汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案1目录第一章编制说明.....................................................21.1、编制依据.......................................................21.2、编制目的.......................................................21.3、适用范围.......................................................2第二章工程概况.....................................................22.1、工程简介.......................................................22.2、水文气象地质条件...............................................52.3、施工技术准备...................................................5第三章施工技术方案..................................................63.1、墩柱质量控制标准...............................................63.2、墩柱施工方法及工艺技术方案.....................................63.3、工程质量保证措施..............................................103.4、测量工作的质量保证措施........................................123.5、钢筋质量保证措施..............................................123.6、砼施工重量保证措施............................................13第四章安全生产措施.................................................134.1确定安全生产目标的安全防范要点.................................134.2建立安全生产体系...............................................134.3、加强施工现场安全教育..........................................144.4主要施工项目安全技术措施.......................................15第五章、雨季施工措施...............................................17第六章、质量保证措施...............................................17第七章、环境保护...................................................17附件墩柱模版计算书................................................19汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案2高墩柱施工专项方案第一章编制说明1.1、编制依据1、《公路工程施工安全技术规程》(JTJ076-95)2、《公路桥涵技术规范》JTG/TF50-20113、《施工现场临时用电安全技术规范》(JCJ46-2005)4、《高速公路交通安全设施设计及施工技术规范》(JTJ74-94)5、《两阶段施工图设计》1.2、编制目的为了规范高墩柱分项工程施工,保证工程质量和施工安全,特制订本专项施工方案。1.3、适用范围本专项方案适用于本合同段所有墩柱施工作业。第二章工程概况2.1、工程简介本项目共有墩柱176根,其中15m以上高墩柱116根占总数的66%。分别位于官洞大桥、锡古塘大桥、曾洞大桥、琴口大桥。桥名墩位柱号柱径(m)柱高(cm)官洞大桥左2#11.62219.2官洞大桥左2#21.62206.7官洞大桥左2#31.62194.2官洞大桥右2#11.62230.2官洞大桥右2#21.61889.4官洞大桥左3#11.82592.8官洞大桥左3#21.82581.5官洞大桥左3#31.82570.2官洞大桥右3#11.82603.8官洞大桥右3#21.82621.8汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案3官洞大桥左4#11.82602.4官洞大桥左4#21.82592.3官洞大桥左4#31.82582.2官洞大桥右4#11.82613.4官洞大桥右4#21.82631.4官洞大桥左5#11.82597.9官洞大桥左5#21.82579.9官洞大桥右5#11.82608.9官洞大桥右5#21.82626.9官洞大桥左6#11.82629.4官洞大桥左6#21.82611.4官洞大桥右6#11.82640.4官洞大桥右6#21.82658.4官洞大桥左7#11.82576.8官洞大桥左7#21.82558.8官洞大桥右7#11.82587.8官洞大桥右7#21.82605.8官洞大桥右8#11.61681.1官洞大桥右8#21.62199.1锡古塘大桥右1#41.62130.3锡古塘大桥左2#21.61718.8锡古塘大桥右2#51.62027.8锡古塘大桥右2#41.62489.8锡古塘大桥左3#21.62652.7锡古塘大桥左3#11.62667.1锡古塘大桥左3#01.62681.5锡古塘大桥右3#51.62641.7锡古塘大桥右3#41.62623.7锡古塘大桥左4#21.61821锡古塘大桥左4#11.61834.2锡古塘大桥左4#01.61847.4锡古塘大桥右4#51.61590锡古塘大桥右4#41.61572琴口大桥左2#01.61941.7琴口大桥右2#31.61958.2琴口大桥右2#41.61985.2琴口大桥左3#01.62023.6琴口大桥左3#11.61996.6琴口大桥右3#31.62240.1琴口大桥右3#41.62267.1琴口大桥左4#01.62257琴口大桥左4#11.62230琴口大桥右4#31.62273.5汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案4琴口大桥右4#41.62300.5琴口大桥左5#01.62290.5琴口大桥左5#11.62263.5琴口大桥右5#31.62307.7琴口大桥右5#41.62334琴口大桥左6#01.82454琴口大桥左6#11.82427琴口大桥右6#31.82470.5琴口大桥右6#41.82497.5琴口大桥左7#01.82407.5琴口大桥左7#11.82380.5琴口大桥右7#31.82334琴口大桥右7#41.82361琴口大桥左8#01.83031琴口大桥左8#11.83004琴口大桥右8#31.82907.5琴口大桥右8#41.82934.5琴口大桥左9#01.82964.8琴口大桥左9#11.82939琴口大桥右9#31.82980.6琴口大桥右9#41.83006.4琴口大桥左10#01.82998.8琴口大桥左10#11.82974.6琴口大桥右10#31.83013.6琴口大桥右10#41.83037.8琴口大桥左11#01.83032.8琴口大桥左11#11.83010.2琴口大桥右11#31.83046.6琴口大桥右11#41.83069.2琴口大桥左12#01.82956.8琴口大桥左12#11.82935.8琴口大桥右12#31.82969.6琴口大桥右12#41.82990.6琴口大桥左13#01.62750.8琴口大桥左13#11.62141.3琴口大桥右13#31.82622.6琴口大桥右13#41.82642.1琴口大桥左14#01.61794.9琴口大桥左14#11.61776.9琴口大桥右14#31.61805.5琴口大桥右14#41.61824.6曾洞大桥右1#11.82031.9曾洞大桥右1#21.82053.3汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案5曾洞大桥左2#123252.2曾洞大桥左2#223225.2曾洞大桥右2#123268.7曾洞大桥右2#223295.7曾洞大桥左3#123401.2曾洞大桥左3#223374.2曾洞大桥右3#123417.7曾洞大桥右3#223444.7曾洞大桥左4#123156.2曾洞大桥左4#223129.2曾洞大桥右4#123472.7曾洞大桥右4#223499.7曾洞大桥左5#123395.2曾洞大桥左5#223368.2曾洞大桥右5#123411.7曾洞大桥右5#223438.7曾洞大桥左6#122470.3曾洞大桥左6#222443.3曾洞大桥右6#121986.8曾洞大桥右6#222013.82.2、水文气象地质条件项目位于广东省中部偏东北,属中纬度亚热带季风性湿润气候,夏长冬短,年平均气温21℃,最低极限气温-1℃,最高极端气温38℃,偶尔霜冻及结冰现象:多年平均降雨量在1400~2400毫米,每年五至九月份为雨季,五个月的降水量占全年的64~75%;主要地层为燕山期花岗岩及下古生代变质岩(如片麻岩等)。基岩出露处,节理裂隙发育。上覆土层较松散,风化层较厚,稳定性差,局部见崩塌、滑坡、水土流失,坡面稳定性较差2.3、施工技术准备组织技术人员,全面熟悉设计图纸,了解设计意图,绘制施工详图,对整个工程的施工布署、施工计划和施工方法作出科学的安排;使分项工程施工能够有组织、有计划、有秩序的规范进行。汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案6第三章施工技术方案3.1、墩柱质量控制标准1、钢筋加工及安装实测项目项次检查项目规定值或允许偏差检查方法和频率1受力钢筋间距(mm)两排以上排距±5每构件检查2个断面,用尺量同排梁板、拱肋±10基础、锚碇、墩台、柱±20灌注桩±202箍筋、横向水平钢筋、螺旋筋间距(mm)+0,-20每构件检查5~10个间距3钢筋骨架尺寸(mm)长±10按骨架总数30%抽查宽、高或直径±5每骨架抽查30%4弯起钢筋位置(mm)±20每构件沿模板周边检查8处5保护层厚度(mm)柱、梁、拱肋±5基础、锚碇、墩台±10板±32、混凝土浇筑项次检查项目规定值或允许偏差检查方法和频率1混凝土强度(Mpa)在设计标准内2尺寸(mm)±30用尺量:长、宽各2处3顶面标高±20水准仪:测量5点4轴线偏位15全站仪:测量纵、横各2点3.2、墩柱施工方法及工艺技术方案1、总体施工方案:在进行墩柱施工前,先做好充分的准备工作,按要求合理配置进行该分项工程的施工人员、设备及材料。做好精确的平面控制和轴线放样工作,并经测量监汕湛高速揭博项目T7合同段项目经理部高墩柱施工专项方案7理工程师抽检合格后安装已制作好的墩柱钢筋笼,然后按照设计要求进行模板的制作及安装,继而进行混凝土的浇筑工作,2天后进行拆模养生。每一道工序都严格按照设计规范要求合理地安排施工,并报监理工程师抽检,经检验合格后方进行下一道工序。2、墩柱施工工艺工艺流程:轴线放样——墩柱钢筋制作安装——墩柱模板的安装——墩柱混凝土的浇筑——拆模养生A、施工准备:在施工前我们根据实际情况,其准备工作如下:a、将墩柱的轴线位置及墩底标高精确测定,检查无误后方可施工;b、将墩柱与桩基连接处进行凿毛;c、将墩柱混凝土施工安排在晴天进行,开工后连续快速浇筑。B、钢筋制作安装:桩基经自检和抽检合格后,立即放出墩柱的轴线,方可进行钢筋的制作安装:用吊车将墩柱的钢筋笼吊起,与桩基的预埋墩柱钢筋对齐。钢筋的焊接、绑条,在焊接前应其轴线位置及