目录1.工程概况··············································································12.编制依据··············································································13.管道材料··············································································14.管沟开挖··············································································15.防腐施工··············································································26.碳钢管道安装工程··································································27.钢骨架PE管安装工程·····························································48.埋地双壁波纹管安装工程·························································59.管道水压试验········································································610.管沟回填············································································711.质量保证措施······································································812.安全保证措施及文明施工·······················································813.环境保护措施······································································914.劳动力组织·········································································915.主要施工机具····································································1016.施工网络计划····································································11附:全厂管沟布置及编号图内蒙古远兴江山10万吨/年DMF项目地下管网工程施工方案11.工程概况2.1工程名称:内蒙古远兴江山10万吨/年DMF项目地下管网土建、安装工程。2.2建设地点:内蒙古鄂尔多斯乌审旗乌审召镇生态工业园区。2.3工程内容:地下循环给、回水钢管(约1114m),生活给水、生产给水、消防给水、泡沫消防水钢骨架PE管(约5429m),生活污水排水、雨水污水排水埋地双壁波纹管安装(约4697m),地下管网合计11240m,其中PE管、埋地双壁波纹管的焊接由业主另行招标确定的供应厂家来完成。2.编制依据2.1内蒙古远兴江山化工股份公司DMF建设工程项目招标文件;2.2内蒙古远兴江山化工股份公司与中化二建集团有限公司签订的10万吨/年DMF建设工程办公楼、部分大型设备基础、地下管网土建、安装项目的工程承包合同;2.3华陆工程科技有限责任公司提供的厂区给排水管网图纸和选用的国家标准图;2.4《给排水管道工程施工验收规范》GB50268-97;2.5《工业金属管道工程施工及验收规范》GB50235-97;2.6《现场设备、工艺管道焊接工程施工及验收规范》GB50236-98;2.7《石油化工设备和管道涂料防腐蚀技术规范》SHJ3022-99;2.8《工业设备及管道防腐蚀工程施工及验收规范》HGJ229-91;3.管道材料3.1管道组成件及管道支承件必须具有制造厂的质量证明书,并符合国家标准的规定。3.2碳钢管材、管件均应有出厂合格证,出库到现场使用前应按设计要求核对其规格、材质,并应进行外观检查,其外观符合下列条款要求。3.2.1无裂纹、缩孔、夹渣、重皮等缺陷。3.2.2不得有超过壁厚偏差的锈蚀和凹陷。3.3管道在运输过程中要小心谨慎,采取措施保证管道不致受损。3.4阀门必须有合格证,安装前应检查填料,其压盖螺栓要有足够的调节余量。4.管沟开挖4.1管沟开挖前,应预先了解地下障碍物(如桩基、设备基础等)的分布情况,以免施工时遭到破坏。4.2管沟开挖前测量放线,测量人员根据甲方提供的现场标准水准点和轴线控制点、图纸坐标点,根据进度计划的安排和实际施工需要进行测量放线。4.3管沟开挖采用反铲挖掘机施工,多条相近平行管道可开挖一条宽沟,并根据管道不同的标高进行分层人工开挖,修整及清理部分采用人工挖土。4.4机械挖土时,沟底应留出200mm-300mm的土层作为清沟余量,铺管前必须用人工清理至设计标高,以防止超挖和槽底基础挠动。内蒙古远兴江山10万吨/年DMF项目地下管网工程施工方案24.5沟槽底部开挖宽度,根据挖掘机的机械切削尺寸及相关规定,确定沟底宽度如下表:单位:mm规格名称管径≤300400500600800900120016001800钢管130014001500180020002100280026002800非金属管道150016001700200022004.6沟槽开挖放坡系数如下表土壤类别人工挖土机械挖土放坡起点Ⅰ~Ⅱ1:0.51:11.2m4.7沟槽开挖过程中,应经常检察沟壁的土壤情况,如发现有裂缝和滑坡迹象时,应及时作应急处理。4.8沟槽开挖时,若出现超挖现象,应用相同土壤填补,并分层夯实。4.9沟槽开挖时,一般采用单边堆土,具体位置根据现场情况确定。如土方量较大影响管道施工时,可暂时将部分土方外运到指定地点。回填时按需运回。4.10沟槽的开挖质量应符合下列规定:4.10.1不扰动天然地基或地基处理符合设计要求。4.10.2槽壁平整,边坡坡度应符合设计施工的规定。4.10.3沟槽中心线每侧的净宽度不应小于管道沟槽底部开挖宽度的一半。4.10.4槽底高程的允许偏差:开挖土方应为±20mm,并在下管前进行沟深标高测量,测量结果应符合要求。5.防腐施工5.1碳钢管道采用集中防腐,由于设计资料不全,待设计文件明确后采购防腐材料并按照设计文件和相应规范的规定进行施工。5.2材料使用前应进行检验与验收,涂料应有制造厂的质量证明书。5.3管道防腐施工应按照设计规定和有关规范的要求进行。5.4不得在雾、雪、湿度大于85%或5级以上大风中露天施工。6.碳钢管道安装工程6.1管道安装程序:采取分段开挖分段安装回填的顺序进行,根据实际情况进行合理安排。内蒙古远兴江山10万吨/年DMF项目地下管网工程施工方案36.2管道的预制安装与铺设6.2.1钢管及管件采用钢丝绳吊装时应加衬草袋或胶板保护管道表面,装卸时应轻装、轻放,运输时应垫稳、绑牢、不得相互撞击;接口及钢管的内外防腐层应采取保护措施。6.2.2管道及管件堆放宜选择使用方便、平整、坚实的场地;按照安装使用顺序堆放,堆放时必须垫稳,堆放层高应符合规范要求。6.2.3起重机下管时,起重机架设的位置不得影响沟槽边坡的稳定,应留一定距离,保证作业安全。6.2.4管道应在沟槽质量检验合格后安装,管道安装应注意各个管道之间的距离和坡度应符合设计文件和规范的规定。6.2.5管件下入沟槽时应尽量避免与槽壁支撑物和槽下的管道相互碰撞。6.2.6管道安装时应随时清扫管道中的杂物,给水管道暂停安装时,两端应做临时封堵。6.2.7钢管安装允许偏差(mm)项目允许偏差轴线位置30高程±206.3焊接6.3.1参加管道焊接的人员应持有经技术监督局颁发的相应项目的焊工合格证。6.3.2管径大于800mm钢管时,应采用单面坡口双面成型施焊。6.3.3管口对接错边要求:(1)壁厚相同的管子、管件组对时,其内壁应做到平齐,内壁错边量不宜超过壁厚的10%,且不大于2mm。(2)不同壁厚的管子、管件组对时,当内壁错边量超过上述规定时留下空隙加固100mm,宽或错边量大于3mm时,应按规定形式进行加工。6.3.4坡口表面及其内外侧不小于10mm范围内应无油、无漆、无尘、无锈,不得有裂纹、夹层等缺陷。6.3.5施焊技术要求:(1)施焊时应按焊接工艺评定的工艺要求进行。(2)使用焊条时,应保持在保温筒内随用随取,每次取用量不超过4小时需用量。(3)露天作业,如遇到下雪、刮风等恶劣天气时应停止施焊。但若有适当的防护措施,在不影响质量的情况下,仍可进行焊接。(4)点焊式定位焊所用焊条和工艺条件应同于正式施焊。点焊焊肉不宜过厚,弧坑应填满,焊肉应均匀,防止产生裂纹,若发现裂纹应查明原因后铲除重焊,严禁在内蒙古远兴江山10万吨/年DMF项目地下管网工程施工方案4焊件表面引弧和试验电流。6.3.6焊口的坡口形式和尺寸本工程中螺旋焊接钢管的壁厚为6㎜~10㎜,施工中坡口形式采用V型坡口,DN800及以上管道的焊口内壁进行封底焊,坡口形式图及尺寸如下:序号管道壁厚T(㎜)坡口名称坡口形式坡口尺寸备注间隙C(㎜)钝边P(㎜)坡口角度α(°)13~9V型坡口0~20~265~7529~260~30~355~656.3.7焊缝的质量要求与检验外观检查:a、表面不允许有裂纹、气孔、夹渣、熔合性飞溅。b、咬肉≤0.5mm。c、咬边:深度<0.5m。长度小于等于焊缝全长的10%0,且小于100mm。d、表面加强高:焊缝为≤1+0.2b,且不大于5mm,其中b为焊缝宽度。e、表面凹陷:焊缝深度≤0.5mm,长度小于或等于焊缝全长的10%。f、接头坡口错位:焊缝小于0.25倍壁厚,最大为5mm。g、焊缝宽度:超过坡口边缘2mm为宜。5.3.8管道对接时,环向焊缝的检验及质量应符合下列规定:(1)检查前应清除焊缝的渣皮、飞溅物;(2)应在煤油渗透、水压试验前进行外观检查;(3)管径大于等于800mm时,焊口应进行煤油渗透检验,不合格的焊缝应铲除重焊。7.钢骨架PE管安装工程7.1施工流程管材、管件现场检查→管沟放线开挖→管材、管件搬运及安装就位→管口位置调整→电熔焊接→冷却→分层回填夯实至地坪标高→管道整体强度、严密性压力试验→与系统管网连接→工程验收7.2材料检验施工前应对管材、管件进行检验,是否符合标准要求,如外观、尺寸及其他要求,不符合要求的一律不许使用。内蒙古远兴江山10万吨/年DMF项目地下管网工程施工方案57.3管道系统预制安装及质量检验钢骨架PE管的预制安装流程、方法及质量检验标准严格按照管道厂家提供的安装指导书的要求执行,同时施工单位、监理单位和建设单位的相关人员应全程进行质量、进度监督,确保管道安装的质量和工程进度都达到工程的要求。8.埋地双壁波纹管安装工程8.1待用的管材应按产品标准逐支进行质量检验,不符合标准者不得使用,并应做好记号,另行处理。8.2管材现场应由人工搬运,搬运时应轻抬轻放。8.3下管前,凡规定须进行管道变形检测的断面的管材,应预先量出该断面管道的实际直径,并做出记号。8.4下管可用人工或起重机吊装进行。人工下管时,由地面人员将管材传递给沟槽内施工人员;对放坡开挖的沟槽也可用非金属绳索系住管身两端,保持管身平衡均匀溜放至沟槽内,严禁将管材由槽顶边滚入槽内;起重机下管吊装时,应用非金属绳索扣系住,不得串心吊装。8.5管道及管件的连接方法按照材料供应厂家的要求进行,施工单位做好下料和组对