XXXXXXXXXXXXXXXXX综合仓库高支模专项施工方案编制:职务:审核:职务:批准:职务:XXXXXXXXXXXXX公司编制日期:2019年6月30日XXXXXXXXXXXXXXXXXXXXXXX项目I目录一、工程概况...........................................11.1总体简介..................................................11.2设计概况..................................................11.3危大工程概况和特点........................................71.4施工要求和技术保证条件....................................71.5技术保证条件..............................................81.6支架选型..................................................8二、编制依据...........................................92.1相关法律、法规............................................92.2规范性文件、标准、规范...................................102.3施工图设计文件、施工组织设计.............................102.4编制范围.................................................11三、施工计划..........................................113.1材料计划.................................................113.2设备计划.................................................123.3工期安排.................................................12四、施工工艺技术......................................124.1技术参数.................................................124.2模板支撑架体搭拆施工工艺.................................214.3技术要求.................................................24XXXXXXXXXXXXXXXXXXXXXXX项目II4.4本工程不同部位施工方法...................................254.5模板支撑架的拆除.........................................264.6检查要求.................................................27五、混凝土浇筑与养护措施..............................305.1混凝土浇筑一般规定.......................................305.2混凝土振捣...............................................305.3混凝土养护...............................................315.4现场制作足够数量的混凝土试块,在常温下的混凝土取样:.....315.5混凝土一般缺陷处理方法...................................315.6质量要求.................................................32六、施工安全保证措施..................................326.1安全管理组织机构图及岗位职责.............................326.2安全管理保证体系.........................................326.3组织保障措施.............................................336.4模板支撑体系搭设与拆除技术措施...........................346.5监测措施.................................................36七、施工管理及作业人员配备和分工......................397.1、施工管理人员............................................397.2、专职安全生产管理人员....................................417.3、特种作业人员............................................417.4、其他作业人员............................................41XXXXXXXXXXXXXXXXXXXXXXX项目III八、验收要求..........................................428.1验收标准.................................................428.2验收程序.................................................448.3验收内容.................................................448.4验收人员.................................................47九、应急处理措施......................................479.1编制目的.................................................479.2适用范围.................................................489.3预防措施与现场处置措施措施...............................489.4应急预案.................................................51十、计算书及图纸......................................5410.7500MM×1000MM梁模板(盘扣式,设置搁置横梁)计算书......14510.8120MM板模板(盘扣式)计算书............................16010.9梁侧模板计算书.........................................1729.10柱模板(设置对拉螺栓)计算书...........................179十一、现场平面布置图(略)...........................189XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目1一、工程概况1.1总体简介序号项目内容1工程名称XXXXXXXXXXXXXXX仓库2工程地址XXXXXXXXXXXXXXXXXXXXXXX3工期2019年X月X日至2019年X月X日,共XXX日历天4安全目标(1)杜绝一般及以上生产安全事故,轻伤年平均月频率控制在3‰以下。。(2)杜绝一般及以上道路交通责任事故。(3)杜绝一般及以上火灾、机械设备责任事故。(4)争创市级及以上安全文明工地。5质量目标(1)交验工程质量达到国家、行业质量验收标准,符合设计文件和有关技术规范要求。(2)工程施工质量验收合格率达到100%,单位工程一次验收合格率100%。(3)无质量事故,无质量投诉,严格控制质量成本损失。(4)保证顾客满意,以良好的信誉和满意的服务保证与老客户保持稳定的战略合作伙伴关系。6建设单位XXXXXXXXXXXXXXXXXXXXXXXXXXXXXX7设计单位XXXXXXXXXXXXXXXXXXXXXXXXXXX公司8勘察单位XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX公司9监理单位XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX公司10施工单位XXXXXXXXXXXXXXXXXXXXXXXXXX公司1.2设计概况结构形式如下图:XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目2(轴5~15/轴D~F)地梁结构图XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目3(轴5~15/轴D~F)4.9m结构图XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目4(轴5~15/轴D~F)10.7m、15.5m结构图XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目5(轴5~15/轴D~F)屋面结构图XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目61-1剖面图XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目72-2剖面图1.3危大工程概况和特点本工程承插型盘扣式支撑架搭设至最大高度23.96m;按照《危险性较大的分部分项工程安全管理规定》建办质(2018)31号中附件2“超过一定规模的危险性较大的分部分项工程范围”第2.2条混凝土模板支撑工程:搭设高度8m及以上;搭设跨度18m及以上,施工总荷载15kN/㎡及以上;集中线荷载20kN/m及以上的工程施工单位应当组织专家对专项方案进行论证。本次论证部位:XXXXXXXXXXXX仓库(轴5~15/轴D~F)标高4.9米,10.7米,15.5米,斜屋面(23-23.64米)1.4施工要求和技术保证条件1.4.1施工要求考虑到施工工期、质量和安全要求,在选择方案时充分考虑了以下几点:XXXXXXXXXXXXXXXXXXXXXXXXXXXXX项目8(1)、模板及其支架的结构设计,力求做到结构要安全可靠,造价经济合理。(2)、在规定的条件下和规定的使用期限内,能够充分满足预期的安全性和稳定性(3)、选用材料时,力求做到常见通用、可周转利用,便于维修。(4)、模架选型时,力求做到受力明确,构造措施到位,搭拆方便,便于施工。(5)、屋面层为坡屋面,需做好防扭措施。1.4.2混凝土浇筑方式模板支设成型且经监理验收通过后,进行竖向结构结构浇筑,再进行横向结构浇筑。1.4.3支架基础情况本工程盘扣架搭设落地于10cm厚C15混凝土垫层上,支撑架立杆下部应有支座,支座下应铺设厚度50mm,宽度不小于200×200mm的通长垫板。搭设脚手架时进行弹线,弹出立杆间距、排距、与结构间距线。盘扣架架基础应平整,不得有积水,雨季施工设置排水沟,在距架体1m左右位置挖排水沟,沟深300mm,宽度500mm,及时将雨水排走。1.5技术保证条件本工程模架施工特点在于超限现浇屋面、梁,架体支撑高度较高。模板支撑设计尤为重要。同时,模板搭设质量必须保证,各管理人员、搭设人员、验收人员也要引起重视,需加强搭设过程的检查,防微杜渐,严格按照方案要求执行。因高大模板施工发生的坍塌事故很多,架体的弹性失稳控制是本工程的重点与难点。方案实施前必须严格按要求组织方案的专家论证,并按相关意见完善专项方案。并保证现场施工按方案进行。施工过程作好相关交底,并加强过程的监督控制,细化各个环节的验收工作,保证高大模板施工过程