施工临时用电方案目录1.编制依据·················································································22.工程概况·················································································23.现场勘测·················································································24.电源进线、总配电箱、分配电箱等的位置及线路走向························25.负荷计算·················································································36.导线选择·················································································67.接地装置设置···········································································78.配电箱与开关箱设计及系统接地图················································89.电缆线路设计··········································································1110.室内配线············································································1111.安全用电技术措施和电气防火措施:········································1112.触电急救·············································································15施工临时用电方案21.编制依据(1)、《施工现场临时用电安全技术规范》JGJ46-2005;(2)、《低压配电设计规范》GB50054;(3)、《民用建筑电气设计规范》JGJ/T16;(4)、《供配电系统设计规范》GB50052;(5)、《建设工程施工现场供用电安全规范》GB50194;(6)、《用电安全导则》GB/T13869;(7)、《漏电保护器安装和运行》GB13955;(8)、《电气装置安装工程电气照明装置施工及验收规范》GB50259(9)、《电力建设安全工作规程》DL5009.2(10)、甲方提供现场电源资料;(11)、现场临时用电设备电荷及配置资料;(12)、《2013年江门市先进制造业江沙示范园区基础设施建设项目-污水管网工程(首期)施工组织设计。(13)、《建筑施工安全检查标准》(JGJ59—2011)为了贯彻JGJ46-2005《施工现场临时用电安全技术规范》,适应施工现场临时用电设计的要求,确保2013年江门市先进制造业江沙示范园区基础设施建设项目-污水管网工程(首期)的安全文明施工,根据现场实际情况,特编制本工程施工现场的临时用电方案。2.工程概况本工程位于江门市先进制造业江沙示范园区,由江门市先进制造业江沙示范园区投资有限公司投资兴建。此工程为市政基础设施工程,其中包括新建污水管长约2640米,改建雨水管长约1000米,雨污水管≤d1500。该工程合同工期为90天,计划工期2013年7月25日起,至2013年10月22日竣工。3.现场勘测经现场实地勘测,本工程无地下管线和沟道等,无需防护处理。施工临时用电从变压器引出。施工现场建筑材料、器具堆放位置、用电设备装置等布置详见施工现场平面布置图。4.电源进线、总配电箱、分配电箱等的位置及线路走向施工临时用电方案34.1本工程施工现场临时用电总电源由建设单位指定的变压器引出,设电表后引至施工现场。配电采用三级配电和三级过载与短路保护系统。遵守分级分路规则、动照分设规则、环境安全规则:总配电箱--分配电箱--开关箱--用电设备。配电箱、开关箱逐一编号,所运行的开关箱均有专人负责,整个施工现场有持证电工按时检查,以防触电伤害事故发生。4.2配电线路经建设单位同意施工单位引入总配电箱后,由总配电箱开始配电,用于现场机电设备及辅助施工现场临时用电。严格按三相五线制(TN-S系统)覆盖施工现场。做到工作零线与保护零线严格分开。正常情况下不带电的金属外壳必须和保护零线相连接,工作零线仅用于负载(即220V照明及220V用电设备使用)。其中保护零线与其它各导线颜色应区别开来,采用绿/黄双色线。用电系统为电源中性点直接接地的220/380V三相四线制低压电力系统。接地保护系统采用TN-S接零保护系统。4.3线路布置配电线路采用放射式与链式相结合的原则。根据现场情况及施工平面布置图,设总电箱三个,总箱、分箱分布详见施工现场临时用电平面布置图。大部分电缆采用架空敷设,小部分电缆敷设于地下,各配电箱及开关箱内应按电气安装要求,装保险熔丝、电源隔离开关(铁壳开关),并切实做到一机一闸一漏一箱,所有配电箱均标明其名称、用途,并在各箱上作出分路标记及做好醒目标志,所有配电箱门配锁,配电箱和开关箱由专人负责,并设置防雨措施,施工现场停止作业一小时以上时,应将动力开关箱断电上锁。4.4发电机组布置施工作业面的地理位置和自然条件对临时用电工程造成影响及有困难时,必须就地采用柴油发电机进行发电施工作业。5.负荷计算5.1用电量计算由于施工现场临时用电由三路变压器分别引至施工现场,分设三个总配电箱,每个总配电箱下设分配电箱,各设配电线路。按照负荷最大线路考虑最不利状态,进行验算如下:施工现场主要用电设备参数表见下表:序号设备名称规格型号单位数量功率(KW)合计(KW)设备类型进场时间1泥浆泵3PN台21530电动机类按进度计划施工临时用电方案42潜水泵AS75-2CB台5315电动机类按进度计划3打夯机HC-70台133电动机类按进度计划4空压机YV9/7台11.51.5电动机类按进度计划5交流电焊机(KVA)BX1-315台21530电焊机类按进度计划6钢筋对焊机(KVA)UN-100台17070电焊机类按进度计划7平板式振动器ZB11台21.12.2电动机类按进度计划8钢筋调直机GW40台17.57.5电动机类按进度计划9插入式振动器ZX50台21.53电动机类按进度计划10钢筋弯切机Qj40-1台11515电动机类按进度计划11破路机台133电动机类按进度计划12砼切缝机台11.51.5电动机类按进度计划13木工圆盘锯台15.55.5电动机类按进度计划14砂浆机台15.55.5电动机类按进度计划15镝灯台13.53.5电动机类按进度计划16电动机总功率P1(KW)196.217备用发电机P2(KW)1005.2现场用电量选择:P=1.05(K1∑P1/COSφ+K2∑P2+K3∑P3)P1(电动机额定功率)=196.2kwP2(备用发电机)=100kwP3(室内照明及办公用电容量)=20kw。COSφ电动机的平均功率因数为0.75。K1、K2、K3需要系数参见表1。(此表经查建筑工程施工组织设计实例运用手册中所得)P=1.05×(0.6×196.2/0.75+100×0.6+0.8×20)=244.61KVA电源从各个变压器引出,现场甲方提供2台315KVA的变压器,每个总箱分别从一台变压器引出。由于本工程是市政基础设施工程,而且各分部工程都是分段进行施工,所以各种设备的进场及使用时间全部按施工进度计划进场及使用。经计算,满足施工现场用电名称K数值需要系数电动机K10.6发电机K20.6室内照明K30.8施工临时用电方案5临时用电要求。5.3施工现场配电线路5.3.1配电线路的设计:从总配电箱出来后,分三大线路供电,具体线路布置见施工平面布置图。配电线路的型式为200/380V三相五线制,基本保护系统用TN-S接零保护系统,并在专用保护零线上,做不少于三次的重复接地。5.3.2配电线路的结构:A.本工程大部分采用架空敷设电缆线路的方法,并应注意以下问题:(a)尽量选择最短线路。(b)尽量减少穿越各种道路,堆场次数。(c)线路架空敷设时要设置标志,不致受到各种机械损伤和腐蚀。(d)进出地面必须加设防护套管,最小内径为50mm。(e)电线杆采用水泥电线杆架空敷设,横跨大门或道路时,高度应≥6米。(f)橡皮电缆架空敷设时,应沿墙壁或电杆设置。严禁用金属裸线作绑线,电缆的最大弧垂距地不得小于2.5m。(g)架空供电线路必须用绝缘导线,以绝缘子支承,用专用电杆或沿墙架设,电杆的板线(接线)必须装设拉力绝缘子,拉力绝缘子距离地面不得小于2.5m,拉线索截面积不小于3×Φ4镀锌铁线。严禁供电线路架设在树木、脚手架上。(h)架设外供电线路时,施工操作人员必须遵守下列要求:①电杆使用小车搬运时,应捆绑卡牢;人工抬运时,动作要一致,电杆不应离地过高。②人工立杆,所用叉木应坚固完好;操作时,互相配合,用力均衡。机械立杆,两侧应设溜绳。立杆时坑内不得有人,基坑夯实后,方准拆去叉木或拖拉绳。③登杆前,杆根应夯实牢固。④登杆操作脚扣应与杆径相适应。使用脚踏板,钩子应向上。安全带应拴于安全可靠处,扣环扣牢,不准拴于瓷瓶或横担上。工具、材料应用绳索传递,禁止上下抛扔。⑤杆上紧线应侧向操作,并将夹紧螺栓拧紧。紧有角度的导线,应在外侧作业。调整拉线时,杆上不得有人。⑥紧线用的铁丝或钢丝绳,应能承受全部拉力,与导线的连接,必须牢固。紧线时,导线下方不得有人。单方向紧线时,反方向应设置临时拉线。⑦电缆盘上的电缆端头,应绑扎牢固。放线架、千斤顶应设置平稳,线盘应缓慢转动,防止脱杆或倾倒。电缆敷设至拐弯处,应站在外侧操作。施工临时用电方案6⑧室外供电线路的架设高度不得小于2.5m,并应保证人员正常活动不能触及供电线路。⑨一切称动式用电设备的电源电缆全长不得有驳口,外绝缘层无机械损伤。B.本工程小部分采用地下埋设电缆线路的方法,并应注意以下问题:(a)尽量选择最短线路。(b)尽量减少穿越各种道路,堆场次数。(c)线路埋地时要设置标志,不致受到各种机械损伤和腐蚀。(d)进出地面必须加设防护套管,最小内径为50mm。C.电缆类型和截面选择架空敷设电缆选用BX型铜芯橡皮线,电缆的截面采用具有专用保护零线的五芯电缆。埋地电缆选用BX型铜芯橡皮线,电缆的截面采用具有专用保护零线的五芯电缆。D.室内配线采用明配线。E.负荷线(a)电动建筑机械:手持电动工具及移动式开关箱的进出线,移动式照明器的电源线采用YC、YCW或YHS。(b)一般电动机选G15。(c)对焊机械如对焊机的二次线采用YHS型长度不大于30m。5.3.3接地与接地装置设计电气设备设工作接地、保护接地、重复接地。接地体采用人工接地体和人工接地线。工作接地:Φ20圆钢焊接重复接地:Φ20圆钢,同工作接地,土壤电阻率为ρ=100Ω.m,接地电阻值为7.0Ω.人工接地线不小于塑套绝缘铜线,截面为10mm26.导线选择6.1总电缆导线截面选择:(1)按照允许电流大小选择导线界面:I=cos··3·UPK=0.6×244.61×1000/(√3×380×0.75)=297.33A施工临时用电方案7临时电总电缆选用210mm2BX型铜芯橡皮线,允许通过电流为300A。(2)查机械强度导线截面符合规定要求。6.2变、配电系统图006分配电箱016(L1.L2.L3.N.PE)FQ2012名称编号开关箱011017开关箱开关箱开关箱开关箱018001名称分配电箱编号分配电箱分配电箱开关箱003002009YY10KV0102(L1.L2.L3.N.PE)FQ10.4KV(L1.L2.L