32常见方案技术条件电压(kV)方案线路长度(km)地形(%)气象区(个)导线型号(种)地线型号(种)新设计杆塔(个)选用杆塔(个)基础(个)受影响通讯线(条)环保水保一般地形困难地形直线塔非直线塔直线塔非直线塔设计选用Ⅰ、Ⅱ级Ⅲ级330Ⅰ120703021211542001020环保水保Ⅱ12030703122265300102043常见方案设计工日定额汇总表电压(kV)方案设计阶段电气土建通信保护概算系统施工组织环保水保备用小计总计(工日)工日%工日%工日%工日%工日%工日%工日%工日%工日%330Ⅰ初设47040.727323.714512.61028.9353.0373.2282.4605.511501002890施工图86349.667738.91377.9633.61740100合计133346.195032.82829.81023.6351.2371.3281.01234.22890100Ⅱ初设58340.138726.614510.01288.8352.4372.5281.91127.714551003780施工图92839.9110047.31375.91606.72325100合计151140.0148739.32827.51283.4351.0371.0280.82727.03780100