新建铁路川藏线拉萨至林芝段站前工程LLZQ-8标铁路基坑围护桩施工变形监测专项监控量测方案四川交大工程检测咨询有限公司二O一六年四月1新建铁路川藏线拉萨至林芝段站前工程LLZQ-8标铁路基坑围护桩施工变形监测专项监控量测方案编制:复核:审核:四川交大工程检测咨询有限公司二O一六年四月2目录一、工程概况..........................................................................................................................11.1朗镇3号桥概况.......................................................................................................11.2朗镇2号桥概况........................................................................................................51.3朗镇4号桥概况........................................................................................................61.4朗镇1号桥概况........................................................................................................8二、编制依据..........................................................................................................................8三、监测目的..........................................................................................................................8四、监测项目..........................................................................................................................9五、监测项目实施................................................................................................................105.1围护结构顶水平位移、竖向位移监测..................................................................105.2围护桩倾斜..............................................................................................................125.3钢支撑轴力.............................................................................................................165.4地表沉降监测..........................................................................................................18六、总体测试安排................................................................................................................19七、监测技术成果................................................................................................................217.1监测数据处理与分析..............................................................................................217.2常规报告..................................................................................................................23八、组织机构、人员及设备配置........................................................................................248.1组织机构..................................................................................................................248.2人员安排..................................................................................................................248.3仪器设备..................................................................................................................25九、质量保证体系及措施..................................................................................................259.1质量方针..................................................................................................................259.2质量目标.................................................................................................................259.3质量管理体系..........................................................................................................269.4质量措施..................................................................................................................271一、工程概况新建川藏铁路拉萨至林芝段(简称“拉林铁路”)位于西藏自治区东南部,线路从既有拉日铁路协荣站引出,向南穿过冈底斯山余脉进入雅鲁藏布江河谷,于贡嘎跨过雅鲁藏布江后向东经扎囊、乃东、桑日、加查、朗县、米林至林芝。新建铁路川藏线拉萨至林芝段站前工程LLZQ-8标段起点位于山南地区加查县冷达乡,经陇南乡、仲达镇、沿S306省道前行,于林芝地区朗镇终止。线路穿越雅鲁藏布峡谷地带,四跨雅鲁藏布江,起讫里程为D3K230+703~DK263+844.62,正线长度32.23km;其中隧道7座16.613km,占正线长度51.5%;桥梁11座9642.35延长米,占正线长度29.9%;路基12段4.719km,占正线长度14.6%;涵洞337.5横延米/21座,其中盖板涵98.4横延米/3座,框架涵239.1横延米/18座;车站2座(热当车站、冲康车站)。朗镇1、2、3、4号雅鲁藏布江特大桥受地形、河道及既有道路控制设计,桥位地区地震动峰值0.15g,区内不良地质为地震、沙土液化、滑坡、冻害,无特殊岩土,桥区内水质对混凝土结构无侵蚀性。根据桥位布置及现场实际地形,朗镇1、2、3、4号桥共存在8个桥墩水中基坑开挖,水中墩基础采用筑岛围堰施工,基坑开挖上层1m范围采用1:1放坡开挖,下层16.5m范围采用钢筋砼围护桩与高压旋喷桩止水帷幕支护方案。钢筋混凝土围护桩直径为1.25m,桩间距为1.5m;高压旋喷桩直径为0.8m,咬合20cm;围护桩上部设置钢筋混凝土冠梁,冠梁尺寸为宽1.4m×高1.0m。基坑上层放坡坡顶临江侧平台宽6m,可作为小型机械临时施工作业平台。1.1朗镇3号桥概况朗镇3号雅鲁藏布江特大桥:本桥受地形、河道及既有道路控制设计,桥位地区地震动峰值0.15g,区内不良地质为地震、沙土液化、滑坡、冻害,无特殊岩土,桥区内水质对混凝土结构无侵蚀性。桥址处江面宽约150米,水流较急,卵石、漂石河床,测时最大水深约7米。桥下小里程端D2K257+371处,跨越新S306省道。桥址处地形平缓,阶地发育。桥区附近有公路相通,交通便利。本桥位于直线、缓和曲线上,采用(44+80+44)m的连续梁跨越雅鲁藏布江主河道,两端辅以24m、32m简支梁,曲线上的简支梁按平分中矢布置。全桥孔跨布置为:2×32+1×24+1×32+(44+80+44)m连续梁+7×32m,中心里程D2K257+493,桥梁全2长532.6m。其中5号墩、6号墩位于雅鲁藏布江江中,其余基础均位于江岸上,目前该位置实测水位标高3092.66,设计洪水位标高为3100.56m(1/300,规划河道)。图1.1-1朗镇3号雅鲁藏布江特大桥平面布置图5、6号水中墩桩基基础均采用12根直径1.8m的C35钻孔灌注桩作为承台承重桩,桩长分别为32m、43m,桩底标高分别为3046.53m、3036.11m,按3×4布置。纵桥向桩基间距为5.1m,横桥向桩基间距为4.9m。水中墩基础承台(二级承台)设计尺寸为17.6m长×13.1m宽×3.6m高+12.1m长×10.1m宽×1.5m高,承台主要位于砂层和卵石层中。承台顶标高分别为3083.63m、3084.21m,承台底标高分别为3078.53m、3079.11m。参见图1.1-2、1.1-3所示。图1.1-26号墩基础示意图(单位:m)3图1.1-35号墩基础示意图(单位:m)水中墩基础采用筑岛围堰法施工,当前位置雅鲁藏布江水位为3092.66m,根据雅鲁藏布江历年水位情况,水中墩基础施工期间雅鲁藏布江水位在3092.66以下,筑岛标高定位3094.66。施工期间派专人对雅鲁藏布江水位标高进行测量记录,如遇水位骤升的突发情况,组织在承台基坑外6m施工平台填筑粘土并分层压实以应对突发情况。筑岛范围为承台边线向外延伸9.4m(1m施工范围+1.4m冠梁宽度+1m放坡宽度+6m机械通行宽度),最大填筑高度9.84m。筑岛顶面北面侧填筑宽度为江岸线延江心方向47m,南面侧填筑宽度为江岸线延江心方向19.5m,西面侧填筑宽度为44.5m。筑岛迎水面边坡采用彩条布+钢筋石笼防止冲刷掏空,厚度为1m,筑岛边坡按照1:2进行放坡。对应顶面尺寸坡脚尺寸为北面侧71.6m,南面侧29.3m,西面