贵州省赤水至望谟高速公路(仁怀至赤水段)RCTJ-18合同段(K95+100.000~K100+000.000)人工挖孔桩专项施工方案编制:审核:审批:编制单位:仁怀至赤水高速公路RCTJ-18项目经理部编制日期:二〇一〇年十一月二十日i目录一、编制依据...............................................................................................................1二、工程概述...............................................................................................................12.1工程概况..........................................................................................................12.2工程地质..........................................................................................................1三、主要施工方法.......................................................................................................23.1施工准备..........................................................................................................23.2挖孔桩施工工艺..............................................................................................23.3挖孔桩施工方法..............................................................................................4四、质量进度控制措施...............................................................................................94.1质量标准..........................................................................................................94.2质量保证措施................................................................................................104.3技术保证措施................................................................................................104.4主要机械设备................................................................................................114.5劳动组织........................................................................................................11五、施工安全技术措施.............................................................................................11六、危险因素及防范措施.........................................................................................166.1重大危险因素的识别....................................................................................166.2对重大危险因素的评价................................................................................166.3安全防范措施................................................................................................17七、环境保护与水土保持措施.................................................................................217.1自然及生态环境保护措施............................................................................217.2水资源环境保护和水土保持措施................................................................217.3大气环境、噪音及粉尘的防治措施............................................................227.4固体废弃物防治措施....................................................................................22八、应急救援预案.....................................................................................................228.1抢险应急组织安排及工作流程....................................................................228.2突发事件应急准备........................................................................................238.3突发事件分析及应急措施............................................................................248.4物资、机具、设备........................................................................................258.5恢复生产及应急抢险总结............................................................................26附:相关联系电话.....................................................................................................27附:应急救援储备物质.............................................................................................281一、编制依据1、两阶段施工图《井干田、枣子林大桥》、《黄金湾特大桥》、《土城特大桥》;2、两阶段施工图《路线工程地质勘测报告》;3、桥涵施工技术规范JTJ041-2000;4、《中华人民共和国安全生产法》;5、《中华人民共和国环境保护法》;6、《建设工程安全生产管理条例》国务院令第393号;7、交通部《公路工程施工安全技术规程》(JTJ076-95);8、《公路水运工程安全生产监督管理办法》(交通部令2007年第1号);9、《施工现场临时用电安全技术规范》(JGJ46-2005);10、《爆破安全规程》(GB6722-2003);11、《贵州省公路局高速公路建设项目安全生产管理办法(试行)》黔路发(2010)13号;12、《贵州省公路局高速公路建设项目环境保护管理办法(试行)》黔路发(2010)5号;13、《贵州省公路局高速公路建设项目安全生产应急预案(试行)》黔路发(2010)13号;14、《遵义市在建高速公路建设工程项目安全管理规定》的通知(遵府办发(2010)160号);15、《关于仁赤高速公路建设项目人工挖孔桩安全生产、文明施工的有关规定的通知》仁赤总监办安发(2010)1号。二、工程概述2.1工程概况本合同段共有大桥两座、特大桥两座,桩径为φ1.5、φ1.6、φ1.8、φ2.0、φ2.3m五种类型,共有孔桩421根,孔桩最深48米,最浅7米,全部采用人工挖孔桩,整个线路所处地形为赤水河河谷区,以谷坡、冲沟、支流沟组合为主,河谷切割交大,山势雄伟。2.2工程地质桥区覆盖层为残坡积层碎石土。下伏基岩为侏罗系中统沙溪庙组砂岩、泥岩。地层呈单斜产出。2三、主要施工方法根据实际地质情况与设计图图纸相关文件规定,全部采用人工挖孔桩施工。3.1施工准备1、组织施工管理人员熟悉施工图纸及场区工程水文地质条件,熟悉施工验收规程及主要施工规程,并对施工管理和操作人员作详细技术交底。2、测量放线。按图纸进行总体测量放线,把工程总体布局放出,对控制桩进行绑点记录,并进行认真复核,确保测量精度满足规范要求。3、桩基础现场接通水电,为保证桩基施工连续作业,设置发电机组。4、在平整好的场地上,根据已放出的控制桩将孔桩位置定出,并在四周绑点控制,以便核对。5、准备施工必须部分物资。3.2挖孔桩施工工艺同一墩台宜跳孔开挖,相邻开挖孔净距不小于3米。当桩长不一致时,应先开挖最长桩。挖孔桩施工工艺流程图见下页3人工挖孔桩施工工艺流程图否是平整场地测量定位挖第一节孔桩土安装垂直运输设备安模浇第一节砼护壁安装活动吊桶在护壁上二次投测标高及桩位十字线轴线第二(下)节桩身挖土安装排水通风照明设施清理桩孔四壁、校核桩孔垂直度和直径拆第一(上)节模板安第二(下)节模板浇第二(下)节砼护壁到桩底设计标高否桩底清理及检查持力层吊放钢筋笼浇注桩身混凝土及养护桩身检测下一工序施工43.3挖孔桩施工方法1、挖孔前施工准备施工前,平整场地,铲除松软土层并夯实,施测孔桩十字线,桩孔位置定位,设置护桩并经常检查校核。孔口四周挖排水沟,作好排水系统,及时排除地表水,搭好孔口雨棚,安装提升设备,布置好出碴道路,合理堆放材料和机具,孔口四周2m范围内不得堆放水泥杂物。孔口四周设带警示色的钢管围栏并挂密目安全网,高度宜在120cm,防止土、石、杂物及人员落入孔内。2、孔桩开挖(1)井孔开挖由人工自上而下逐层用镐、锹进行,挖土次序为先挖中间部分后挖周边。挖至地下水位时,在孔内挖集水井,设小型潜水泵将水排至场地排水沟内,集水井随挖土加深而加深。随着挖孔加深,及时安装孔底通风、照明、防护、通讯等设备,垂直运输如下:挖孔桩垂直运输示意图(2)挖孔达到设计标高后,进行孔底处理,使孔底平整、无松碴淤泥及沉碴,嵌入岩层符合设计要求,经监理工程师检查合格后应马