工程量现场签证单工程名称:砚山太科光伏电站通讯工程编号:分部工程名称单元工程名称单项工程名称光纤更换数量11.光纤敷设150米;2.车2辆3.技工6人;4.光纤熔接48芯;施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:02分部工程名称35kV开关场单元工程名称电缆沟施工单项工程名称800×800电缆沟数量32m电缆沟土方开挖:V=32m×1.6m×1m+8m×1.6m×1=64m3(30m包含过公路电缆沟)电缆沟以接新主控室重挖段:V=7×1.6×1=11.2m3电缆沟C15混凝土:V=32m×1.6m×0.15m=7.68m3(30m包含过公路电缆沟)电缆沟砖砌体:V=27.7m×0.9m×0.24m×2=12m3电缆沟抹灰:V=32m×0.9m×2+27.7m×0.24m×2+32×0.4×2+32×0.8=122.1m2电缆沟C25混凝土:V=4.3m×0.24m×0.9m×2+4.3×0.3+4.3×0.9×0.2=4m3(注:过公路电缆沟为钢筋混凝土,有模板)电缆沟抹灰:V=4.3m×0.8m×2=6.88m2施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:03分部工程名称35kV—110kV开关场单元工程名称基础施工单项工程名称端子箱安装数量27个700×500开挖土石方:V=1m×0.9m×0.8m×16=11.52m3800×650开挖土石方:V=1.2m×1m×0.8m×11=11m3700×500垫层混凝土:V=1m×0.15m×0.9m×16个=2.16m3800×650垫层混凝土:V=1.2m×1m×0.15m×11个=1.98m3700×500砖砌体:V=(0.9m×0.12m×0.6m×2+0.35m×0.12m×0.6m×2×16个=3m3800×650砖砌体:V=(1.1m×0.12m×0.6m×2+0.5m×0.12m×0.6m×2)×11个=2.53m3700×500压顶混凝土:V=(0.9m×0.12m×0.3m×2+0.35m×0.12m×0.3m×2)×16个=1.44m3800×650压顶混凝土:V=(1.1m×0.12m×0.3m×2+0.5m×0.12m×0.3m×2)×11个=1.3m3(注:有模板)700×500抹灰:V1=(0.9m×0.7m×2+0.7m×0.7m×2+0.35m×0.7m×2+0.5m×0.7m×2+0.9m×0.12m×2+0.7m×0.12m×2)×16个=61m2800×650抹灰:V1=(1.1m×0.7m×2+0.8m×0.7m×2+0.7m×0.6m×2+0.5m×0.7m×2+1.1m×0.12m×2+0.8m×0.12m×2)×11个=51.2m2施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日新增工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:04分部工程名称110kV开关场单元工程名称基础施工单项工程名称110kV#2主变压器102断路器技改数量1基土方开挖:V=1.4×4.3×1=6.02m3垫层混凝土:V=1.4×4.3×0.2=1.2m3基础混凝土:V=1.2×4×0.8=3.84m3抹灰:S=4×0.8×2+1.2×0.8×2+4×1.2=13.12m2拆除混凝土:V=5.2×0.5×0.2+1.8×1.2×0.2+6×1.3×0.2+3.1×1.1×0.2+4.5×1.7×0.2=4.7m3碎石回填:110kV开关场:V=29×4.2×0.3+4×14×0.3+16×4×0.3=68.3m335kV开关场:V=6×3×0.6+7×1.6×1=22.2m3施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日新增工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:05分部工程名称10kV出线侧单元工程名称基础施工单项工程名称10kV出线侧电缆沟改造工程工程量29m土方开挖:(电缆井)V=4×29×1.2=139.2m39电缆沟V=1.3×29×1.2=45.2m3拆除混凝土地板:V=2.5×0.2×29=14.5m3混凝土垫层:电缆沟及电缆井:V=5.3×0.2×29=31m3电缆井上线电缆沟V=1.8×0.7×0.2×10=3m3砖砌体:电缆井:V=28×2.7×1-3.14×12×1×10+3.14×0.62×1×10=55.5m3电缆沟:V=28×0.35×1=9.8m3电缆井出线电缆沟:V=(1.8×0.7×0.6-0.46×1.8×0.5)×10个=3.42m3抹灰:电缆井:S=28×2.7-3.14×12×10个+2×3.14×1×1×10个+2×3.14×0.3×1×10个+3.14×0.62×10=137.1m2电缆沟:V=28×1×2+0.35×28=65.8m2电缆井出线电缆沟:V=(1.8×0.6×3面+0.46×0.6×4面)×10个=43.44m2施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日新增工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:06分部工程名称10kV出线侧单元工程名称基础施工单项工程名称10kV出线侧排水改造工程工程量35m土方开挖:V=0.6×0.4×35=7.7m3垫层混凝土:V=0.6×0.2×35=4.2m3砖砌体:V=0.3×0.12×35×2+0.3×0.12×0.36×2=2.32m3抹灰:S=0.3×35×2+0.3×0.36×2=19.42m3盖板:混凝土预制盖板规格500㎜×300㎜,全长32米,共计64块施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日新增工程量签证单工程名称:110kV回龙变电站10kV高压开关柜改造工程编号:07分部工程名称10kV高压室装修及排水沟增加工程单元工程名称基础施工单项工程名称10kV高压室装修及增加排水设施工程量土方开挖:排水沟:V=0.8×1.3×5=5.2m3集水井:V=1.5×1.5×1.6=3.6m3C25垫层混凝土:排水沟:V=0.8×1.3×5×0.2=1.04m3集水井:V=1.7×1.7×0.2=0.6m3砖砌体:排水沟:V=0.3×0.24×35×2=5.6m3集水井:V=1.5×1.5×0.24×2+1.06×0.24×1.6×2=2m3拖把池:V=1.1×0.7×0.5×2=0.38m3抹灰:排水沟:V=0.3×0.24×35×2=5.6m3集水井:V=1.5×1.6×2+1.06×1.6×2+1.5×0.3×4=10m2排水管埋设开挖土方V=28×1×1.2=33.6m3更换高压室排水管50米,10KV场地排水至厂区围墙外排水管埋设33米砖砌体:高压室小门封堵:V=1.5×0.37×2=1.11m3高压室门洞补砌:V=(1.7×0.7×0.37+2.5×0.4×0.37)×2=1.62m3(两道)高压室窗子补砌:V=0.8×1×0.37×2=0.6m3(两扇)抹灰:高压室小门封堵:S=1.5×2.5×2=7.5m2高压室门洞补砌:S=(1.7×0.7×2+2.5×0.4×2+2.5×0.37×2)×2=12.5m2(两道)高压室窗子补砌:S=(0.8×1×2+0.8×0.37×2=4.4m2(两扇)刮腻子粉:内墙:S=26m×6m×2+6m×5m×2-1.7×2.5×2(门)-1.7×3.2(门)-1×0.6×10(窗子)-1×0.8×4(窗子)+(1×0.2×2+0.6×0.2×2)×10(窗檐)+(1×0.2×2+0.8×0.2×2)×4(窗檐)+(2.5×0.37×2+1.7×0.37)×2+3.2×0.37×2+1.7×0.37=366.1m2屋顶:S=26m×5m+5×0.4×2×6(梁)=154m2外墙:S=5.8×5=29m2挑檐:S=27.4×0.7×2+7.2×0.7×2=48.44m2门外框:S=(0.7×3.2×2+1.7×0.7)×2+2×0.2×2+1.2×0.2×2=12.62m2高压室原粉层脱落处:V=2.1×3+2×4=14.3m2(两处)站外排水土方开挖:共清运177车(每车可运2.1m3)V=177×2.1=371m310kV高压室照明改造12盏施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日工程量签证单工程名称:110kV回龙变电站10kV高压开关柜改造工程编号:08分部工程名称10kV高压开关柜改造单元工程名称基础施工单项工程名称电缆沟及盘柜基础工程量(m3)23.4m开挖土石方:V=23.4×1.4×1.2+13.45×1.72×1.2=67.1m3拆除混凝土:V=23.4×0.4×1.2+26.54×0.15×4.4=28.7m3回填土石方:V=26.54×0.6×0.8=12.7m3C25垫层混凝土:V=23.4×0.2×2+13.45×0.2×2=15m3砖砌体:V=23.4×0.24×0.65+1.04×0.24×0.65+1.72×0.24×0.65×2+8.735×0.24×0.65+0.8×3.87×0.65+11.85×0.36×0.65=10.5m3C25压顶混凝土:V=23.4×0.24×0.2+1.04×0.24×0.2+1.72×0.24×0.2×2+8.735×0.24×0.2+0.8×3.87×0.2+11.85×0.36×0.2=3.23m3盘柜端子混凝土:V=0.27×0.8×0.85×10个=1.84m3高压室地坪混凝土:V=23×1.8×0.2+3×4.8×0.2=11.2抹灰:S=23.4×0.9+1.04×0.9+1.72×0.9+0.895×0.9+11.45×0.9+1.72×0.9+8.735×0.9+3.87×0.9×2+0.8×0.9×22面+0.27×0.9×20面+48.7×0.24+0.27×0.8×10个+3.87×0.8+4.8×26.4=215.4m2施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年月日新增工程量签证单工程名称:110kV回龙变电站主控室综合自动化改造工程编号:09分部工程名称屋外配电装置单元工程名称电缆井单项工程名称电缆井改造工程工程量6处砖砌体:110kV2#主变低压侧:V=0.6×0.12×0.4×6面+0.4×0.12×0.4×3面+1.1×0.12×0.4+0.6×0.12×0.4×2=0.5m3高压室进线侧:V=1.4×0.24×0.4×2+0.6×0.24×0.4=0.33m3110kV2#主变低压侧:V=0.35×0.12×0.4×6=0.1m3110kV1#主变中压侧:V=3×0.6×0.12×2+0.6×0.6×0.12×2=0.51m3C25垫层:110kV2#主变低压侧:V=0.6×0.4×0.15×3+1.1×0.4×0.15=0.17m3高压室进线侧:V=1.4×1.3×0.15=0.3m3110kV1#主变中压侧:V=3×0.9×0.15=0.4m3抹灰:110kV2#主变低压:S=0.6×0.4×6面+0.4×0.4×3面+1.1×0.4+0.6×0.4×2面+0.6×0.24×8面+0.4×0.24×3面+1.1×0.24=4.54m2高压室进线侧:S=1.4×0.4×2面+0.6×0.4+3.4×0.24+3.4×0.3=3.2m2110kV1#主变低压:S=0.24×0.4×12+0.35×0.4×6=2m2110kV1#主变中压侧:S=0.6×3×2+0.6×0.6×2+3×0.12×2+0.6×0.12×2=5.2m2施工单位代表签字:年月日建设单位负责人签字:年月日建设单位分管领导签字:年