检查井砌筑技术交底-砖砌井

整理文档很辛苦,赏杯茶钱您下走!

免费阅读已结束,点击下载阅读编辑剩下 ...

阅读已结束,您可以下载文档离线阅读编辑

资源描述

relationship,establishedequivalentrelationship14,andsubject:applicationproblem(4)--scoresandpercentageapplicationproblemreviewcontentoverviewanswersscores,andpercentageapplicationproblemofkeyis:accordingtomeaning,(1)determinestandardvolume(units1)(2)findassociatevolumeratecorrespondstorelationship,Thenin-linesolution.CategoryfractionmultiplicationwordproblemscoreDivisionapplicationsengineeringproblemproblemXV,asubject:reviewofthemeasurementoftheamountofcapacity,measurementandunitsofmeasurementofcommonunitsofmeasurementandtheirsignificanceinrate1,currency,length,area,volume,unitsize,volume,weightandrate.(Omitted)2,commonlyusedtimeunitsandtheirrelationships.(Slightly)withameasurementunitsZhijianofofpoly1,andofmethod2,andpolymethod3,andofmethodandpolymethodofrelationshipmeasurementdistanceofmethod1,andtoolmeasurement2,andestimates16,andsubject:geometrypreliminaryknowledge(1)--lineandanglereviewcontentline,andsegment,andRay,andvertical,andparallel,andangleangleofclassification(slightly)17,andsubject:geometrypreliminaryknowledge(2)--planegraphicsreviewcontenttriangle,andedgesshaped,andround,andfanaxisymmetricgraphicsperimeterandareacombinationgraphicsofareasubject:Preliminaryknowledge(3)-reviewofsolidcontentcategory1-dshapesaredividedinto:cylinderandcone2,columnisdividedinto:cuboid,square3,coneconeofthefeaturesofcuboidsandcubesrelationshipbetweencharacteristicsofcircularconeisslightlysolidsurfaceareaandvolume1,size2,table...和和平与发展是当今世界发展的主题,中国作为屹立在世界东方的大国,要担负起重要的责任。从“亚太自由贸易区”到“亚投行”、“一带一路”,再到G20峰会,都体现出中国一个负责任的大国形象。1.1一般规定1.1塑料检查井安装前应做好相应的交底工作。1.2塑料检查井安装前应进行检查产品进场检验:1.2.1塑料检查井的井座、井筒、配件、井盖及密封材料进场后均应按国家和行业有关塑料检查井产品标准进行检查,检查项目主要为环刚度、环柔性和抗冲击性。1.2.2塑料检查井的内外表面应光滑平整,无气泡、变形、裂口、脱皮和明显的痕纹、凹陷,且色泽基本一致,接口完好,无破损变形。1.2.3塑料检查井的规格尺寸均应符合设计施工图的要求,并应根据塑料检查井的编号进行核实,塑料检查井产品合格证格式见附录E。1.2.4塑料检查井尺寸偏差应符合表1.2.4的规定。对外观质量不符合要求的检查井,不得使用。表1.2.4塑料检查井允许偏差(mm)井筒内径高度孔口直径垂直度偏转角+10,-15±20+10,-15≤2%±2°1.2.5塑料检查井在装卸、运输、堆放时,应轻抬轻放,不得抛摔或受剧烈撞击,严禁拖拉。塑料检查井应存放在通风良好、温度低于40摄氏度的房库内,不宜露天存放。如须露天临时存放时,应有遮盖,尽量避免爆晒和雨淋。不得与油类、酸、碱、盐等其他化学物质接触,注意防火安全,远离热源。1.3塑料检查井安装应编制详细的施工组织方案,方案应包括施工方法、主要机械设备配置、施工质量和安全措施等内容。2.1井坑2.1井坑开挖应与管沟同时开挖,开挖时井座主管道应与管沟中的管道在同一轴线上;2.2井坑开挖应根据选用的规格,考虑井座主管线偏置因素,偏置端的坑壁应与管沟齐平;2.3有沉泥室的雨水检查井井坑应根据选用的规格局部开挖沉泥室坑;2.4井坑边坡应与管沟边坡一致,施工时应根据地质条件放坡开挖或采取支护措施,确保施工安全。2.5井坑开挖时,不得扰动基土超挖,如基土受到扰动,则应按现行国家标准《给水排水管道工程施工及验收规范》GB50268的有关规定,根据基土土质采取弥补措施;2.6井坑人工开挖时,临时堆土或施加其它荷载不得影响井坑的稳定性,堆土高度及其距井坑边缘的距离按相关施工规范执行。2.7井坑底部如有砖、石等坚硬物体时应将其清除。2.8地下水位较高的地区或在雨季施工,应有排水降低水位的措施;施工时应把地下水降至井坑最低点300mm以下。检查井安装连接完毕后,必须回填至满足检查井抗浮稳定的高度后才能停止降水。2.9井坑不得受水浸泡。施工时如发生井坑被水浸泡,应先将水排除,然后清除被浸泡的土层,按设计要求换填处理,密实度应达到设计要求。relationship,establishedequivalentrelationship14,andsubject:applicationproblem(4)--scoresandpercentageapplicationproblemreviewcontentoverviewanswersscores,andpercentageapplicationproblemofkeyis:accordingtomeaning,(1)determinestandardvolume(units1)(2)findassociatevolumeratecorrespondstorelationship,Thenin-linesolution.CategoryfractionmultiplicationwordproblemscoreDivisionapplicationsengineeringproblemproblemXV,asubject:reviewofthemeasurementoftheamountofcapacity,measurementandunitsofmeasurementofcommonunitsofmeasurementandtheirsignificanceinrate1,currency,length,area,volume,unitsize,volume,weightandrate.(Omitted)2,commonlyusedtimeunitsandtheirrelationships.(Slightly)withameasurementunitsZhijianofofpoly1,andofmethod2,andpolymethod3,andofmethodandpolymethodofrelationshipmeasurementdistanceofmethod1,andtoolmeasurement2,andestimates16,andsubject:geometrypreliminaryknowledge(1)--lineandanglereviewcontentline,andsegment,andRay,andvertical,andparallel,andangleangleofclassification(slightly)17,andsubject:geometrypreliminaryknowledge(2)--planegraphicsreviewcontenttriangle,andedgesshaped,andround,andfanaxisymmetricgraphicsperimeterandareacombinationgraphicsofareasubject:Preliminaryknowledge(3)-reviewofsolidcontentcategory1-dshapesaredividedinto:cylinderandcone2,columnisdividedinto:cuboid,square3,coneconeofthefeaturesofcuboidsandcubesrelationshipbetweencharacteristicsofcircularconeisslightlysolidsurfaceareaandvolume1,size2,table...和和平与发展是当今世界发展的主题,中国作为屹立在世界东方的大国,要担负起重要的责任。从“亚太自由贸易区”到“亚投行”、“一带一路”,再到G20峰会,都体现出中国一个负责任的大国形象。2.10井坑底开挖净尺寸不应小于表2.10中的规定;表2.10井坑净尺寸井座连接井筒的接口直径(mm)井坑净尺寸(mm)315900×9005001100×11007001500×150010002000×2000注:当埋地管道直径大于井筒直径时,应按埋地管道管沟要求开挖。2.11井坑与管沟开挖后应有安全护绳(栏)等安全警示标志。3基础3.1塑料检查井必须安装在符合设计要求的地基土层上,或是在开挖井坑后经处理密实的地基上。3.2塑料检查井基础应根据当地地质勘察资料和回填土下曳力经计算确定,当无资料时,可按下列规定执行:1砂土、岩石、砂砾土土质的井坑内铺设100mm中粗砂垫层;2软土土质的井坑内铺设150mm厚碎石(砖)或砾石(粒径5mm~40mm)道渣层,夯实后上层再铺50mm中粗砂垫层;3湿陷性黄土土质的井坑内原土夯实后铺垫三七灰土100mm~150mm垫层,再按本条第1款铺设中粗砂垫层。砂砾石垫层的压实系数不宜小于0.95。4市政用检查井井座应采用不低于C15现浇混凝土基础浇捣密实。3.3塑料检查井基础位于淤泥或其它不良土层时,检查井地基应按设计及相应规范进行处理。3.4管件式检查井基础处理应按聚乙烯排水管管道工程的相关工程技术标准执行。4井座与管道连接4.1井座与管道连接安装顺序应遵循以下原则:1先从接户管上游段起始安装,逐渐向下游支管、干管延伸;2以井→管→井→管顺序安装;3应先定位井座中心,将井座与下方垫块置于井坑内,调整其管底标高,然后进行接管安装。4.2塑料检查井井座上如有流向箭头应与管道水流流向一致。4.3井座接头与管道连接施工方法应与同类型接头的管道连接的施工方法一致。4.4排出管与接户管连接4.4.1在下列情形下,排出管采用过渡井连接(见图4.4.1):relationship,establishedequivalentrelationship14,andsubject:applicationproblem(4)--scoresandpercentageapplicationproblemreviewcontentoverviewanswersscores,andperc

1 / 8
下载文档,编辑使用

©2015-2020 m.777doc.com 三七文档.

备案号:鲁ICP备2024069028号-1 客服联系 QQ:2149211541

×
保存成功