雨季施工方案二〇一三年五月十九日1目录一、编制依据..................................................................1二、适用范围..................................................................1三、雨季施工主要工作内容......................................................1四、雨季施工保证措施..........................................................11、雨季施工组织措施.........................................................12、雨季施工管理措施.........................................................13、防汛抗洪措施.............................................................24、现场布设与机械材料保证措施...............................................25、施工生产保证措施.........................................................2(1)道路施工......................................................................................................................4(2)涵洞施工......................................................................................................................56、排水系统、排水设施情况...................................................77、安全保证措施.............................................................78、环保措施.................................................................89、防汛降水主要材料、机具、劳动力...........................................8五、应急救援组织机构及职责....................................................91、组织机构.................................................................92、职责.....................................................................9六、预防预警及救援...........................................................101、预防预警准备.............................................................92、险情等级划分.............................................................93、发生较大或重大险情时的救援程序..........................................10七、恢复正常状态的原则和程序..................................................101、恢复正常状态的原则......................................................102、恢复正常状态的程序......................................................113、后期处置................................................................11八、防汛应急预案.............................................................111、组织体系................................................................112、应急救援组织的职责......................................................113、应急救援组织主要部门职责................................................124、重点检查监控内容........................................................135、施工现场的防汛措施......................................................146、重特大事故报告和现场保护................................................147、机械、人员、材料撤离措施................................................158、雨季施工安全措施........................................................159、施工资料撤离保护措施....................................................1610、事故应急救援措施.......................................................17九、预案的培训与演练.........................................................181、演练目的................................................................182、演练时间及内容..........................................................183、演练地点................................................................184、参加演练人员............................................................185、演练组织机构............................................................186、各工作组职责............................................................1927、演练组织指挥............................................................208、演练内容及程序..........................................................20十、附则.....................................................................201、预案管理与更新..........................................................202、奖励与责任追究..........................................................203、预案备案................................................................204、预案实施时间............................................................201标雨季施工方案一、编制依据为提高抗御建筑施工特大安全事故的快速反应能力,防止本工程一旦发生汛情,保障施工安全和人身安全,最大限度的减少事故损失,维护社会稳定,迅速排除汛情造成的危险,减少损失,特制定本预案。二、适用范围本《雨季施工方案》适用于本项目雨季防汛措施工作。三、雨季施工主要工作内容本标段重要工作:全线路基填筑,涵洞施工。根据地区雨季时间,雨季和行洪期一般在6月至9月,而此时间正是我合同段全面施工的季节。雨季施工任务繁重,为确保工程质量,搞好安全生产,保证各项计划指标任务的完成,必须做好雨季施工各项准备工作,才能保证本工程顺利进行。四、雨季施工保证措施1、雨季施工组织措施(1)雨季施工主要以预防为主,采取防雨措施及加强排水手段。为了使工程顺利进行,不耽误工期,及时收集气象信息,详细调查并掌握当地水文资料,做好施工中的防雨措施,对职工进行雨季施工和防汛抗洪教育。(2)防汛器材、防雨材料、抽排水设备充足,对主要材料工具要估计在雨季期间的储备量,施工人员配备必要的雨季劳动保护用品。(3)生产生活区保持排水系统通畅,并与原有排水系统相适应。(4)为保证工程质量,雨季尽量不安排路基土方的填筑施工,视实际的天气情况,可安排路基土方的弃方施工,以充分利用雨季中的间歇时间,做到科学、合理地安排和组织施工生产,尽可能地提高工效。2、雨季施工管理措施(1)加强组织领导,有针对性的进行抗洪防汛安全教育,提高广大职工的抗洪防汛意识和警觉性。2(2)在雨季、汛期到来之前,开展抗洪防汛大检查,重点检查抗洪防汛方案是否可行,职工住房环境、设备停放地点、材料储存场所等是否安全可靠,排水、防水设施是否齐备等。并认真执行雨季、雨后两检查制度。(3)积极与当地气象局联系,及时收集气象信息,并向各施工队发布信息。(4)项目经理部成立防汛抗洪领导小组,在雨季、汛期,各施工队在项目经理部统一领导下,组成应急突击队,明确责任,落实到人。(5)坚持值班制度,遇有险情及时组织力量抢修,及时与当地政府取得联系。(6)汛期加强与其它兄弟单位的联系,互相配合,相互支持。3、防汛抗洪措施项目经理部成立防汛抗洪领导小组,制定防洪抢险措施。在汛期各施工队在抗洪领导小组统一领导下,做好防汛抗洪工作。与当地气象部门取得联系,及时了解汛情。4、现场布设与机械材料保证措施(1)施工现场合理布置,制定防汛预案,以防万一,确保人员安全。(2)生产生活区保持排水系统通畅,并与原有排水系统相适应。(3)便道应碾压坚实,并作好路拱,两旁设排水沟,保证雨后通行不陷。雨季前对现场已有的临时施工道路要进行一次平整铺垫,做到路面坚实平整,不沉陷、不积水、行车不打滑、不颠簸。(4)机械设备和材料全部存放在最高洪水位以上,防止浸泡。(5)防汛器材、防雨材料、抽排水设备充足,对施工人员配备必要的雨季劳动保护用品。5、施工生产保证措施(1)道路施工(一)雨季填筑路基,应根据使用机具的性能和数量,合理组织3几个工点或几个工作面轮流作业,紧凑衔接,快速施工,不宜全面铺开。(二)高速公路路基边坡设置临时排水急流槽,采用砂浆弧形临时排水急流槽,位置按设计位置,根据现场情况在主线实际低填方位置增设左右各2个,以减少冲刷对路基的危害。路基基础较高时,两侧人工做好土埝,确保