1****二期工程脚手架施工方案中国建筑****工程局有限公司****二期工程项目经理部二OO八年七月十八日2目录1.编制依据:································32.工程概况:································33.脚手架构配件的质量标准:·························34.脚手架的用途:······························45.脚手架搭设方案:·····························46.脚手架体系设计:·····························41体系选择·······························42脚手架稳定性验算···························57.脚手架的搭设方法和技术要求:······················107.1落地脚手架····························107.2挑架式钢管脚手架·························138.脚手架搭设技术措施:··························159.脚手架搭设质量标准:··························1610.脚手架的搭设及安全措施:·······················1711.满堂脚手架:·····························1911.1承重结构的脚手架·························1911.2承重结构的脚手架搭设·······················1911.3承重结构的脚手架检查与验收····················2011.4承重结构的脚手架的使用管理····················2011.5满堂脚手架的整体稳定性计算即立杆的稳定性计算···········2012.脚手架的拆除:····························2112.1脚手架的搭设规定·························2112.2脚手架的使用规定·························2212.3脚手架拆除规定··························2313.脚手架的质量检查及验收和管理:·····················2314.脚手架搭设安全注意事项:·······················2531.编制依据:建筑施工扣件式钢管脚手架安全技术规范(JGJ130-2001)建筑施工安全检查标准(JGJ59-99)****二期工程施工组织设计****二期工程施工图纸2.工程概况:工程名称:****二期工程建设单位:天津****置业有限公司设计单位:天津市****建筑设计有限公司监理单位:天津市****建设监理公司****监理所建设地点:天津市****区****路东侧结构类型及层数:本工程为砖混、框架及框剪结构,其中配套用房地上二层,29、30#楼地上11层,28#楼地上5层,地下车库1层。建筑规模:24945.48㎡(其中地下部分为3909㎡)承包方式:包工包料质量标准:达到国家施工验收规范合格标准开竣工日期及工期:2008年6月28日开工,2009年8月30日竣工;总工期429天(日历天)(2008年6月28日为招标日期,实际开工日期为7月18日)。文明施工目标:保证现场文明施工,创建文明施工环境。3.脚手架构配件的质量标准:根据本工程结构特点及钢管强度高、刚度好等优点,本工程外脚手架均采用扣件式钢管脚手架,用于本工程外脚手架的所有材料必须遵循以下原则:3.1钢管采用外径48mm、壁厚3.5mm的焊接钢管,钢管的材质使用力学性适中、稳定的Q235钢,其材质应符合《碳素结构钢》(GB700─88)的相应规定。钢管有弯曲、压扁等缺陷的不得使用。用于立杆、大横杆、剪刀撑和斜杆的长度宜为4─6m,便于工人操作。钢管严禁使用有明显变形、裂纹、压扁和严重锈蚀的钢管,本工程所用外脚手架上的立杆、横杆颜色为桔黄色,剪刀撑颜色为蓝色,架管防锈漆应定期复涂,以保证外观形象。43.2扣件应采用GB978—67《可锻铸铁分类及技术条件》的规定,应与钢管管径相配合、机械性能不低于KT—33—8的可锻铸铁制造,扣件的附件要用的材料应符合GB700─88《碳素结构钢》中Q235钢的规定,螺纹均应符合GB196—81《普通螺纹》的规定,扣件严禁使用加工不合格,无出厂合格证,表面裂纹,变形,锈蚀的扣件,扣件活动部位应灵活转动,扣件表面应涂刷防锈漆。当扣件夹紧钢管处最小距离不小于5mm。3.3脚手板用木脚手板,长度4-6m,宽度不低于200mm,厚度不低于50mm,材质符合《木结构设计规范》(GBJ5)中Ⅱ级材质规定,不得有腐朽、贯通节疤,两端用铁丝绑紧。3.4安全网采用经国家指定监督检验部门鉴定许可生产的厂家产品,同时应具备、监督部门批量验证和工厂检验合格证。安全网的力学性能应符合GB5725—85《安全网力学性能试验方法》的规定,立网采用安全网─L—1.8×6m的密目安全网,平网采用P—3×6m的安全网,密目式安全网在100㎡面积上不少于2000目(即2000个洞眼)。4.脚手架的用途:用作水平运输和砖砌筑、钢筋绑扎、支模及混凝土浇筑、外墙装饰的操作防护架。5.脚手架搭设方案:本工程建筑高度为9.000米、16.200米和38.550米。根据本工程结构特点和相关施工方案,本工程施工脚手架方案为:多层及一层顶板下外脚手架采用双排落地架,29、30#楼采用外挑架。6.脚手架体系设计:1体系选择本工程外脚手架方案作如下选定:1)地下结构施工时在基础底板浇筑完后沿外墙四周搭设单立杆双排脚手架,随地下基础结构的进度进行到主体结构一层完。2)一层以上开始采用外挑架,6层一挑,搭设高度18m。外挑架立杆纵横间距、步距同双排落地式钢管脚手架。外挑架从主体结构一层开始搭设至主体结构完成。53)主体结构完成在装修阶段采用吊蓝进行外墙装饰做业。2脚手架稳定性验算1)根据此结构外架搭设的特点,本工程采用分段悬挑脚手架,在设备层顶及七层地面下埋件,各层均采用工字钢做为挑梁,采用间距1500,用双根作悬挑杆,伸出墙面1450,其上搭设扣件式钢管脚手架,内外立杆间距1050mm。其中遇到剪力墙位置时,在剪力墙的相应楼层位置予留双根孔洞,顶板预留3根φ20钢筋锚环,预留位置详见结点详图。悬挑结构承受荷载的传递途径是:脚手板→小横杆→大横杆→立杆→挑梁→楼面顶板。需要计算的项目有:立杆的稳定性;连墙杆的强度、稳定性和扣件的抗滑力;悬挑梁的强度、挠度;搭设参数说明:立杆纵距La=1.5m立杆横距Lb=1.05m步距h=1.5m木脚手板满铺3步架立杆计算截面以上架高Hi=18m施工荷载取3kN/m21.恒载标准值:GK计算GK=GK1+GK2+GK3公式(5-11)(1)GK1=Hi×gk1公式:(5-12)Hi=18m(立杆计算截面以上架高,考虑每隔六层悬挑一次,层高3米)gk1=1/(10h)[0.413(la+h)+0.377Lb+0.259)=1/(10×1.5)×[0.413(1.5+1.5)+0.377×1.05+0.259]=0.1263公式:(5-22)故GK1=18×0.1263=2.2734(kN)(2)Gk2=n1×Lagk2公式:(5-12)n1=3la=1.5m6gk2查表5-14,插入法得:gk2=0.3613故Gk2=3×1.5×0.3613=1.6259(kN)(3)Gk3=Hi×gk3公式(5-12)gk3查表5-15,得:gk3=0.0768故Gk3=18×0.0768=1.3824(kN)故Gk=2.2734+1.6259+1.3824=5.2817(kN)2.脚手架施工荷载标准值QK计算Qk=n1×La×qk公式(5-18)n1=1La=1.5mqk查表5-16,乘法得:qk=1.575(kN/m)故Qk=1×1.5×1.575=2.3625(kN)轴向力设计值N=1.2Gk+0.85×1.4×Qk=1.2×(5.2817+2.3625)=9.173KN3.风荷载标准值Wk按最不利风荷载考虑,即最高处风荷载标准值为:Wk=0.7×1×1.64×0.55=0.631Mw=0.12×0.631×1.5×1.5×1.5=0.2556kN.m4.整体稳定性计算:要求:N9.0+WMw9.0≤mcf公式:(5-35)式中:N=1.2NK+0.85*1.4niQikN1公式(5-38)=1.2×5.2817+0.85*1.4×2.3625=9.173kNA查表5-21,得:A=4.89×102mm2φ:轴心受压杆稳定系数:由长细比入查表5-22,得λ=iL0=i计算长度系数μ查表5-20,得μ=1.50i:回转半径查表5-21,得i=15.8mmλ=8.1510005.15.1=142.4057表5-22得φ=0.340W=5×103mm3故:N9.0+WMw9.0=231089.434.010173.99.0+36105102556.09.0=95.8N/mm2材料强度附加分项系数γm=1.1705fc查表5-23,得fc=205N/mm2材料强度附加分项系数γm,查表5-5,得γm=1.5607fc查表5-23,得fc=205N/mm2材料强度附加分项系数γm,查表5-5,得γm=1.5607故:mcf=5607.1205=131.35N/mm2N9.0+WMw9.0≤mcf所以此外架经稳定性计算满足要求2)连墙杆扣件抗滑验算Nl=Nw+Ns=1.4.Sw..k+Ns脚手架平面外变形产生的轴向力Ns=5KNNl=1.4×6×3×0.3798+5=9.57+5=14.57Kn考虑为双扣件受力,故Rc=8.5×2=17kN>Nl=14.57kN所以连墙杆扣件抗滑符合要求。3)验算地基承受力二层以下采用落地脚手架;最高双排架Hmax=10.5m1恒载标准值:GK计算GK=GK1+GK2+GK3公式(5-11)(1)GK1=Hi×gk1公式:(5-12)Hi=10.5m8gk1=1/(10h)[0.413(la+h)+0.377Lb+0.259)=1/(10×1.5)×[0.413(1.5+1.5)+0.377×1.05+0.259]=0.1263公式:(5-22)故GK1=10.5×0.1263=1.326(kN)(2)Gk2=n1×Lagk2公式:(5-12)n1=3la=1.5mgk2查表5-14,插入法得:gk2=0.3613故Gk2=3×1.5×0.3613=1.6259(kN)(3)Gk3=Hi×gk3公式(5-12)gk3查表5-15,得:gk3=0.0768故Gk3=10.5×0.0768=0.806(kN)故Gk=1.326+1.6259+0.806=3.2383(kN)2.脚手架施工荷载标准值QK计算Qk=n1×La×qk公式(5-18)n1=1La=1.5mqk查表5-16,插乘法得:qk=1.575(kN/m)故Qk=1×1.5×1.575=2.3625(kN)轴向力设计值N=1.2Gk+0.85×1.4×Qk=1.2×(3.2383+2.3625)=6.721KN在支座下设250mm×50mm×4000mm的木垫板立杆纵距La=1.5m,木垫板上有3根立杆验算公式:dAN≤kfkAd=n1×a×bn为立杆数量=31×0.25×4=0.333>0.25m2时取Ad=0.25m29N/Ad=6.721÷0.25=26.8814KN/m2<fk=40kN/m2fk为立杆底座承载力设计值4)挑架工字钢承载力计算aFbqFc31、恒荷载标准值Gk计算GK=GK1+GK2+GK3=18*0.10735+1.6259+18*0.0768=5.2817kN2、施工荷载Qk