第1页共32页目录一、编制依据及执行标准·················································2二、工程节能设计概况····················································2三、施工部署································································33.1工程施工目标···············································································33.2施工组织管理架构及管理职能··························································4四、施工准备工作··························································44.1技术准备·····················································································44.2材料准备·····················································································54.3施工机具准备···············································································54.4劳动力准备··················································································6五、主要施工方法及技术措施···········································65.1挤塑聚苯乙烯泡沫板外保温墙面·······················································65.2环保型聚氨酯防水涂膜··································································155.3节能门窗工程··············································································19六、成品保护措施························································22七、质量通病防治措施··················································237.1节能墙体工程质量问题及防治措施···················································237.2节能屋面工程质量问题及防治措施···················································237.3节能门窗工程质量问题及防治措施···················································24八、质量标准、施工质量要求和分项验收·························268.1质量保证措施··············································································268.2质量标准及验收···········································································27九、安全文明施工保证措施············································319.1安全措施····················································································319.2文明施工措施··············································································31十、环保及职业健康管理措施·········································3210.1环境保护措施·············································································3210.2职业健康安全管理措施·································································32十一、季节性施工措施··················································32第2页共32页一、编制依据及执行标准1、《建筑节能工程施工质量验收规范》GB50411-2007;2、《夏热冬暖地区居住区建筑节能设计标准》广东省实施细则DBJ15-50-20063、《公共建筑节能设计标准》广东省实施细则DBJ15-51-20074、《建筑工程施工质量统一验收标准》GB50300-2001;5、《外墙外保温工程技术规程》JGJ144-2004;6、《外墙饰面砖工程施工及验收规程》JGJ126-20007、《屋面工程技术规范》GB50345-20048、《屋面工程质量验收规范》GB50207-20029、《铝合金门窗工程设计、施工及验收规范》(广东省标准)DBJ15-30-200210、《塑料门窗安装及验收规程》JGJ103-9611、《玻璃幕墙工程技术规范》JGJ102-200312、东莞**广场工程施工图纸及有关政府部门颁发的文件;13、现行国家有关施工规范及标准等;14、企业标准。二、工程节能设计概况1、屋面工程:(1)基层刷素水泥浆一道,泥聚苯发泡颗粒(250kg/m3)现浇找坡,随捣随抹(最薄处40厚);(2)20厚1:3水泥砂浆找平;(3)2厚环保型聚氨脂防水涂膜;50厚聚苯乙烯泡沫隔热层;(4)满铺聚苯乙烯无纺布一层(300KA/M2);(5)40厚C20补偿收缩砼(内配Φ4冷拔钢筋,双向100),隔缝间距3~5米,防水油膏填缝;(6)3~5厚B型聚合物水泥砂浆粘结层;8~10厚地砖铺平拍实;A型聚合物勾缝分隔缝间距6~9米。2、外墙装修:(1)涂料墙面:墙面基层,8厚纤维水泥浆;防保型防水、透气、耐候外墙涂料。第3页共32页(2)外墙面砖:12厚纤维水泥浆找平扫毛;8厚B型聚合物水泥砂浆;3厚A型聚合物砂浆粘贴、勾缝。(3)外墙石板干挂:在墙面(或钢骨架制安)基层刷处理剂;1:2.5水泥砂浆补实,B型聚合物水泥砂浆填实勾平螺丝孔;10厚B型聚合物水泥砂浆找平或2厚聚合物水泥基防不涂膜;植筋(或不锈钢螺栓)固定不锈钢挂件;干挂25厚石板,透空缝封胶。3、地下室防水工程:(1)侧板防水:①20厚1:2水泥砂浆找平层;②2.5厚环保型聚氨脂涂膜或2.5厚合成高分子防水卷材;③M5水泥砂浆砖砌120厚保护墙;④3:7灰土分层回填夯实。(2)底板防水:①40厚细石砼保护层(地梁处抹8厚聚合物水泥砂浆);②铺0.5厚塑料膜保护层;③2.5厚防保聚氨脂防水涂膜;④20厚1:2水泥砂浆找平层;⑤100厚C15素砼垫层。(3)顶板防水:①20厚1:2水泥砂浆找平层;②3厚高聚物改性沥青防水卷材;③40厚细石砼保护层。4、门窗做法:本工程门窗为铝合金窗、塑钢门窗等。三、施工部署3.1工程施工目标充分发挥公司优势和结合多年的施工经验,严格按照设计要求和施工规范组织施工,认真履行合同,我司将配备强有力的管理和技术力量,投入相应的施工机械设备,科学组织、严格管理、精心施工,真诚与业主合作,优质高速完成本工程的施工任务。3.1.1质量目标1、施工质量总目标本工程施工质量总目标为确保优良工程,争创省、市样板工程。2、单项工程施工质量目标根据本工程施工质量总目标,确定每个分部工程施工质量目标为优良。3.1.2安全目标本工程安全目标为杜绝重大安全事故的发生,控制工伤、轻伤频率在1‰内。第4页共32页3.1.3工期目标本工程的施工合同工期为530天,我公司计划施工总工期为510日历天。在工期计划中主要控制好以下几个阶段的进度:开工后90天:完成地下室;(90天)开工后150天:完成裙楼;(60天)开工后225天:完成至十四层;(75天)开工后270天:主体封顶。(45天)本工程的开工时间从施工现场符合开工条件,在接到建设(监理)单位的开工令后起计。于2007年1月上旬开工,2008年5月底竣工。具体的施工总进度计划安排见控制性总体进度计划。3.1.4文明施工目标严格遵照有关建筑工程的文明施工规定组织施工,确保达到文明施工工地的标准。3.1.5节能目标严格执行《建筑节能工程施工质量验收规范》(GB50411-2007)的规定,确保本工程达到设计及规范要求的节能标准。3.2施工组织管理架构及管理职能为了贯彻国家建筑节能的政策,加强建筑节能工程的施工管理。我项目经理部成立了以项目经理为组长;项目生产副经理、项目技术负责人为副组长的建筑节能工程施工领导小组,其机构组成、人员编制及责任分工如下:组长:***(项目经理)——负责组织协调工作副组长:***(生产副经理)——负责现场施工指挥、质量监督工作***(项目技术负责人)——技术总部署、方案编制及交底组员:***——现场施工管理、协调***——现场施工质量及细部施工做法管理四、施工准备工作4.1技术准备1、会审图纸,掌握施工图中的细部构造及有关技术要求。第5页共32页2、做好工程技术人员的培训,熟悉施工技术规程。3、编制施工方案。针对工程特点及材料特性,编制具体的施工方案,并经监理(建设)单位批准。4、技术交底。对施工操作人员进行技术、安全交底,使其掌握施工的关键技术及对相关工序的配合。4.2材料准备1、根据施工组织设计中的施工进度计划和施工预算中的工料分析,编制工程所需的材料用量计划,作好备料、供料工作和确定仓库、堆场面积及组织运输的依据。2、原材料的进场检验:原材料进场由现场质量员按照公司制定的原材料进场验收标准进行原材料进场验收,同时填写材料进场验收记录。3、原材料的技术性能,表观密度、导热系数、抗压强度、尺寸变化率、吸水率应符合设计要求。4、建筑节能工程进场材料和设备的复验项目应符合下表的规定,复验项目中应有30%为见证取样送检。建筑节能工程进场材料和设备的复验项目序号子分部工程复验项目1墙体1、保温板材的导热系数、材料密度、压缩强度、阻燃性;2、保温浆料的导热系数、压缩强度、软化系数和凝结时间;3、粘结材料和抹面砂浆的粘结强度;4、增强网的力学性能、抗腐蚀性能;5、其他保温材料的热工性能;6、必要时,可增加其他复验项目或在合同中约定复验项目2门窗1、严寒、寒冷地区应对气密性、传热系数和露点进行复验;2、夏热冬冷地区应对气密性、传热系数进行复验;3、夏热冬暖地区应对气密性、传热系数、玻璃透过率、可见光投射比进行复验。3屋面1、板材、块材及现浇等保温材料的导热系数、密度、压缩(10%)强度、阻燃性2、松散保温材料的导热系数、干密度和阻燃性4地面1、板材、块材及现浇等保温材料的导热系数、密度、压缩(10%)强度、阻燃性2、松散保温材料的导热系数、干密度和阻燃性4.3施工机具准备根据施工组织设计中确定的施工机具、设备的要求及施工进度的安排,编制施工机具设备需用量计划,落实施工机具设备需用量计划,确保按期进场,准时开工。具体施工机具配置情况见下表施工机具配置情况一览表第6页共