崇明陈家镇南横引河(东段)河道整治工程技术标目录第一章编制说明....................................................21.1工程概况.....................................................21.2施工条件.....................................................41.3编制依据.....................................................51.4工程特点、难点分析及应对措施.................................61.5施工目标.....................................................8第二章施工总体部署................................................92.1施工区的划分.................................................92.2施工准备工作.................................................92.3工程施工安排原则............................................102.4土方平衡及处置..............................................102.5施工工艺总流程..............................................11第三章主要分部分项工程施工技术方案及控制措施.......................133.1测量控制....................................................133.2护岸(河道)工程施工........................................143.2.1河道开挖...............................................153.2.1.1河道水力冲挖........................................153.2.1.2护坡机械开挖........................................193.2.2护岸结构清基及回填.....................................203.2.3护岸施工...............................................203.2.4雨水排放口施工.........................................223.2.5防汛道路修筑...........................................253.3绿化种植....................................................26第四章施工总体平面布置及全场性临设工程...........................314.1布置原则....................................................314.2施工道路....................................................314.3临设及用水、用电............................................314.4施工总体平面布置图..........................................33第五章施工总体进度计划、单位工程施工进度计划及保证.................37崇明陈家镇南横引河(东段)河道整治工程技术标5.1工期目标....................................................375.2主要单位工程施工进度计划....................................375.3施工总进度计划..............................................375.4施工进度计划保证措施........................................39第六章劳动力、材料、机械等资源需要量计划及控制...................406.1劳动力需求计划及控制........................................406.2材料需求计划及控制..........................................406.3机械需求计划及控制..........................................41第七章质量目标、计划及保证措施....................................437.1质量目标....................................................437.2质量保证体系................................................437.3质量管理组织措施............................................477.4各分部分项工程质量保证措施..................................487.5雨季施工保证措施............................................547.6冬季施工措施................................................55第八章防台度汛措施.................................................568.1工程建筑物防台度汛措施......................................568.2设备及人员的防台(含大风)方案..............................568.3防台度汛保障措施............................................568.4防台度汛的具体措施..........................................578.5突发强对流天气应急措施预案..................................578.6台风袭击的防范措施..........................................57第九章安全生产计划及管理目标.....................................589.1安全生产目标................................................589.2安全生产组织与管理网络图....................................589.3安全生产管理措施............................................589.4安全生产保证措施............................................609.5安全危险源的辨识及对应措施..................................649.5.1重大危险源分析及对应措施..................................649.5.2一般危险源分析及对应措施..................................64崇明陈家镇南横引河(东段)河道整治工程技术标9.6管线保护措施................................................66第十章文明施工、环境保护计划及管理目标...........................6810.1文明施工目标...............................................6810.2文明施工、环境保护管理网络图..............................6810.3文明施工、环境保护管理.....................................6810.4文明施工、环境保护保证措施.................................71第十一章项目管理体系及项目经理、技术负责人资历......错误!未定义书签。11.1施工组织管理体系............................错误!未定义书签。11.2拟投入本合同工作主要人员资历................错误!未定义书签。崇明陈家镇南横引河(东段)河道整治工程技术标1崇明陈家镇南横引河(东段)河道整治工程技术标2第一章编制说明1.1工程概况崇明陈家镇南横引河(东段)河道整治工程位于上海市崇明县陈家镇,工程东起东滩启动区界限以西1.0km,西至郊野公园东界。本工程为在原鱼蟹塘基础上新开挖河道,修筑护坡,并在坡面及坡顶设置防汛通道及绿化。主要建设内容为:新开挖河道836m;新建护岸1661.86m;新建防汛通道2360.9m2;种植绿化1.2336万m2;新建道路雨水排水口1座。1、河道结构新建河道为在原鱼蟹塘基础上开挖新河道,河道总长836m,桩号为C2+513.8~C3+349.8,河口宽78m,河底宽度40m,河底标高为-0.5m,两侧1:4放坡,放坡段横向长度8.8m,之后设置3.3m宽平台,平台标高1.7m,然后1:3放坡,放坡段横向长度6.9m,之后北岸设置3m宽绿化和3m宽防汛通道,南岸设置6m宽绿化。2、护岸结构新建护岸总长1671.9m,其中北岸桩号为N2+520~N3+375.4,南岸桩号为S2+521.3~S3+337.8。护岸结构为:在1.7m平台内侧设置0.4*0.5mC20素砼镇脚,镇脚临水侧采用15%水泥土回填,在6.9m护坡上设置0.15m厚MU15混凝土连锁砌块,连锁砌块结构自下而上依次为:100mm厚粗砂垫层、100mm厚碎石垫层、150mm厚MU15混凝土连锁砌块,连锁块空隙2.5m高程以上采用种植土填充,2.5m以下采用碎石填充。坡顶设置0.3*0.4mC20素砼格梗。格梗及镇脚每9.9m为一个标准段,采用20mm厚聚乙烯低发泡泡沫板分缝,外周采用单组份聚氨酯密封膏嵌缝20mm。3、雨水排放口结构雨水排放口设置在河道南岸,桩号为S2+553,排放口为新埋设D1000承插式钢崇明陈家镇南横引河(东段)河道整治工程技术标3筋砼管,管口为浇筑砼底板、导流墙以及浆砌石坡面。承插管管道外径1.2m,内径1.0m,管底外口标高1.44m,向河道方向设置1%的坡度,管底基础自下而上依次为素土夯实、100mm厚砾石砂垫层、150mm厚C20素砼基础。管道口设置0.4m厚钢筋砼底板,两侧设置0.3m厚C30钢筋砼导流墙,底板与河道底部之间设置0.3m厚浆砌块石。底板与墙身之间采用20mm厚聚乙烯低发泡泡沫板分缝,内侧设置止水带,外周采用单组份聚氨酯密封膏嵌缝20mm。4、防汛通道防汛通道设置在河道北岸,总长855.4m,桩号为N2+520~N3+375.4。防汛通道宽度3m,设置1.5%倾向河道的横坡,结构自下而上为:素土夯实、100mm厚级配碎石、150mm厚道渣垫层、180mm厚C30砼路面。两侧设置C30素砼路缘石。防汛通道每隔150m设置胀缝。5、绿化北岸设置3m宽绿化,南岸设置6m宽绿化,北岸绿化主要包