滨江花园基坑降水施工方案编制人:审核人:审批人:编制单位:第二建筑工程公司编制日期:二OO六年六月二十八日目录1.工程概况······································································12.场地工程地质情况··························································12.1.地层结构及岩性特征················································12.2.场地水文及气象情况················································33.降水井设计与施工··························································43.1.降水设计·······························································43.2.基坑降水对周边环境影响及处理方案···························74.抽水监测与管理·····························································85.项目经理部主要人员组成·················································96.施工计划····································································106.1.进度计划·····························································106.2.保证工期措施·······················································107.安全文明施工措施·························································117.1.安全保证措施························································117.2.文明施工措施························································118.竣工验收····································································1311.工程概况本工程位于海口市二东路鸭尾溪出海口处。场地原地貌属海漫滩,现为菜地,地形平坦,周边尚无其它建筑物,基坑施工对环境的影响较小。本工程基坑采用放坡开挖,基坑大致呈长方形mm16.799.95,基坑面积约244.7591m,基坑采用放坡开挖,基坑开挖最深处约m15.3。根据勘察报告提供,降水范围内土层的综合渗透系数dmk/41.21,影响半径mR60.61。2.场地工程地质情况2.1.地层结构及岩性特征在本次勘察55.10m深度范围内,揭落地层有第四系全新统沉积土(Q4m),第四系下更新统沉积土(Q1m),和第三系上新统海口沉积土(N2m)。根据地层岩性特征和沉积新老关系从上而下划分为①、②③、④、⑤、⑥、⑦、⑧共8个工程地质层.现分述如下:2.1.1第①层粉质粘土(Q4m):分布全场地的地表,褐黄色,可塑状。成份以粉粒、粘粒为主,含中粒,细粒,局部砂粒含量较高,无摇震反应,切面稍光滑、韧性中等,干强度中等。层顶标高2.32~3.32m,平均值2.66m;层底埋深0.60~2.30m,平均值1.19m。2.1.2第②层中砂(Q4m)分布于整个场地,浅黄色,饱和,松散状。成分以中粒,细粒为主,粗粒、粉粒次之,局都粉、细粒含量2较高,粘性含量<3%,分选性差,次棱角~次圆状。层顶标高0.04~2.28m,平均值1.47m;层底埋深4.40~6.60m,平均5.51m;层厚3.30m,平均值4.31m。2.1.3第③层淤泥质粉质枯土(Q4m):分布于整个场地,深灰~灰黑色,流塑~软塑状。成分以粉粒、粘粗为主,含细粒及少量贝壳碎屑,局部粉、细砂含量较高,含腐植质,具腐臭味。层顶标高-4.15~-1.62m,平均值-2.84m;层底埋深7.30~8.90m,平均值7.79m;层厚0.90~3.60m,平均值2.29m。2.1.4第④层粘土(Q1m):分布于整个场地,枯红、浅黄、浅灰色,夹薄层状粉砂,局部粉砂含量较高,可塑状,无摇震反应,切面光滑,干强度高,韧性高。层顶标高-6.07~4.52m,平均值-5.13m;层底埋深10.10~12.4m,平均值11.11m;层厚2.20~4.20m平均值3.32m。2.1.5第⑤层粉砂(N2m):分布于全场地,青灰、浅灰色。成分以石英质粉粒、细粒为主,含中粒,局部中粒、粗粒含量较高,粘粒含量3~6%,饱和,松傲~稍密状,磨圆度为次圆状。层顶标高-14.10~9.78m平均值-11.84m;层底埋深12.30~16.40。平均值14.53m;层高1.30~4.70m,平均值3.25m。2.1.6第⑥层粉质粒土(N2m):分布于整个场地。成分以粉粒、粘粒为主,具水平页理,夹薄层状或团状粉砂,局部粉砂含量校高。无摇震反应,切面稍有光滑~光滑,韧性中等,干强度高,可塑~硬塑状。层顶标高-14.04~-9.85m,平均值-12.00m;层底埋深15.20~320.20m平均值16.79m;层厚1.00~4.60m。,平均2.14m。2.1.7第⑦层粉砂(N2m):分布于全场地,青灰色,成分以石英粉、细粒为主,局部含中粒,粘粒含量3~6%,饱和,密实状为主,局部中密状,磨圆度为次圈状。层顶标高-17.71~11.92m,平均值-14.25m;层底埋深21.20~25.60m,平均值23.26m;层厚2.40~9.70m,平均值6.40m。2.1.8第⑧层粉质粘土(N2m):分布于整个场地,厚度大,本次勘察未揭穿。成分以粉粒、粘粒为主,具水平页理,夹薄层状或团状粉砂,部粉砂含量较高。无摇震反应,切面稍有光滑,韧性中等~高,干强度高,可塑~硬塑状,局部钙质胶给呈坚硬状。层顶标高-22.75~18.60m,平均值-21.52m;最大揭落厚度30.70m。2.2.场地水文及气象情况海口市位于海南岛北部,在中国建筑气候中属ⅣA区,为热带海洋性气候,年平均气温为22.4~25.5℃,气候炎热,雨量充沛,雨水主要是季风雨和台风雨。每年5~6月份为季风雨降雨高峰期,8~10月份为台风雨,11月份至次年月4月份为枯水期。枯水期雨量少、干旱、气候温和,是施工的黄金季节。场地地下水埋藏浅,旱季实测稳定水位埋深1.08~1.28m,地下水位年变幅约1.00m,最高水位基本与现地面持平。在基坑开挖深度内地下水主要赋存在第②层中砂,为松散岩类孔隙隙潜水,富水性和透水性好,属富水含水层。地下水与地表水(鸭尾溪)关系密切,第②层中砂在水头压力的作用下易产生涌水涌砂现象。43.降水井设计与施工3.1.降水设计3.1.1方案选择由于地下水与地表水(鸭尾溪)关系密切,第②层中砂在水头压力的作用下易产生涌水涌砂现象。必须保证降水效果的可靠性,防止涌水、涌砂等现象的发生。决定沿基坑上口周边设计管井,形成坑外管井降水,坑内明沟排水的方法进行降水,保证降水的可靠性和安全性。3.1.2基本参数根据勘察报告提供,降水深度范围内土层综合渗透系数smdmk/000248.0/41.21。基坑设计水位降深mS65.3(即地下水降至基坑底以下0.50m),含水层厚度mH0.8,影响半径mkHSR54.952。降水井半径据地区经验取mrw3.0。3.1.2基坑涌水量(Q)估算根据等代大井法估算了该基坑的涌水量,估算时采用下式:)1lg()2(366.10rRSSHkQ式中0r——基坑口等效半径,mAr17.4914.3/0。计算结果:49.2811Q(dm/3)3.1.3单井出水量(q)及降水井个数(n)152klrqw5式中q——管井单井出水量(dm/3)l——管井进水部分长度,取2.0(m)wr——管井半径,取300mmk——含水层渗透系数,dmk/000248.0计算结果:dmq/79.3413。降水井个数:0.91.1qQn(口),考虑管井间距及群井干扰,取14口。3.1.4井点间距及降水井布置在基坑周边共布设降水井14口,井点间距24~26m。降水井的凿井深度为8.0m;井径为600mm;钢筋笼直径为400mm,钢筋笼外裹包2层层过滤尼龙网、2层铁丝网、1层竹片,钢筋笼周边填充100mm厚粒径2cm碎石过滤层。另外在基坑中心设一观测井,观测井做法同降水井。降水井的平面位置详见图。3.1.5水位降低检验本次采用基坑中部设置降水井法进行降水,水位降低检验的重点是基坑中心点的水位降低情况。用等代井法进行计算,等代大井面积244.7591mA,等代井的半径mr17.490,基坑中部水位降深mS15.3,群井抽水时,单井井管进水长度0y计算。)]lg(1)[lg(732.010020wnrnrnRrkQHy)]3.017.4914lg(141)54.9517.49lg[(41.2149.2811732.00.81320y6mlm0.24.3满足要求。基坑中心点水位降低检验基坑中心点采用下式进行验算:)]lg(1)[lg(366.121020nrrrnRrkQHHS14个管井井点距基坑中心的距离如下:mrrrr18.6212851mrrrr28.4611942mrr58.39103mrrrr74.49141376计算结果为:mSmS65.36.30可以满足降水要求。群井总涌水量验算:)lg(1)lg()2(366.12100nrrrnrRSSHkQ计算结果为;dmQdmQ/49.2811/5.28663303.1.6降水设备抽水设备可采用深井潜水泵,每一口管井内设一台潜水泵,设计总出水量≥600dm/3。降水井采用旋转钻机成孔,降水由专人负责,配专职抽水工及电工各1名,24小时值班。7在实施基坑开挖前五天开始降水,观测井水位降至下一次开挖基底下0.5m时,进行下一次开挖。3.2.基坑降水对周边环境影响及处理方案基坑降水对环境的影响主要表现为降水引起的地面沉降问题。由于本工程场地目前为一菜地,周边尚无其它建筑物,基坑降水对环境的影响很小。降水井平面布置图8管井结构图4.抽水监测与管理(1)降排水之前观测一次自然水位,在抽水开始的5~l0天内,要求每早晚各观测一次水位、流量;以后改为每天观测一次,并作好记录。进入雨季或出现新的补给源时,应增加观测次数。(2)对观测记录应及时整理,绘制Q~t(抽水量与时间)与S~t(水位下降值与时间)关系曲线图,分析水位下降的趋势与流量变化,预测水位下降达到设计要求的时间;根据实际抽水情况,研究降9水设计的可靠程度或提出调整措施:查明抽水过程中的不正常状况及其产生的原因,及时组织排除。(3)对抽水设备应建立定期检修保养制度,保持设备的正常运行。降水期间不得停泵。(4)抽出的水应排至降水区以外,不应产生回渗。遇有大雨或暴雨,应及时排除地面和基坑积水,以减少下渗,保证降水。5.项目经理部主要人员组成项目经理:技术负责:测量:施工员:各个岗位均选派我公司责任心强、技术水平高、有工作经验的,近年来有突出业绩的管理和技术人员上岗。现场主要工序负责人及劳动力安排。主要工序负责人及劳动力安排计划表表10序号岗位负责人人员数量(人)备注1技术组22质检组23钻孔组104钢筋班35降水井施工106降水施工47安全员1106.施工计划