全国建筑安装工程统一劳动定额

整理文档很辛苦,赏杯茶钱您下走!

免费阅读已结束,点击下载阅读编辑剩下 ...

阅读已结束,您可以下载文档离线阅读编辑

资源描述

《全国建筑安装工程统一劳动定额》砖墙工作内容:包括砌墙面艺术形式、墙垛、平碹及安装平碹模板,梁板头砌砖,梁板下塞砖,楼梯间砌砖,留楼梯踏步斜槽,留孔洞,砌各种凹进水、山墙泛水槽,安放木砖、铁件,安装60kg以内的预制混凝土门窗过梁、隔板、垫块以及调整立好后的门窗框等。表2—1单位:工日/m³项目双面清水单面清水序号1砖1.5砖2砖及2砖以外0.5砖0.75砖1砖1.5砖2砖及2砖以外综合塔吊1.271.21.121.521.481.231.141.07一机吊1.481.411.331.731.691.441.351.28二砌砖0.7260.6530.5681.000.9560.6840.5930.52三运输塔吊0.440.440.440.4340.4370.440.440.44四机吊0.6520.6520.6520.6420.6450.6520.6520.652五调制砂浆0.1010.1060.1070.0850.0890.1010.1060.107六编号4567891011项目混水内墙混水外墙序号0.5砖0.75砖1砖1.5砖及1.5砖以外0.5砖0.75砖1砖1.5砖2砖及2砖以外综合塔吊1.381.341.020.9941.51.441.091.041.01一机吊1.591.551.241.211.711.651.31.251.22二砌砖0.8650.8150.4820.4480.980.9150.5490.4910.458三运输塔吊0.4340.4370.440.440.4340.4370.440.440.44四机吊0.6420.6450.6540.6540.6420.6450.6520.6520.652五调制砂浆0.0850.0890.1010.1060.0850.0890.1010.1060.107六编号121314151617181920例如:(1)。某工程砌筑2砖墙厚混水外墙,工程量150m³,每天有22名工人在现场施工,试计算完成该项工程的施工天数(塔吊运输)。解:表2—1中查出,砌筑2砖厚混水外墙的综合时间定额为1.01工日/m³。该工程所需的劳动量=1.01x150=151.5(工日)完成该工程的施工天数=151.5/22=6.89=7(天)(2)。产量定额的应用某办公楼内墙抹灰工程,计划施工25天完成,抹灰班安排13名工人施工,产量定额为9.52㎡/工日,计算抹灰班应完成的抹灰面积。解:总工日数=25x13=325(工日),应完成的抹灰面积=9.52x325=3094(㎡)

1 / 2
下载文档,编辑使用

©2015-2020 m.777doc.com 三七文档.

备案号:鲁ICP备2024069028号-1 客服联系 QQ:2149211541

×
保存成功