邵阳兴昂国际城基础工程土方开挖施工方案编制人:审核人:审批人:湖南家和建设有限责任公司邵阳兴昂国际城项目部2012年12月6日1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司1目录目录···························································································1编制说明一、工程概况··················································································3二、地质情况现场情况三、组织机构··················································································4四、土方开挖施工准备······································································4(一)、测量放线及测量控制点的保护·················································5(二)、土方开挖前期准备································································5(三)、土方开挖技术、安全准备·······················································6五、土方开挖施工············································································7(一)、工期··················································································7(二)、施工工艺············································································7(三)、土方开挖允许偏差································································9(四)、基坑开挖注意事项······························································10六、土方回填施工方案七、施工监测及应急措施·································································13八、基坑土方开挖质量保证措施························································13九、基坑土方开挖安全措施······························································14十、基坑土方开挖文明施工注意事项··················································15十一、基坑土方开挖进度横道图························································161-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司2附录1:·······················································································17基坑土方开挖施工方案编制说明邵阳兴昂国际城位于邵阳市双清区市兴业路东侧,拟建道路集仙路南侧,拟建财桥路西侧,由湖南省第四工程有限公司设计院设计,全部土建、安装工程由我公司兴建。应建设单位要求,我公司于2012年11月16日进场进行施工准备和施工临时设施的建设工作,包括对现场道路、水文、地质、周围环境进行调查了解。因设计图纸交付缓慢,我公司一直缺乏对工程整体的全面了解和认识,在前期工作中未编制周全的施工组织设计,在施工程序的安排上随图纸进度随时进行调整和部署,对具体施工方案和具体施工方法,我公司只有分别编制阶段性施工方案,用以指导施工。设计图纸全部到齐后,我公司即着手进行全面的施工组织设计,根据我公司对设计图纸的初步理会,对工程量的初步估算,结合现场施工条件及我司施工力量,力求对施工中人力、物力和方法,时间和空间,需求与可能,局部与整体,阶段与过程,前方与后方等给予周密的安排和布置。在进度安排上,已完成的工作按实计入,在施工方案和方法上,已完成部分按阶段性施工方案和实际施工情况实录。由于编者水平所限加上时间仓促,缺乏对设计意图周全而深入的了解,因而不足之处在所难免,敬请有关领导及专家提出宝贵意见,具体施工中,我公司将据领导及专家意见随时改进。1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司3一、工程概况建设单位(即业主单位):邵阳兴昂银信置业有限公司设计单位:湖南省第四工程有限公司监理单位:湖南金阳监理施工单位:湖南家和建设有限责任公司本工程为邵阳兴昂国际城一期工程地下室和12栋单体楼基础土石方方工程地下室基础面积约为28000m2,共有土方约80000m3。甲方已在原始地貌上初步进行了场地平整给出了自然地面,其现状是大体分为三块:自然地面标高在黄海高程241米~242米之间为一块;自然地面标高在黄海高程243米~24米4之间为一块;自然地面低于黄海高程244高低不平的为一块。地下室底标高在黄海高程239米~243米之间,因地下室底板带有3%的坡度,所以导致每栋主楼的基底标高都不一致,从自然地面以下基坑最深的约8米,最浅的约2.6米,高程控制数据多而杂,由此造成施工难度大。二、地质情况、现场情况(一)、地质情况拟建兴昂国际城项目位于邵阳市双清区,兴业路东侧集仙路南侧,财桥路西侧,地理位置优越,属低山丘陵地貌,甲方挖填土方平整基本完成,根据中国有色金属长沙勘察设计研究院有限公司出具的《兴昂国际城岩土工程详细勘察报告书》,该土方开挖工程场地内地层主要有人工填土层、第四系湖积层、冲积层、坡积层及残积层、下伏基岩为三叠系大冶组炭质页岩及砂岩。炭质页岩及砂岩按其风化程度不同分为强风化、中风化两带,据勘察报告书反映基本取炭质页岩及砂岩层做为持力层。1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司4(二)、现场情况1、本土方工程是该工程施工工期控制的关键,必须优化施工工序,合理安排施工顺序,尽量缩短施工工期,。2、本工程土方开挖量大、混凝土浇筑量大,而施工道路尚未硬化且不畅通,大型车辆出入不便,必须加强车辆调度和疏导,避免在土方开挖和混凝土浇筑时引起交通堵塞。4、本工程南侧及北侧均有居民居住,在施工中必须采取切实措施,特别是爆破作业,尽力降低施工噪音,并做好协调工作,尽最大努力减少扰民,确保文明施工。5、本工程土方开挖深度较大,必须做好边坡支护及临边防护工作,采取有效措施保证边坡稳定。三、组织机构为确保土方开挖、回填过程顺利进行,我项目部配备下列管理人员负责现场组织管理:四、土方开挖施工准备总指挥生产负责人编制说明邵阳兴昂国际城位于邵阳市双清区市兴业路东侧,拟建测量员电工安全负责人安全员技术负责人技术员质量员1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司5(一)、测量放线及测量控制点的保护1、在基坑开挖之前核准红线桩和建筑物定位桩。场内所有红线桩及建筑物的定位桩全部经市规划部门测量核准,查清红线桩及定位桩是否产生移位,若有移位应会合规划部门、设计单位、建设单位重新定位。2、对场边道路及场地的临边设施做好定位标记,用作施工阶段定位的相对参照物标记。3、在基坑开挖前,根据施工图纸,建筑轴线位置结合基坑围护平面布置图放出土方开挖基线。4、土方的机械施工容易碰压测量桩。因此,在基坑开挖前,基坑开挖范围内的所有轴线桩和水准点都要引出施工活动区域以外并设置深红白漆的钢筋支架予以保护。5、所有的测量桩、红线定位标记一经核实后,项目部就落实专业人员对其进行定期检查复核,以确保红定位标记的准确性。(二)、土方开挖前期准备1、土方开挖所需设备机械应准备就绪。2、土方外运的运输道路、运输路线及弃土的位置已经落实并准备就序。3、办理渣土外运方面的有关手续,并做好与交通、市容等有关部的协调。4、由于土方开挖时间长且24小时连续施工有关夜间施工的手续及周围居民的协调工作应准备就绪。5、现场临时道路及排水沟已准备完毕。6、土方施工机械、机具应做好施工前的保养、维护。7、土方开挖作业系统内的夜间照明,基坑采用固定的木架子架高安置1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司6的2只3.5kw太阳灯照明。8、劳动力组织到位,主要劳动力的定员及配备见下表:(按允许夜间施工考虑)工种、设备机械台数定员人数班制配备人数备注1.2m3反铲挖土机5台10人1班10人必要时两班破碎机1台2人1班2人必要时两班装载机ZL-50型1台2人1班2人必要时两班15t自卸汽车25辆25人1班25人必要时两班机修车司机及机修人员2人1班2人必要时两班电工2人1班2人必要时两班修土配合人员30人1班30必要时两班场地清理人员3人1班3必要时两班管理指挥人员3人1班3必要时两班(三)、土方开挖技术、安全准备1、开工前要向土方施工人员进行书面交底,熟悉图纸,掌握现场测量桩及水准点的位置尺寸,熟悉基坑施工范围内土质及周边情况、施工方向、施工范围的支撑布置情况,桩位情况。并同专业监理工程师办理验桩、验线手续。2、确定周边环境及围护结构的检测及应急方案,围护结构突发的变形、1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司7滑移等应急措施及必备的机械设备、劳动力等准备就绪。3、配备专职测量人员进行标高控制。土方开挖中及时控制标高,做到5m扇形挖土工作面内,标高白灰点不少于2个。4、检查施工机械、机具是否做好施工前的保养、维护。5、对土方夜间施工的照明设备及架设情况并做好检查及验收,按要求配备随班电工及其他辅助劳动力。6、对进场施工人员三级安全教育,并将三级安全教育结果汇总并存档保存。7、成立以项目经理为组长的安全及应急领导小组。8、向监理(业主)申请开挖令。9、在正式开挖前应做1-2天的试开挖,在试挖顺利后根据甲方(监理)的开挖令正式开始基坑挖方施工。五、土方开挖施工(一)、工期由于本工程工期紧,土方施工直接影响工程的进度,确定本工程的土方开挖的施工工期为45天,见施工进度横道图。(二)、施工工艺1、土方开挖的方法土方开挖以人工配合2台PZ200型挖土机进行,土方运输采用15辆15T自卸土方车。现场配备一台ZL—30型装载机,根据现场条件本工程开挖出来的土方,一部分(约10000m3)堆放在现场东面的土方临时堆放场,多余部分外运至甲方认可的弃土场。具体施工方法:1-5#、12#、13#、14#、15#、16#、18#-20#、25#楼基础土方开挖施工方案湖南家和建设有限责任公司8在机械开挖准备工作及安全措施全部做到位后,开始基坑土方大开挖,计划30天左右完成基坑内土方大面积挖土。机械开挖;控制基底土层保持平整,及时引测基底标高,挖土过程随时进行标高测量,防止因超挖扰动降低地基承载力。挖机挖土时,必须可靠控制,挖土时,