0000市红荔西路(香蜜湖段)市政工程监理规划0000二OOO年一月目录第一章工程概况.....................................................................................11.1工程名称........................................................................................11.2建设地点........................................................................................11.3工程范围及内容............................................................................11.4计划工期........................................................................................21.5质量等级........................................................................................21.6计划投资........................................................................................21.7主要工程量表................................................................................2第二章监理工作总目标及监理工作范围.............................................32.1监理工作总目标............................................................................32.2监理工作的依据............................................................................32.3施工准备阶段的主要监理工作....................................................42.4施工准备阶段监理工作分工和要求............................................62.5施工阶段的主要监理工作...........................................................92.6监理人员职责.............................................................................112.7竣工期的主要监理工作...........................................................162.8保修期主要监理工作...............................................................16第三章监理组织机构及人员配置.......................................................173.1组织机构框图..............................................................................173.2监理人员的配置..........................................................................18第四章自配监理仪器和设备...............................................................19第五章监理工作程序...........................................................................225.1施工准备阶段监理程序.............................................................225.2单项工程质量控制程序.............................................................235.3分项工程监理程序.....................................................................245.4隐蔽工程、分部分项工程签认程序.........................................265.5成品、半成品构配件及设备质量签认程序.............................275.6原材料监理程序.........................................................................285.7工序(工艺)质量控制程序举例(C15混凝土).................295.8工程质量事故处理程序.............................................................305.9工程停、复工程序.....................................................................315.10工程进度控制程序...................................................................325.11中期支付程序...........................................................................335.12工程计量程序...........................................................................345.13工程变更程序...........................................................................355.14工程延期确定...........................................................................365.15索赔处理程序...........................................................................37第六章监理质量保证措施...................................................................386.1合理组织监理机构,配置监理人员.........................................386.2建立完善的监理措施.................................................................396.3建立完善的监理制度..................................................................47—1—第一章工程概况0000市红荔西路香蜜湖段是一条东西走向的城市次干道,位于深南路以北,莲花路以南,该路西起农科中心段0+740,向东跨过香蜜湖路,穿越香蜜湖渡假村,东至香梅路2+363.32,全长1623米。该工程由0000市市政工程设计院设计,我院受0000市土地投资开发中心委托实行全面建设监理工作,本着“严格监理、热情服务、秉公办事、一丝不苟”的监理原则,为认真贯彻执行有关施工和监理的各项方针、政策、法律、法规,明确岗位责任,严格检查制度,制定本监理规划。1.1工程名称0000市红荔西路(香蜜湖段)市政工程1.2建设地点0000市福田区红荔西路1.3工程范围及内容本工程西起0+740,东至2+363.32,全长1623米,包括道路工程、桥梁工程及市政管线工程,道路工程路幅宽100米,为双向六车道。桥梁工程全长195米,为预应力砼变截面连续梁,桥面全宽28.4米,沿道路中心线分为对称的南北两座桥,共有钻孔灌注桩96根,市政管线工程包括给排水、电力、电讯、照明及燃气工程。—2—1.4计划工期本工程计划开工日期为2000年1月25日,计划竣工日期2001年1月25日,总工期为365日历天。1.5质量等级本工程按国家现行有关施工技术规范、规程进行验收,要求达到优良标准。1.6计划投资本工程预计投资为人民币1.2亿元。1.7主要工程量表单位工程主要分项工程单位工程量备注桥梁工程桩φ1.0根32桩尖嵌入微风化岩层深度不小于一倍桩径φ1.2根32φ1.4根32承台个20C25砼桥台个4重力式桥台C25砼墩柱φ1.5个8双柱圆墩C30砼φ1.8个8梁m34273预应力砼变截面箱梁C50砼道路工程土石方m3194500香蜜路以西为刚性砼路面香蜜路以东为柔性沥青路面水泥石粉渣稳定层m322150水泥砼面层m27500沥青砼面层m238650市政管线工程给水管线m3975铸铁管和钢管,管径DN200~DN400雨水管线m3150钢筋砼管,管径DN200~DN800污水管线m2397钢筋砼管,管径DN300~DN500电力管线m16101.0×1.0和1.2×1.2m隐蔽式电缆沟电讯管线m2650白色增强双壁波纹管燃气管线m2690无缝钢管,管径DN108~DN219—3—第二章监理工作总目标及监理工作范围2.1监理工作总目标本着“严格监理、热情服务、秉公办事、一丝不苟”的监理宗旨,使本工程的监理达到以下总目标:工程质量、工期和投资满足施工合同要求。同时,加强工程建设,强化管理,使本工程建设达到质量优、进度快、投资省、效益高的目的。具体目标如下:1.质量总目标:质量控制是整个监理工作的核心内容,要在工程预定的投资范围内及预期的工期内,实现最佳的质量效果。监理质量目标为:工程质量等级为优良,并创0000市优质样板工程。2.进度总目标:实现业主对工期的要求,按进度总目标控制。3.投资总目标:按施工合同之承包合同的总价作为投资控制目标,严格现场计量及技术经济签证制度。2.2监理工作的依据1.政府为业主建设项目所下达的文件。2.业主与承包商、承包商与分包商签订的正式合同或协议以及监理合同规定的条款。3.正式的工程项目施工图纸及说明。4.国家和地方建设主管部门现行建筑工程技术规范、规程和工程质量评定标准及施工验收规范。5.当地建设主管部门的现行预算定额取费标准及有关建设管理办—4—法。6.国家有关工程建设管理的方针、政策、法规、规范和工程建设的文件以及当地的实施细则。2.3施工准备阶段的主要监理工作1.监理中标后,迅速建立监理机构,由项目总监组织配备各专业监理工程师、监理人员、试验人员、测量工程师等,实行项目总监理工程师全面负责制。2.成立工地监理办公室,配备必要的监理设备、试验设备和测量仪器,配备的仪器设备详见附件之仪器设备表。3.全面熟悉合同文件及有关标准和测试方法,对合同文件中存在的差错、遗漏、含糊不清的问题加以查证,并提出解决办法。4.协助业主做好施工招标的各项工作:(1)帮助业主编制招标文件,特别是根