自在城市花园A地块大体积混凝土施工方案1目录一、编制依据.......................................................2二、工程概况、特点.................................................2三、施工部署.......................................................33.1劳动力(人员)安排....................................................................................33.2机械、车辆配备............................................................................................43.3技术管理安排................................................................................................4四、施工准备.......................................................54.1技术准备........................................................................................................54.2生产准备........................................................................................................5五、混凝土拌制、供货...............................................55.1供货技术指标................................................................................................65.2供货验收........................................................................................................6六、混凝土运输.....................................................6七、混凝土浇筑.....................................................77.1浇筑施工工艺流程........................................................................................77.2混凝土浇筑顺序............................................................................................77.3浇筑方法........................................................................................................77.4钢筋防止移位措施........................................................................................97.5泌水处理........................................................................................................97.6表面防裂施工技术要点................................................................................9八、混凝土养护.....................................................9九、试块留置......................................................10十、泵送作业......................................................1010.1泵送程序....................................................................................................1010.2泵送操作要求............................................................................................10十一、混凝土裂缝温度验算及测温....................................1111.1裂缝温度验算.............................................................................................1111.2温度测试.....................................................................................................14十二、裂缝防止要点及修补预案......................................1512.1裂缝的防治要点.........................................................................................1512.2裂缝修补预案.............................................................................................16十三、质量保证....................................................1813.1质量主控项目............................................................................................1813.2一般项目....................................................................................................1813.3应注意的质量问题.....................................................................................1813.4混凝土工程质量预控.................................................................................19十四、安全文明施工................................................19自在城市花园A地块大体积混凝土施工方案2A地块4、5号楼大体积混凝土施工方案一、编制依据1、《大体积混凝土施工规范》(GB50496-2009);2、《混凝土结构工程施工质量验收规范》(GB50204-2002);3、《普通混凝土配合比设计规程》(JGJ55-2000);4、《高层建筑施工》(第二版,胡世德主编);5、自在城市花园A地块设计图纸;6、本公司有关施工、施工质量、安全生产、技术管理等文件。二、工程概况、特点自在城市花园A地块4、5号楼地下室长211.5米、宽78.7米、占地面积约16645平方米。按后浇带划分,共分为9块,基础底板厚500mm,本工程承台表如下:管桩承台见4、5号楼承台详图。根据后浇带划分的每个施工段混凝土方量约1500m3。地下室底板面积大、体积大,为避免底板出现裂缝及今后出现渗水现象,施工过程中要严格按照后浇带分区,注意混凝土的浇筑顺序及混凝土浇筑方法,分层浇筑,一次浇筑完毕;同时,在混凝土配合比上进行优化,采用水化热较少水泥,控制原材料,采取散热、养护等相应措施。本工程处于居民生活区,混凝土连续浇筑时间尽可能安排在早6点至晚10自在城市花园A地块大体积混凝土施工方案3点之间完成,因此,组织本次基础底板混凝土浇筑必须从:汽车泵、混凝土运输罐车的配备,商品混凝土供货速度,混凝土罐车进场运输路线,混凝土浇筑班组及振捣手、振捣机具安排,确保在此时间区段内完成混凝土浇筑任务。三、施工部署3.1劳动力(人员)安排为保证基础底板混凝土的连续浇筑,浇筑时配备两个浇筑小组,具体人员配备如下(其他工种配合)具体人员配备表3-1序号工种名称人员数量主要人员名单备注1现场生产总指挥1人李涛2现场技术总指挥1人张于磊3混凝土供货验收2人周建春、魏豆豆4混凝土浇筑队长2人5泵车处放料2人×2=4人6浇筑点放料3人×2=6人7振捣手4人×2=8人8找平、抹光、压实8人×2=16人9护模2人10护筋2人11电工2人12泵管移动4人杂工13泵车紧急修理机工4人泵车租赁商配备2人14试验员1人彭登伟15测温孔布置及施工员2人张小龙、冀慧明自在城市花园A地块大体积混凝土施工方案416现场车辆交通调度1人彭力总人数58人3.2机械、车辆配备现场配置混凝土输送泵、混凝土罐车计算:本工程拟采用型号HBT80D混凝土输出泵,混凝土泵每小时最大混凝土输出量80m3,混凝土泵的实际平均输出量1max1QQ=80×0.80×0.6=38.4。混凝土泵配置的数量(以20h完成1500m3计算):TQQN1=1500/(38.4×20)=1.95台,现场采用两台混凝土泵满足施工要求。混凝土运输车辆按照现场泵送能力(实际平均输出量Q1)配置,每罐车装方量以8m3计:8.4207550608604.386060101111TSLVQN即每台混凝土泵配备5辆混凝土运输车满足要求,考虑到兴业路修建及中途堵车等情况,现场配置混凝土运输车12辆。式中1N—混凝土搅拌运输车台数;1Q—每台混凝土泵车的实际输出量(hm3);1V—每台混凝土搅拌运输车容量(3m);0S—混凝土搅拌运输车平均行驶速度(hkm);1L—混凝土搅拌运输车往返距离;1T—每台混凝土搅拌运输车总计停歇时间;3.3技术管理安排3.3.1对混凝土振捣手上岗前进行技术交底,交底目的必须让每位参加大体积混凝土底板浇筑的人员知道:混凝土的浇筑量,浇筑时间,浇筑流水线,浇筑振捣的技术要求,质量要求,各岗位人员的职责,各岗位人员的配合。3.3.2混凝土浇筑过程中安排专人负责商品混凝土供货验收。(坍落度14~16cm,供货小票)并填写浇灌记录。自在城市花园A地块大体积混凝土施工方案53.3.3项目经理、技术负责人到场参与协调、指挥大体积混凝土浇筑;工长、质检员、技术员深入施工一线,跟踪监督、检查现场的施工状况。3.3.4专人负责大体积混凝土浇筑后的养护、测温工作,发现控制温差值超过指标,及时反馈到项目技术部,并采取措施,降低混凝土温升和温降的梯度,降低混凝土中心温度和表面混凝土温度差,降低混凝土表面温度和大气环