融创绿城精装修工程施工工艺样板指引-1-精装修工程施工工艺样板指引(试行版)上海融创绿城投资控股有限公司项目管理中心2015.1融创绿城精装修工程施工工艺样板指引-2-目录前言........................................................................................................................-4-一、吊顶部分............................................................................................................-5-1.0吊顶部分工艺样板前置条件及要求..........................................................-5-1.1轻钢龙骨安装要求......................................................................................-6-1.2轻钢龙骨吊顶拐角处斜拉加固..................................................................-7-1.3轻钢龙骨吊顶侧挂板转角处铁片固定加固..............................................-8-1.4叠级式吊顶叠级转角处封9mm多层板加固............................................-9-1.5叠级式吊顶叠级转角处面层石膏板封板...............................................-10-1.6叠级式天花挂板做法一...........................................................................-11-1.7叠级式天花挂板做法二...........................................................................-12-1.8叠级式天花挂板拼接做法.......................................................................-13-1.9天花封双层石膏板施工做法...................................................................-14-1.10天花高位封单层石膏板须设横撑龙骨加固.........................................-15-1.11吊灯加固.................................................................................................-16-1.12天花石膏线条安装.................................................................................-17-二、墙面部分.........................................................................................................-18-2.0墙面部分工艺样板前置条件及要求.......................................................-18-2.1砌体墙与砼墙柱交接位置加固及喷浆做法...........................................-19-2.2墙面抹灰做法...........................................................................................-20-2.3门框木基层做法.......................................................................................-21-2.4木饰面轻钢龙骨基层做法.......................................................................-22-2.5木饰面木龙骨基层做法...........................................................................-23-2.6墙面木饰面安装做法...............................................................................-24-2.7室内木门安装做法...................................................................................-25-2.8墙纸铺贴做法...........................................................................................-26-2.9软硬包做法...............................................................................................-27-2.10卫生间石材(墙砖)铺贴做法.............................................................-28-融创绿城精装修工程施工工艺样板指引-3-2.11卫生间台面石材钢架做法.....................................................................-29-2.12石材线条钢架做法.................................................................................-30-2.13石材造型钢架做法.................................................................................-31-三、地面部分.........................................................................................................-32-3.0地面样板前置条件及要求.......................................................................-32-3.1卫生间导墙浇筑.......................................................................................-33-3.2卫生间淋浴房挡水槛浇筑.......................................................................-34-3.3地面大理石铺贴.......................................................................................-35-3.4防水施工...................................................................................................-36-3.5木地板及木踢脚线安装...........................................................................-37-四、其它(由各项目公司根据项目实际情况优化完善)融创绿城精装修工程施工工艺样板指引-4-前言1.目的随着上海融绿公司精装交付项目的日益增多,各种质量投诉逐渐增长,业主对精装修住宅的产品质量要求越来越高,这也势必对精装工程质量提出更高的要求。如何合理组织施工,把控好工程施工质量的事前控制,是确保工程品质的重要措施。工程各个工序在大面积展开施工前,通过施作工艺样板对施工工艺工法优化,并依据工艺样板对施工班组进行施工交底尤为重要。平台项管中心汇总了各项目的施工工艺样板,从中摘选出有代表性的样板照片,结合《融创集团精装修工程细部节点构造标准及管理要求》的工艺工法标准,编制了本“施工工艺样板指引”。要求各精装修项目依据本指引内容,结合自身项目特点及设计风格编制工艺样板实施方案,在批量装修施工时必须先做施工工艺样板。2.适用范围上海融绿平台所有住宅、公寓及公共部位批量精装修项目,办公楼、酒店精装修项目均适用本指引。3.实施要求施工工艺样板要求施工单位进场后30-45天内完成,各工序工艺样板经确认后方可大面积展开该道工序施工。4.执行时间2015年1月1日后新开工的精装修项目开始试行。融创绿城精装修工程施工工艺样板指引-5-一、吊顶部分1.0吊顶部分工艺样板前置条件及要求1.要求每个标段施工单位设置一套专用房做施工工艺样板。2.户内所有机电安装隐蔽管线及天花上的所有设备安装必须施工完成。(包括上一层的排水管线及防水,下一层的天花吊筋打孔等)3.吊顶展示形式要求:户内所有房间龙骨全部安装完成,石膏板部分封板,石膏线部分安装,外露相关材料施工节点断面,完整展示出用材及施工节点做法,施工工艺及材料严格按工艺工法执行。轻钢龙骨安装要求:施工工艺样板套内所有吊顶区域,天花轻钢龙骨均需按工艺工法安装完成。吊顶高低叠级转角位局部封板要求:其中一处转角位封一层L角(300mm*600mm长)9mm多层板;另一处转角位多层板、石膏板封板完成,同时将高低叠级处的装饰石膏线及反光灯槽(转角长度不小于1000mm)安装完成;其余转角位及天花高位大面均保留轻钢龙骨完成面,不封板。天花开孔要求:天花低位封板部分的天花灯孔、风口及设备检修孔洞需全部开好,成品检查口需安装一个样板。4.样板标识要求:工艺样板说明标识,应采用统一格式打印,张贴在该项工艺样板施做位置的明显部位,标识说明应包括但不限于:样板名称、工艺工法主要控制点说明、材料品牌、规格尺寸及使用部位说明、施工节点大样图纸等。融创绿城精装修工程施工工艺样板指引-6-1.1轻钢龙骨安装要求1.技术要点采用50系主龙骨,壁厚为1.2mm,安装间距不大于900mm;副骨为50系列,壁厚为0.5mm,安装中心间距300mm。吊杆应采用热镀锌成品螺杆,直径不小于Φ8,吊杆长度大于1200mm的须采用60系主龙骨或30x30mm热镀锌角钢作反支撑加固处理。吊顶低位侧挂板至墙体距离大于300mm的须增设一根主龙骨。吊顶高位空间不够的位置可以采用卡式加强型主龙骨施工。2.示范照片融创绿城精装修工程施工工艺样板指引-7-1.2轻钢龙骨吊顶拐角处斜拉加固1.技术要点叠级式吊顶低位的转角部位副龙骨面采用0.8mm厚,40mm宽镀锌铁皮斜拉加固,减少吊顶转角位开裂风险。镀锌斜拉铁片应延伸至边龙骨,固定平直、牢固。2.示范照片融创绿城精装修工程施工工艺样板指引-8-1.3轻钢龙骨吊顶侧挂板转角处铁片固定加固1.技术