具体施工计划,并监督执行;组织落实冬季施工方案、主要工程项目冬季施工措施、设备、设施的冬季6施工措施、冬季施工安全措施、冬季施工工期保证措施及冬季施工物资准备计划等具体工作;组织定期性质量检查验收,对出现的问题及时采取措施、解决处理,并不断完善冬季施工方案。4、工程技术部职责负责本工程冬季施工过程中的技术管理。编制本工程冬季施工的实施性冬季施工方案、各类冬季施工措施、冬季施工的质量安全保证措施及有关冬季施工的应急预案等;负责重点技术问题攻关,技术交底,检查指导作业工区的技术工作;参与定期性质量检查验收、问题处理及不断完善冬季施工方案。5、安全质量部职责负责本工程冬季施工过程中的安全、质量管理工作。编制本工程冬季施工的质量保证措施、检查督促各作业工区现场质量管理工作;负责冬季施工过程中的安全生产管理;负责制定本工程冬季施工的安全保证措施、管理方案及应急预案等;制定各工种冬季施工操作规程,对安全生产、劳动保护进行监督检查。6、物资设备部职责负责本工程冬季施工的生产物资、设备的采购、租赁、验收及供应等管理工作。编制、调整及优化冬季施工所需设备、配件及材料的供应计划,并组织按时到位,确保冬季施工生产顺利进行;负责冬季施工过程中现场物资设备的维护与保养,确保机械设备在低温环境下正常运转。7、财务部职责负责本工程冬季施工中的资金保证工作。组织与筹措本工程冬季施工生产所需资金,并保证资金的落实;参与研究和开展冬季施工的成本核算工作。8、综合办公室职责负责本工程冬季施工过程中的日常管理工作。负责冬季施工所需的劳力调配;负责制定适宜于冬季施工的环境保护方案和环保措施,并进行相应监测;负责冬季施工中的后勤生活服务管理工作。9、工地试验室职责负责对本工程冬季施工中的送检材料进行检测及进行适宜于各种气候条件下的混凝土配合比、外加剂、钢筋加工等有关试验工作。负责冬季施工测温记录工作。73.3.3冬季施工总体部署由于受工期制约,本工程的混凝土浇筑冬季施工是不可避免的,在冬季施工期间应对搅拌站及时提出对原材料,外加剂及到达现场时的混凝土温度等技术要求,以