中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程1目录1.编制依据.............................................32.工程概况.............................................32.1工程简介.................................................32.2模板工程特点.............................................42.3模板选型.................................................43.施工部署.............................................43.1质量目标.................................................43.2模板工程质量控制系统及职责...............................53.3场区安排.................................................53.4模板工程料场安排.........................................53.6流水段的划分.............................................63.8模板配置.................................................73.7劳动力安排...............................................84.施工准备.............................................84.1技术准备.................................................84.2物资准备.................................................84.3机械设备准备.............................................95.施工方法.............................................95.1底板集水坑模板施工.......................................95.2底板、反梁板施工........................................105.3后浇带模板施工及保护....................................115.4独立柱模板施工..........................................135.5梁、板模板施工..........................................145.6楼梯模板施工............................................165.7门窗洞口模板施工........................................175.8电梯井筒................................................185.9墙体模板施工............................................195.10模板的拆除.............................................22中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程25.11模板的维修及修理.......................................226、质量标准和控制.....................................236.1模板加工质量标准........................................236.2模板施工安装验收质量标准................................236.3模板施工质量预控措施....................................247、成品保护与文明施工.................................247.1成品保护................................................247.2安全文明施工............................................257.3环境保护措施............................................25附表--1钢木组合大钢模计算书..............................25附表--2梁、板模板验算...................................27附表--4柱箍计算........................................28附表--5吊钩验算........................................29中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程31.编制依据1.1《中国科学院大气物理研究所综合科研楼工程施工组织设计》1.2中国科学院大气物理研究所综合科研楼工程施工合同2.工程概况2.1工程简介本工程结构形式为剪力墙框架钢筋混凝土结构,地下一层,地上六层,总建筑面积为10473.07m2(其中地下1635.48m2,地上8805.72m2)。主体结构基础形式为筏板基础。具体形式见下表。序号部位内容1底板部位结构形式截面尺寸结构主体基础筏板基础底板厚度为600m,底板反梁尺寸400×1200mm,700×1200mm,850×1200mm。下沉广场挡土墙基础条形基础尺寸为3000×400(250)mm。首层门厅柱基础独立基础尺寸为1600×1700×600mm,1800×1800×600mm,2400×2400×700mm。2地下1层部位截面尺寸备注(层高4.43m)竖向结构墙体外墙:300mm内墙:200mm,250mm,300mm,400mm框架柱600×600mm,600×700mm,730×300mm,600×1200mm下沉广场挡土墙400(300)mm水平结构顶板人防顶板360mm,外挑板100,其余180mm顶板标高不同顶板梁300×530mm,400×530mm,400×1150mm,300×600mm,400×400mm3地上1至6层(层高3.3m)竖向结构墙体200mm,250mm,300mm,400mm首层层高3.9m框架柱600×600mm,600×700mm,730×300mm,600×1200mm首层门厅框架柱400×500mm,600×600mm顶板100mm,120mm,130mm,160mm,220mm顶板梁首层200×400mm,200×530mm,300×530mm,300×750mm,400×530mm,400×600mm,250×530mm,400×800mm中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程43地上1至6层(层高3.3m)竖向结构顶板梁二层200×400mm,250×530mm,250×1330mm,300×530mm,300×750mm,300×630mm,300×1100mm,400×530mm,400×600mm,400×1630mm,三层200×400mm,200×530mm,300×530mm,300×430mm,400×530mm,300×750mm,400×600mm四层200×400mm,200×530mm,250×530mm,300×530mm,300×750mm,400×530mm,400×600mm五层200×400mm,300×530mm,300×600mm,300×750mm,300×500mm,400×530mm,400×530mm,400×600mm六层200×400mm,300×530mm,300×1150mm,300×600mm,400×530mm,400×600mm,400×1300mm2.2模板工程特点2.2.1模板作为一种周转性材料,在施工质量中起着关键性的作用,对施工工期、成本投入、质量控制(尤其砼的外型尺寸、外观质量)有着重要性影响,为了达到施工精品质量目标,本模板方案设计主要满足模板实用、科学、先进性要求。2.2.2地下室、首层、二层以上各层高不同,造成模板之间不能流水使用,墙模较难处理。2.2.3工期紧,不利于模板周转。2.3模板选型根据本工程施工工期较短、质量标准高的特点,模板综合选型为序号使用部位模板选型主要支撑体系1筏板基础底板240砖台模2墙18mm双面覆模多层板100*100木方、φ48钢管3柱18mm双面覆模多层板100*100木方、槽钢、φ48钢管4梁、板18mm双面覆模多层板100*100木方、碗口式脚手架3.施工部署3.1质量目标中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程5满足合同要求,质量合格的目标,同时我方将确保对业主的承诺。确保本工程达到“结构长城杯”,分部分项一次交验合格率达到100%。3.2模板工程质量控制系统及职责李文慧:负责整个质量体系的管理和决策。李蕴飞:负责日常技术管理工作及检查技术交底的落实情况。徐歆炎:负责现场的生产协调和质量监督工作,并指导施工。刘守虎:负责各个施工环节质量的验收。缪荣:负责整个木工组的施工协调生产。邢建军:负责墙体模板施工的过程控制和质量验收。陆长云:负责顶板模板施工的过程控制和质量验收。吕建国:负责木工后台预制模板的过程控制和质量验收。3.3场区安排3.3.1根据现场情况和吊运能力,在场区南侧设置封闭式木工棚,木工棚地面做混凝土硬化处理,上部搭设防雨棚。木工棚必须满足相关消防要求。3.3.2地下结构施工期间模板堆放场地设在场区西南角。3.4模板工程料场安排根据工程的特点,本工程所选用模板的类型比较多所以各个类型模板应分类堆放保管,以保证施工方便。3.4.1模板堆放区内模板堆放须分规格、分类型,模板堆放区设一出入口,左右各设一标识牌,标明模板适用范围、吊运、保养方法、使用、安全、质量等施工中注意事项。堆李文慧刘守虎李蕴飞徐歆炎南通六建项目经理部木工工长:缪荣木工质检:邢建军、陆长云木工加工:吕建国中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程6放区内设一工具架,用于放置自制角尺、拖布(两把:一把用于模板清理;另一把用于脱模剂涂刷)、清洗桶、工具、铁铲、扫帚等维护、保养、堆放工具。所有堆放区钢管均刷红、白漆,并在内侧满挂密目安全网;地面用C10混凝土(厚50mm)硬化,平整度要好。模板堆放设专人负责模板堆放和标识工作。3.4.2墙体、柱模板类型为木模板,根据场地和施工要求,木模堆放维护区设在模板加工场西面,四周设2米高防护架。堆放场区四周挖好排水沟,地面坡向排水沟,防止地面积水。3.4.3墙体模板按照使用部位进行分类,同一使用部位的模板集中堆放,并设置明显标志。3.4.4堆放模板时采取两块模板板面相对的方式,平放在堆放区。3.6流水段的划分地下结构分别按照各自的后浇带来划分施工段,并分别在各自的施工区域流水施工。施工段划分见下图。中建七局模板施工方案中国科学院大气物理研究所综合科研楼工程713D111313A1/67HEⅠⅡⅢ后浇带分段线分段线Ⅳ地上施工流水段示意图Ⅱ后浇带Ⅰ13D113A1/67H地下施工流水段示意图3.7施工缝位置3.7.1垂直施工缝:1.基础底板及反梁按后浇带设置。2.墙体及顶板梁在E轴南2.5m处设置一条施工缝(见上图)及后浇带设置。3.7.1水平施工缝1、底板、基