1混凝土施工方案编制:审核:审批:X年X月X日2目录1工程概况................................................................................................................42施工安排................................................................................................................42.1施工目标........................................................................................................42.2施工顺序及流水段........................................................................................42.3重点及难点....................................................................................................52.4组织机构及岗位职责....................................................................................63施工进度计划........................................................................................................74施工准备与资源配置计划....................................................................................74.1施工准备........................................................................................................74.1.1技术准备...............................................................................................74.1.2现场准备...............................................................................................94.1.3资金准备...............................................................................................94.2资源配置计划..............................................................................................105施工方法及工艺要求..........................................................................................115.1施工方法......................................................................................................115.1.1技术方案.............................................................................................115.1.2工艺流程.............................................................................................115.1.3组织措施.............................................................................................175.1.4检验手段.............................................................................................205.2重点说明......................................................................................................215.2.1质量通病.............................................................................................215.2.2安全文明施工.....................................................................................225.2.3部分节点处理.....................................................................................235.3“四新”技术应用......................................................................................235.3.1原材料要求.........................................................................................235.3.2配合比要求.........................................................................................245.3.3施工要求.............................................................................................2435.4雨期施工措施..............................................................................................255.4.1准备工作.............................................................................................255.4.2施工技术措施.....................................................................................255.4.3雨季安全措施.....................................................................................2641工程概况X工程总建筑面积为X㎡,地下X层,地上X层,总建筑高度为Xm,基础形式为X,底板厚度Xmm,结构形式为X。表1各部位砼强度等级及数量统计表序号部位强度等级抗渗等级数量备注1234……合计2施工安排2.1施工目标1、进度目标底板:浇筑完成±0.000:浇筑完成主体:浇筑完成2、质量目标:3、安全目标:4、环境目标:5、成本目标:2.2施工顺序及流水段1、施工顺序砼浇筑顺序依据的整体原则为:先地下后地上、先竖向后水平、先高标号后低标号、先低标高后高标高。52、流水段划分本工程流水段划分主要以图纸设计的膨胀加强带、后浇带、变形缝等结构缝为准。对于某些流水段划分线未留置在以上区域的,要做好止水措施(有防水要求的区域)及施工缝处理。施工缝的留置要严格按《砼结构工程施工质量验收规范》(GB50204-2002)执行。附件1《XXX工程施工流水段划分图》2.3重点及难点1、本工程底板砼厚度为Xmm,属典型大体积砼,砼浇筑及养护过程中的内外温差控制是砼施工的重点及难点。2、本工程底板砼长度为Xm,属超长无缝底板砼施工,砼裂缝控制是砼施工的重点及难点。3、本工程建筑总高度为Xm,对砼垂直输送技术要求较高,超高层砼泵送是砼施工的重点及难点。4、本工程最大砼强度等级为CX,浇筑部位关键且体量较大,高强砼施工工艺控制是砼施工的重点及难点。5、本工程楼板设计为GBF空心楼板,GBF管在砼浇筑过程中的抗浮处理为砼施工的重点及难点。6、本工程局部梁板为后张法预应力梁板,预应力砼为砼施工的重点及难点。7、本工程结构施工过程中存在多种不同强度等级的砼同步施工,相邻构件不同强度等级砼浇筑的范围较广、体量较大,避免强度混淆和结点处理不当是砼施工管理的重点。8、本工程部分主体结构砼浇筑正值冬季,北方地区严寒状态下的砼浇筑与养护是砼施工管理的重点及难点。……(以上为部分重点与难点罗列,请根据实际情况酌情予以增减)62.4组织机构及岗位职责1、组织机构项目经理项目书记商务经理生产经理安全总监项目总工工程管理部技术质量部物资管理部总承包部商务合约部安全管理部深化设计部综合办公室图1项目组织机构图2、岗位职责项目经理:①负责砼施工所需资源的整合与组织,包括人、财、物、机、法。②外部资源、关系、手续的协调者。③砼浇筑令的最终签署人。项目总工:①砼施工方案编制、审核、优化讨论的组织者,确保方案与设计文件及现行规范、规程的符合性,确保方案的可行性与科学性。②组织砼浇筑技术交底工作,组织砼施工的样板制作与验收工作。生产经理:①调动和组织各类资源服务于进度计划目标。②确保现场施工作业与施工方案的符合性与一致性。7商务经理:①做好合约交底,使施工管理人员明确合约要求。②做好砼成本核算,为项目盈亏分析做好基础铺垫。安全总监:①监督好安全专项方案和安全技术措施的落实情况。②组织好日常安全巡查和整改工作。责任工程师:①砼施工过程组织的直接操作者。②砼施工质量验收和整改的直接实施者。③施工技术交底和安全交底的贯彻落实者。3施工进度计划本工程工期紧、任务重,砼分项工程按预定进度计划如期完成是确保总进度计划目标顺利实现的必要条件之一。砼分项工程进度计划的编制依据为《施工组织设计》的总体要求,要确保该计划顺利推进,重点关注如下事项:①砼供应及时,为以防万一,可选择2~3家商砼供应单位。②砼浇筑场地满足施工需求,交通线路畅通,罐车通行方便。③施工机具、设备维护到位,运行良好。④各工种配备齐全,人员充分。附件2《XXX工程砼分项工程施工进度计划横道图》4施工准备与资源配置计划4.1施工准备4.1.1技术准备1、技术资料8组织相关技术人员认真学习设计蓝图、设计交底、图纸会审记录、设计变更、规范规程、施工合同、施工方案、技术交底、档案编制规程等技术资料,为施工管理做好全面铺垫。2、技术交底技术交底由砼责任工程师负责编制,项目总工负责审核把关,合格后予以下发。交底内容要求通俗易懂、简洁明了、有的放矢、操作性强。第一次技术交底安排在首次开盘之前,交底地点在会议室,参加人员包括项目部全体管理人员、劳务队伍全体管理人员、砼班组主要成员;第二次交底安排在首次开盘时,会议地