1福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计弋阳县华晨国际钻孔灌注桩工程施工组织设计福建新华夏建工有限公司二0一二年六月十日2福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计目录第一部分:编制说明·······································································1一、编制原则·······································································1二、编制依据·······································································1第二部分:工程概况·········································································2一、概述···············································································2二、设计要求·······································································4第三部分:施工准备·········································································4一、施工现场条件准备·························································4二、施工技术准备·······························································43三、施工机械及工具配备···················································5四、劳动力安排计划···························································5五、施工现场管理体系网络图··········································6第四部分:施工工艺和施工方法····················································7一、施工工艺和施工方法··················································7二、施工工艺流程图··························································8第五部分:施工技术质量保证措施················································9一、护筒埋设······································································9二、成孔施工······································································9三、钢筋笼制作····································································10福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计四、砼质量控制··································································114五、二次清孔与砼灌注··························································11第六部分:安全生产及文明施工保证措施···································12一、安全生产·····································································12二、文明施工措施······························································13三、环境保护措施······························································13第七部分:施工现场管理网络图··················································145福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计第一部分:编制说明一、编制原则1、安全第一的原则施工组织设计的编制,按照技术可靠、措施得力、确保安全的原则确定施工方案。2、优质高效的原则加强领导,加强管理。根据我们在施工组织设计中明确的质量目标,贯彻执行ISO9001质量体系标准。3、确保工期的原则搞好工序衔接,实施进度监控,确保实现工期目标,满足业主要求。4、合理布局、科学配置的原则根据工程量、各项管理目标、以及地形地貌的特征,在临时施工准备上,特别是对水、电、道路安排利用,进场材料的存放,生活设施布置。本着安全、文明、方便、高效的原则,优化配置、合理布局,6满足施工需要。二、编制依据本施工组织设计严格按照施工组织设计编制原则,并以以下文件为编制依据:1、施工合同的要求。福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计2、工程相应图纸及设计变更。3、《工程测量规范》4、《建筑地基基础设计规范》5、《建筑桩基技术规范》6、《工业与民用建筑灌注桩基础设计与施工规程》7、《钢筋焊接及验收规程》8、《施工现场临时用电安全技术规范》9、《建筑工程质量检验评定标准》10、《建筑施工安全检查标准》11、《建筑地基基础工程施工质量验收规范》12、《建筑工程施工质量验收统一标准》13、《桩基工程手册》14、《混凝土结构工程施工质量验收规范》15、《建筑机械使用安全技术规程》7福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计第二部分:工程概况一、概述弋阳县华晨国际位于上饶市弋阳县圭峰大道南侧,拟建2幢11层连体小高层,占地面积约3084M2,施工场地平坦,周围交通方便,现场“三通一平”工作已结束且已基本开挖至地下室标高。根据中材上饶地质工程勘察院提供的勘察报告,地基岩土主要可以划分为以下7个工程地层图:○1层素填土,深灰色,中密,稍湿。透水性较强。由近年来平整场地而人工杂乱填筑并经碾压的泥质土、砂、砾石和细砂岩岩石细碎块组成,具高压缩性,均匀性极差。层厚1.00~1.30M,平均厚度1.11M。○2层耕填土,深灰、黑色,松散,稍湿。透水性较强。由泥质土、砂、砾石和细砂岩岩石细碎块组成,具高压缩性,均匀性极差。层厚0.30~0.70M,平均厚度0.34M。8○3层粉质粘土,棕黄色、可塑,稍湿。透水性弱。压缩性中等。湿土刀切断面规则、有光泽,内无包含物,可搓成径为0.5~2mm的土条,摇震无反应,干强度高,高韧性,具强粘滞性。由粘土矿物组成。层厚1.10~1.90M,平均厚度1.47M。○4层中砂,棕黄色、松散,饱和,局部地段稍湿。分选性良好,级配差,质纯。透水性中等。由中粒长石、石英砂和云母碎片组成。福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计据室内土工试验资料,粒径大于0.5~1mm的颗粒质量占总质量的25.0%,粒径大于0.25~0.5mm的颗粒质量占总质量的52.5%,粒径大于0.075~0.25mm的颗粒质量占总质量的19.4%,粒径小于0.075mm的颗粒质量占总质量的3.4%。层厚3.00~4.20M,平均厚度3.43M。○5层卵石,灰白色,密实,饱和。由卵、砾石和中、粗粒硅质、石英砂组成。透水性强。卵、砾石成分为花岗岩、硅质岩和石英岩,卵、砾石粒径一般为2~60mm,大者达120mm,磨圆度良好,呈亚圆~圆状。分选性差,级配良好,据室内土工试验资料,粒径大于20mm的颗粒质量占总质量81.0~82.3%、平均81.7%,粒径大于2~20mm的颗粒质量占总质量4.4~8.3%、平均6.4%和粒径大于0.25~2mm的颗粒质量占总质量7.1~9.1%、平均8.1%。层厚3.20~4.80m,平均厚度4.23M。○6层强风化细砂岩,浅红、棕红色,组织结构已大部分破坏,残留原岩结构痕迹,偶见层理。上部呈砂土状,中、下部渐呈薄饼、碎块状,岩芯较完整,用手易捻成粉末,岩体基本质量等级BQ为V级。层厚0.90~1.20M,平均厚度1.07M。9○7层中风化细砂岩,棕红、紫红色。细粒结构,钙、铁质胶结,厚层状构造,层理清晰。由细粒长石、石英砂和钙、铁质组成。裂隙不发育,岩芯较完整,以长柱状为主,少数短柱状,局部碎块状,锤击声稍哑、轻易击碎,岩石质量指标RQD=86~88%,岩石坚硬程度属软岩,岩体基本质量等级BQ为IV级。勘察揭示层厚7.90~9.50M,最大揭示厚度9.50M。福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计二、设计要求本工程设计单位为江西省现代建筑设计研究院,主要建筑物基础采用钻孔灌注桩,设计桩直径为Φ900Φ1000Φ1100Φ1200Φ1300Φ1400Φ1500,部分桩为抗拔设计,桩底均采用扩大头设计,桩身砼强度等级为C25,设计桩尖持力层为○7层中风化细砂岩,设计桩长6M。其它有关技术要求将在正式施工图中详细明确。第三部分:施工准备一、施工现场条件准备1、现场“三通一平”工作完成后,按本施工组织设计要求有计划地组织人员、机械、材料等有序地进场。2、按平面规划图科学合理地布置生活区和施工区,确定施工顺序及泥浆沟、槽、池的合理布置。3、施工用电方案3.1.桩基施工期间用电量为100KW。103.2.施工用电与生活用电分开。根据施工现场用电设备布置情况,施工用电由现场配电房引至配电箱,再由分配电箱引至各用电设备的开关箱。4.施工用水方案4.1.由业主提供水源,3寸水管进场。4.2.水管沿场地周围环绕布置,每隔20米左右设一水龙头。福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计5、厕所卫生设施在场地外面宿舍区内由总包单位提供临时厕所,厕所专设上下水道,以便于冲洗。二、施工技术准备1、项目经理组织项目部各级施工人员进行学习施工规范和施工方法等技术性文件。2、技术负责人组织学习施工图纸,熟悉图纸上的设计要求,做好图纸会审,设计交底工作。3、根据业主或有关部门提供的书面控制点,认真测量基准点和标高,实施定位放线,保护好控制点,有待核查。4、做好材料的进场验收工作,并按要求进行复验,合格后方可投入使用。4.1、材料的进场:a.所有使用的物料,应符合设计及有关规范规定;b.钢筋的级别、直径应符合设计及有关规范规定,合格后才能使用。11c.认真选择好商品砼的供应单位;本次商品砼的供应单位为弋阳县步鑫混凝土有限公司。d.按规定做好各有关原材料的采样和复试工作,确保原材料的质量。三、施工机械及工具配备根据本工程工作量及工期需要,结合我公司施工经验,我公司配福建新华夏建工有限公司弋阳县华晨国际桩基工程施工组织设计备的机械设备、工具如下表:序号机械名称及型号单位数量备注一GPS-15型钻机台2二3PNL泥浆泵台2三泥浆车辆1四100NL排污泵台2五电焊机台2六水泵台2—4七水准仪台1八经纬仪台1四、劳动力安排计划1、劳动组织工地设项目经理1名;项目副经理1名,项目工程师(技术负责人)1名;质检员1名,施工员1名,材料员1名,安全员1名,测量员1名,资料员1名;合计9人。122、劳动力计划机械操作工12人;场地工3人,排浆工2人,电焊工3人,电工1人,后勤人员3人,机械维修2人,合计26人。五、施工现场管理体系网络图福建新华夏建工有限公司弋阳县华晨国际