1目录一、工程概况...............................................................................................................2二、线路布置及线路截面选择...................................................................................2三、施工临时用电计算:...........................................................................................3四、施工现场安全组织措施:...................................................................................8五、施工现场安全用电技术措施.............................................................................13(一)、接地与接零.............................................................................................13(二)配置漏电保护器.......................................................................................14(三)配电装置...................................................................................................14六、电器防火措施.......................................................................................................................................15附:1临时施工用电平面布置图2、临时用电系统图3、电力负荷及导线截面选用表2施工现场临时用电施工方案一、工程概况成都市中西医结合医院迁建工程位于成都市南面高新区,武侯大道北侧,元华路东侧。由综合楼、行政楼、传染病筛检站等建筑组成,总建筑面积约68332.00m2,建筑高度最高达48m,施工场地约10万㎡,东西方向相距约150m,南北方向相距175m。现场施工用电由甲方指定的箱式变压器内接出,现场临时用电线路敷设采用TN—S三相五线制,以穿电缆沿围墙埋地敷设为主的方式。照明和动力用电分开,开关箱采用“一机一箱一闸一漏”安全用电的方案,分配电箱严格采用安全部门监制的标准电源开关箱,并配有安全用电漏电保护系统。对住宿、食堂、办公室用电作了严格的安全保护措施。编制依据:严格按照JGJ46-88《施工现场临时用电安全技术规范》和JGJ59-99《建筑施工安全检查标准》,编制现场施工用电方案,以加强对现场临时用电的管理,保证施工用电安全可靠,经济合理,达到用电设备安装、维修方便和保障现场作业人员人身安全及机械设备安全的目的。二、线路布置及线路截面选择供电方式选择:根据施工现场的实际情况,建设单位分别提供400kVA、315kVA箱式变压器各一台。因此现场施工用电分配也据此分别A、B两区,(详见临时施工用电总平面布置图)。原则上以P轴以南为A区,使用315kVA变压器,P轴以北为B区使用400KVA变压器,各用电区采用BV-1000V穿PVC管埋地及沿墙敷设相3结合的方式进行布线。(从变压器到各总配电柜用VV-1000V电缆敷设)。变压器的选择:业主已为现场施工配备了一台400KVA的配电柜,根据现场用电实际情况还应再配一台315KVA的配电柜才能满足施工要求。为保证工程质量,现场配备一台250kW发电机,并与市电进行连锁,为停电应急用,不影响施工。为了保证供电质量,防止架空线与水平、垂直运输等机具的相互干扰,同时为施工现场的标准化、文明化管理创造有利条件,输电线路在非围墙边均按埋地敷设,各主要供电线路沿墙均设支架架空敷设(详附图)。三、施工临时用电计算:现场施工机具统计表:序号机具名称数量Pe(kW)Se(kVA)JCcostgP’e(kW)总功率(kW)备注1自升式塔机4350.40.850.6244..2177A、B区各2台2砼主机1600.71.026060B区3砼输送泵1900.71.029090B区4钢筋对焊机31000.30.850.6281243A区1台,B区2台5钢筋对焊机11000.30.850.628181A区1台,6交流电焊机2130.30.850.6210.521A区7钢筋竖焊机4360.30.51.731768A区2台,B区2台8弯钢机430.850.7512A区2台,B区2台9钢筋切断机45.50.850.7522A区2台,B区2台10钢筋调直机27.50.850.7515A区1台,B区1台11砼震捣器81.10.651.178.8A区4台,B区4台12木工园盘锯260.850.6212A区413木工刨木机250.850.6210A区14镝灯63.521A区15照明12020A区A区:(315KVA变压器)用电设备:1、自升式塔机Pe=2Pe1=2×35×0.4=44.25kW×2=88.5kW2、钢筋对焊机:Pe1=Se1TC×cos3=100×0.4×0.85×3=81kW×2=162kW3、电焊机Pe=SeTC×cos3=13×3×0.85×3×2=21kW4、钢筋竖焊机:Pe=SeTC×cos3=36×3×0.5×3×2=34kW5、弯钢机:Pe=6kW(3×2)6、钢切断机:Pe=5.5×2=11kW7、钢筋调直机:Pe=7.5kW8、砼振捣器:Pe=1.1×4=4.4kW9、木工园盘锯:Pe=6×2=12kW10、木工刨木机:Pe=5×2=10kW11、镝灯:Pe=3.5×6=21kW12、照明:Pe=20kWA区:5Pj=396kWK=0.6Pj=396×0.60=237QjA=237×0.75=178kVARSjA=22237178=296kVA296448()30.383jAjAsIAUA区导线截面选择(环境温度40℃)。XV-1Kv-3×240+2×120(mm2)AΦ=00PjLCU=237200775=123㎜2A0≥0.5AΦ=62㎜2∴满足使用要求A-1回路:Pe=166.5cosθ=0.8tgθ=0.751、塔机144.25kW2、电焊机2台:21kW3、钢筋竖焊机2台:34kW4、砼振捣器4台:4×1.1=4.4kW5、木工园盘锯:12kW6、木工刨木机:10kW7、照明:41kWK=0.6tg=0.75IPj=Pe×0.6=166.5×0.6=100kWQjA-1=100×0.75=75kVARSjA-1=222210075125PjAQjAkVA6I=125190()0.381.73A导线选择:(环境温度40℃)。VV-1kV-3×95+2×50PC40按电压降允许范围内选择AΦ=00100120772PcCU=78㎜2∴满足要求A-2回路:Pe=198.75kW1、塔机144.25kW2、钢筋对焊机:81kW3、钢筋对焊机:60kW4、弯钢机:6kW5、调直机:7.5kWA-2回路:Pj=0.6×Pe=119kWQj=119×0.75=90kVARSj=2211990150()kVAI=150227()0.381.73A导线选择:BX-1KW-3×120+2×70PC40B区(400KVA)用电设备:cosθ=0.8tgθ=0.751、自升式塔机:Pe=88.5kW2、钢筋对焊机:Pe=81+80=162kW73、砼泵:Pe=90kW4、砼主机;6Pe=60kW5、钢筋竖焊机:Pe=34kW6、钢筋弯钢机:Pe=6kW7、钢筋切断机:Pe=11kW8、钢筋调直机:Pe=7.5kW9、砼振捣器:Pe=1.1×4=4.4kWPe=442.4Pj=0.6×442.4=265kWQjB=265×0.75=199KVARSjB=22PjQj=22265199331kVAB区导线截面选择:331500()30.383jBSIAU导线:XV-1kV-3×240+2×120AB=200265160183()773PjLmmCU导线选择:XV-1kV-3×240+2×120(㎜2)PC40B区配电计算K1=0.6分三个回路:B-1:砼生产区、泵及主机Pe=90+60KW=150KWB-2:塔机1+钢筋竖焊机×2+砼振捣器+对焊机44.3+17×2=34+4.4+81=163kW8B-3:塔机+对焊+弯钢机+调直机Pc-3=44.3+81+11+7.5=143kWB-1:Pj=0.6×150=90kWQj=0.75×90=68kVARSj=229068113kVAI=3SjUo=113172()0.383AB-2:Pj-2=0.6×163=97kWQj-2=0.75×97=72kVARSj-2=229772121kVAI=3SjUo=121184()0.383AB-3:Pj-3=0.6×143=86kWQj-3=0.75×86=65kVARSj-3=228665108()kVAI=3SjUo=108163()0.383AB-1:选用导线BX-1kV-3×95+2×50PC40B-2::选用导线BX-1kV-3×95+2×50PC40B-3:选用导线:BX-3×70+2×35PC40PC40附:电力负荷及导线截面选择表9四、施工现场安全组织措施:(一)建立安全用电保护体系,项目经理、工长全面负责。工长主要负责总配电箱的检查。维修、操作者负责单机开关箱的检查、维护。公司质安科、现场质安员负责监督检查。(二)从配电柜引出的主线路均沿墙上固定支架架设或埋地敷设。(三)临时用电电缆线在非围墙位置均采用穿导管埋地敷设,严禁沿地面明设,并应避免机械操作和介质腐蚀。电缆在室外直接挖地沟埋地敷设的深度不小于0.6m,并应电缆上、下各均匀铺设不小于50mm厚的细砂,然后再覆盖砖后,加盖泥土硬质保护层。埋地线路边均应设明显的标识牌并有专人负责保护。(四)施工现场用电措施均应遵照建设环保部颁发的JGJ46-88《施工现场临时用电安全技术规范》,遵照“安全第一”的原则,按照国家有关标准,本供电系统用用TN—S(三相五线制)接零保护系统供电。其分配电箱、单机配电箱、楼层配电箱、插座箱实行三级配电、二级保护,均采用标准化工地规定使用的标准铁壳的电箱。(五)所有移动式、固定式的电气设备的金属外壳、配电箱、开关箱的金属外壳及箱门均与专用保护零线可靠连接,固定设备的保护零线截面不小于6mm2的铝线,移动式制备的保护零经理在绝缘良好的多股铜芯软电线,其截面不小于1.5mm2。(六)楼层供电随作业面的增高用楼层配电端子箱逐层接力敷设。楼层配电箱,安装在电气井口,进线采取穿管保护。楼层用电采用移动式分电箱和开关箱上楼,箱内的进出线采用橡皮绝缘电缆,设三相动力的设漏电开关,自动空气开关,漏电开关在下级开关箱(如插座箱等)中,视需要而设置(依规范要10求)。在总配电箱、分配电箱及塔机、砼输送泵处应作重复接地,且接地电阻应小于10Ω,必须极用焊接或压接方式连接,在所有电路末端均采用重复接地。(七)所有电子表器材料及元件均应购置正规合格产品,所有电器线路和设备的安装、维修和调整都必须有专人进行,发现问题及时解决。漏电开关必须定期检查,试验其动作可靠性。(八)所有电器(电工)操作人员必须持证上岗,并应配备相应的防护用