地铁7号线02标2011年冬期施工方案

整理文档很辛苦,赏杯茶钱您下走!

免费阅读已结束,点击下载阅读编辑剩下 ...

阅读已结束,您可以下载文档离线阅读编辑

资源描述

北京地铁十四号线工程第00标段冬期施工方案编制:审核:审批:中铁三局集团有限公司北京地铁十四号线工程第00标段项目经理部2011年10月20日1目录一、编制依据·································································································2二、工程概况·································································································2三、施工部署·································································································3四、施工准备·································································································51、现场准备·······························································································52、人员准备·······························································································53、物资准备·······························································································6五、冬期施工技术要点·····················································································71、现场原材料保护······················································································72、工序施工防寒措施···················································································93、办公生活区管理····················································································194、机械设备管理·······················································································205、其他防寒措施·······················································································20六、质量保证措施·························································································21七、安全保证措施·························································································22八、绿色施工管理措施···················································································23九、冬季施工管理·························································································24附件:混凝土蓄热养护热工计算·······································································262冬期施工方案一、编制依据1、《建筑工程冬期施工规程》(JGJ104-97)2、《混凝土结构工程施工质量验收规范》(GB50204-2002)2011年版3、《地下铁道工程施工及验收规范》(GB50299-1999)2003年版4、《轨道交通车站工程施工质量验收标准(修订版)》(QGD-006-2008)5、《钢筋机械连接通用技术规程》(JGJ107-2010)6、《钢筋焊接及验收规范》(JGJ18-2003)7、《地下工程防水技术规范》(GB50108-2008)8、《地下防水工程质量验收规范》(GB50208-2002)9、《锚杆喷射混凝土支护技术规范》(GB50086-2001)10、《施工现场临时用电安全技术规程》(JGJ46-2005)11、《建筑机械使用安全技术规程》(JGJ33-2001)12、《建筑工程施工手册(第四版)》13、北京地铁7号线工程土建施工02合同段施工图纸14、北京地铁7号线工程土建施工02合同段施工组织设计二、工程概况本标段合同范围包括北京地铁7号线工程的菜市口站、广安门内站、广安门内站~菜市口站区间、达官营站~广安门内站区间,标段总长2828.715m。菜市口站位于宣武门外大街与菜市口大街交叉的十字路口,车站沿菜市口大街东西方向布置,与既有4号线节点换乘;广安门内站位于广安门内大街和白广路交叉路口,沿广安门内大街跨路口设置;广安门内站~菜市口站区间、达官营站~广安门内站区间都为沿两广路下方东西方向走势,菜市口站主体采用明挖法施工,广安门内站采用暗挖法(PBA)施工,区间采用盾构施工。3菜市口站为北京地铁七号线与四号线的中间换乘站,车站主体位于广安门内大街与菜市口大街、宣武门外大街的交叉路口处,呈东西走向。车站为三跨双层矩形框架结构,明挖法施工,车站总长255米(既有段长度21.90米),起、终点里程为右K5+191.685~右K5+446.685。有效站台中心里程为右K5+353.085,轨面埋深14.6米,顶板埋深2.69米,标准段宽度20.9米,盾构井段宽度22.65米,站台宽12m,车站总建筑面积为15190㎡。车站西端右线设盾构始发井,左线采用矿山法从车站挖至区间盾构井,东端区间为矿山法区间。车站设风道两处,施工方法为明暗结合;设置4个出入口,出入口地面出口部分均采用明挖法施工,通道采用暗挖法施工;本站是与既有四号线换成站,设置两个联络通道均采用暗挖法施工与既有四号线联通;另设置紧急疏散口一个。车站东端左右线均增设30米长、5米宽的轨排井。广安门内站为北京地铁7号线一个中间站,车站主体位于广安门内大街和白广路交叉路口,沿广安门内大街跨路口设置。车站为单柱双层双跨岛式站台结构,采用暗挖法(PBA法施工)施工。车站全长249.2m,标准段净宽20.9m,站台宽12m;车站覆土为10.2米,底板埋深为26.8米。车站两端区间为盾构区间。车站共设置1、2、3A、3B共4个出入口及2组风道4个风亭,2个紧急疏散通道。1、2号出入口位于车站北侧;3A、3B号出入口位于车站南侧;4个风亭分别设置于规划宣武区图书馆及报国寺前绿地内。附属通道采用暗挖法、出口段采用明挖法施工。车站周边有规划宣武区图书馆,报国寺,菜百商厦,水利水电物资总公司,普明大厦,京粮大厦等建筑物。三、施工部署1、冬期施工时间根据《建筑工程冬期施工规程》(JGJ104-97)的规定,当室外日平均气温连续5天低于5℃,即进入冬期施工;当室外日平均气温连续5天高于5℃时,解除冬期施工。根据北京地区气温资料统计显示,每年11月15日至第二年3月15日为工程建设冬期施工期,4在这一期间北京地区地面以上日平均气温低于5℃。本方案适用于北京地铁7号线工程土建施工02合同段2011年11、12至2012年1、2、3月份期间各工序的施工。2、施工计划根据总体施工进度计划安排,2011年至2012年冬期施工期间,本标段主要的分部分项工程有:临建施工、钻孔灌注桩、钢支撑腰梁、基坑土方开挖、明挖主体结构、降水施工、暗挖工程开挖,暗挖主体结构施工。3、冬期施工组织机构成立以项目经理为组长、项目副经理及总工程师为副组长,各部门负责人、各工区长为组员的冬期施工领导小组,负责本标段冬期施工各方面工作的组织协调。冬期施工领导组织机构框图如下:冬期施工领导组织机构框图组长:海胜副组长:卜宪龙李晓权邢学峰工程部安质部物质部机电部预算部试验室财务部广安门内站工区菜市口站工区5冬期施工领导小组职责:1)组长:负责总体组织、协调项目部及工区冬期施工各方面工作。2)副组长:制定项目部冬期施工工作计划并编制项目冬施方案,建立并健全冬施期间的管理制度,做好冬施部署,现场冬施管理、技术管理等工作。3)各组员:负责实施各部门与冬期施工有关的具体工作:(1)冬期施工到来之前,技术负责人应对各工区管理人员进行方案交底,工区长、工区技术室根据冬期施工方案对施工人员进行书面技术交底。各部门管理人员根据自己的职责,安排、落实冬期施工之前的各项准备工作。(2)物资部应根据冬期施工材料计划提前做好准备,确保冬期施工所需要的材料设备按时按计划进场;工区做好冬施技术人员安排,并同工程部、安质部门对特殊工种如测温工等进行安全质量培训、考核;工程部及工区技术室负责作好现场冬期施工的技术准备工作。(3)各部门及各工区了解近期天气变化,及时接收天气预报防止寒流突然袭击。四、施工准备1、现场准备1)机电部和工区电工、机修工对各种机械设备、用电设备、线路进行检查、维修、保养,保证冬施正常进行。2)根据施工计划提前组织有关机具、外加剂和保温材料按计划进场。3)工地的临时供水管道及施工用料做好保温防冻工作。2、人员准备在进入冬期施工前对项目部参施人员进行冬施培训,对项目部各级管理人员组织技术业务培训,学习工作范围内的相关知识,明确职责。组织各施工队的技术、质量、试验等人员以讲课的形式进行冬期施工专题培训,使他6们熟悉掌握冬期施工规程。工区设专职测温员至少2名,严格执行测温制度,测温员对每次测温要认真做好记录并及时上报技术主管,技术主管对测温结果要及时进行分析,根据分析结果做出判断,以指导施工。3、物资准备物资部应按现场需要以及工程部和各工区提供的材料计划落实材料进场,确保材料、物资提前进场,保证冬期施工期间所需要的保温材料提前准备到位。1)提前安排苫布、阻燃性草帘子、塑料薄膜、玻璃棉、玻璃丝布等保温材料进场。2)由指定的具备专业资质的试验室负责冬期施工混凝土、砂浆及掺外加剂的试配、试验工作,提前做好施工配合比。3)冬期施工期间施工用的各种电暖气等应急加热设备提前进场。4)冬期施工准备阶段的材料必须保质保量。冬期施工物资、设备计划表序号项目数量备注1玻璃棉1000m2管路的覆盖2棚布1000m2用于材料覆盖3防冻液压油地面设备用4温度计30支测气温、混凝土温度5电子测温仪4支测混凝土温度6电暖气100台办公室、暖棚采暖7塑料薄膜10000m2结构混凝土保湿8彩条布2000m2苫盖9阻燃性草帘子2000m2苫盖710棉被1500m2苫盖11聚苯乙烯板600m2模板背贴覆盖12φ12.5钢拉丝5t暖棚支撑五、冬期施工技术要点1、现场原材料保护1)钢筋(1)在负温下,随着温度的降低,钢筋的屈服点和抗拉强度提高,伸长率和冲击韧性降低。为了保证钢筋工程的施工质量,冬期施工过程中钢筋材料采取在钢筋存放场地底部垫10cm方木,防止钢筋触及地面,保证钢筋处于干燥的环境中,并在钢筋原材上采用棚布覆盖。(2)对于成品及半成品钢筋在钢筋存放场地底部垫10cm方木,棚内采用电暖气取暖,尽量避免棚外

1 / 30
下载文档,编辑使用

©2015-2020 m.777doc.com 三七文档.

备案号:鲁ICP备2024069028号-1 客服联系 QQ:2149211541

×
保存成功