丙洲岛综合整治二期工程(E标)I标段工程围堰工程专项专项技术方案编写:审核:批准:广东省航盛建设集团有限公司2011年12月目录一、工程概况...................................................................................................................1二、计划投入机械设备表...............................................................................................2三、人员配置...................................................................................................................2四、施工工期计划...........................................................................................................2五、工艺流程图...............................................................................................................2六、施工方法...................................................................................................................36.1施工总体安排.....................................................................................................36.2充填袋施工.........................................................................................................3七、材料检验...................................................................................................................6八、质量保证措施...........................................................................................................7九、安全保证措施...........................................................................................................99.1施工过程危险源识别........................................................................................99.2应急措施..........................................................................................................139.3安全保证措施..................................................................................................15十、环境保护措施.........................................................................................................1710.1重要环境因素识别评价.................................................................................1710.2针对重要环境因素制订的环境保护措施.....................................................18十一、文明施工措施.....................................................................................................1811.1管理规章制度.................................................................................................1811.2布置.................................................................................................................19十二、附图:施工平面布置图.....................................................................................201一、工程概况丙洲岛综合整治二期工程(E标)I标段位于丙洲岛中部,地块北侧为丙洲村,地块南段为同安大桥,地块西侧为丙洲渠,地块北边为东西溪。工程内容主要包括围堰、清淤疏浚、吹填造地、软基处理、地块场平及附属工程(施工阶段场地临时排水、施工便道、施工用电和储泥砂池等)。本标段围堰由外围围堰和分隔围堰组成,总长度3866.36m,土工布充填砂袋47.61万m³,外围围堰包括外围围堰1、外围围堰2、外围围堰3、外围围堰4、外围围堰5;分隔围堰包括分隔围堰1、分隔围堰2、分隔围堰3、分隔围堰4、分隔围堰5;围堰吹填的位置共分为2大块,及吹砂1区围堰和吹泥砂1区围堰。其中除外围围堰3利用护岸作为围堰外均为新建围堰。充填袋工程量如下表:围堰断面工程量(㎡)长度(m)方量(m³)预计沉降量(沉降计0.5m)(m³)施工流失量(按20%)(m³)施工工程量(m³)底宽(m)ABCD=B*0.5*底宽E=(C+D)*20%F=C+D+E外围1159.9752.4120308.82275.424516.8147101.028.46外围2111.7123.313772.61894.43133.418800.533.92外围4106.2462.0449068.61561.110126.060755.729.4外围5185.5208.6538704.62589.68258.849553.027.92分隔1262.882.3821649.55518.85433.732601.942分隔2262.8213.756160.45518.812335.874015.042分隔3-193.44140.7413150.71021.32834.417006.521.86分隔3-286.71385.3533413.7871.96857.141142.720.11分隔3-395.33191.3818244.31115.83872.023232.123.41分隔3-484.4173.3314629.1780.73082.018491.718.5分隔4-1123.03344.1742343.21728.68814.452886.228.1分隔4-293.51318.2729761.41305.46213.437280.227.92分隔4-393.5174.887002.01305.41661.59968.927.92分隔5-1109.32233.9725577.61967.85509.133054.436分隔5-2134.12132.7717807.12286.74018.824112.634.1合计640002.32二、计划投入机械设备表序号名称型号、性能单位数量备注1高压水泵75KW台11一台备用2ES-6E砂泵120KW台11一台备用3自卸汽车25方台204挖掘机PC820台25推土机D8K/410Kw台2本工程充填袋充填量约为64万m³,计划工期120天,每天需完成工程量=640000/(120天*0.8)=6667万m³。ES-6E砂泵每小时充填量约为100m³/h,每天工作8小时,11台(1台备用)砂泵每天可完成充填量8000m³,满足计划要求。三、人员配置劳动力配备及管理人员表管理人员人8操作工人人58司机人22合计人88四、施工工期计划工期计划120天,从2011年10月19日起至2012年2月16日。五、工艺流程图围堰软弱地基处理填筑土工布充填砂袋、理坡堤心填砂料(第一级)编织袋装砂理坡3尼龙砂袋护坡砂袋压脚第二级充填砂填土并分层碾压堤顶施工便道结构层施工围堰施工流程图六、施工方法6.1施工总体安排围堰分两级进行,第一级充填到+3.3m,第二级充填到顶标高。充填袋施工在开挖软弱地层到设计标高后进行,围堰充填顺序如下:外围围堰1外围围堰5分隔围堰5分隔围堰2外围围堰2分隔围堰1分隔围堰3分隔围堰4外围围堰4外围围堰3围堰工程充填砂由海上运砂船运到集泥砂池,再由绞吸船吹填到吹填区,利用汽车倒运到充填地点进行充填袋充填施工。围堰地基处理:将现有鱼虾池的水排干,对基底淤泥进行开挖,开挖至设计标高。围堰填筑:横断面上部及横断面下部两侧由土工布充填砂袋构筑,土工布充填砂袋采用机械直接充填,土工布充填砂袋每层厚500mm,分级填筑,其端头用砂袋压脚,横断面下部中间回填中粗砂。围堰外侧采用编织袋装砂理坡,300mm尼龙砂袋护坡。围堰堤顶:围堰堤顶筑挡泥堰袋装砂。6.2充填袋施工充填袋采用陆上高压水泵配合砂泵进行充填,利用高压水泵形成的高压水枪冲击泥砂形成砂浆,砂浆流入砂浆池后通过砂泵进行砂袋充填,砂浆池布置在现有虾池中。围堰按200m布置一个施工段,每个施工段分配2个砂泵,共分5个施工面同时进行充填。4砂泵布置按泵距控制在300m范围进行布设,充填袋施工平面布置示意图见附图。充填施工工艺流程图如下图:施工工艺流程图1、施工前准备:软土层开挖至设计标高后整平场地,清除表层可能有损坏土工织物的凹凸物、杂物,做好清基工作。2、测量及定位测量放样:首先是测放出第一层充填砂袋的底边线导标,每隔150~200m立一个标,以此作为铺设砂袋内、外边线。施工上层充填袋时,导标须根据已施工的砂袋标高结合围埝坡比经常调整位置。3、充填袋加工和定位(1)充填袋加工充填袋的制作材料根据设计要求应选用透水性和保土性较好聚丙烯编织土工布。充填袋制作成筒状,尺寸以棱体断面的不同高程的尺寸加上退档尺寸,高度按充填后厚度为0.5m设置,在围堰横断面方向须整块制作,纵向充填袋尺寸以利于制作和施工方便为宜,一般在20~30m,每个砂袋的袖口布置呈梅花型,袖口数量视充砂管袋的大小,土质等情况而定,一般每16~20m²设一只,充填袋由土工织物生产厂家加工制作。(2)充填袋定位1)、充填袋四周设计系缆环,便于系缆于钢管桩上以固定编织袋;2)、根据围堰轴线和充填袋尺寸,由全站仪指挥钢管桩定位;3)、人工打设钢管桩入土,钢管直径和入土深度应能保证砂袋充填过程中钢管桩不至于倾斜倒塌;4)、充填袋四个角绑好绳子与4根定位钢桩套结,使砂袋平整展开,然后将砂泵的排泥管与袋子的充填袖口连接绑扎固定。第二层的充填袋同样由与定位钢桩连接的绳子进行定位,直至达到设计断面位置,以上层数以此类推;5)、每层